Marbucco Corp. v. Suffolk Construction

CourtCourt of Appeals for the First Circuit
DecidedJanuary 28, 1999
Docket98-1651
StatusPublished

This text of Marbucco Corp. v. Suffolk Construction (Marbucco Corp. v. Suffolk Construction) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marbucco Corp. v. Suffolk Construction, (1st Cir. 1999).

Opinion

USCA1 Opinion
                 United States Court of Appeals

For the First Circuit

No. 98-1651

MARBUCCO CORP., d/b/a GRANITE STATE GLASS,

Plaintiff, Appellant,

v.

SUFFOLK CONSTRUCTION COMPANY, INC.,

Defendant, Appellee.

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF NEW HAMPSHIRE

[Hon. Paul J. Barbadoro, U.S. District Judge]

Before

Selya, Circuit Judge,

Campbell, Senior Circuit Judge,

and Lynch, Circuit Judge.

Matthew J. Lahey, with whom McLaughlin, Hemeon & Lahey, P.A.was on brief for appellant.
Lawrence M. Edelman, with whom Sanders & McDermott, P.L.L.C. and Patricia M. Weathersby were on brief for appellee.

January 25, 1999

CAMPBELL, Senior Circuit Judge. The principal issue in
this appeal is whether New Hampshire law requires a disappointed
bidder to demonstrate a private subcontractor's bad faith before
the bidder may recover lost profit damages under a theory of
promissory estoppel. The district court held that such a showing
was necessary in this case, and it instructed the jury accordingly.
We find no error in the court's instructions and therefore affirm.
Appellee Suffolk Construction Company, Inc., a
Massachusetts general building contractor, was awarded a contract
to build a new sports arena for the University of New Hampshire.
Suffolk invited nine glass suppliers to bid on a portion of the job
that required the fabrication and installation of some of the glass
products for the arena. Among these suppliers was Appellant,
Marbucco Corporation. Marbucco claimed that one of Suffolk's
agents had told Marbucco's Vice-President that Marbucco's bid would
be selected so long as it was the lowest. When Suffolk awarded the
subcontract to another glass supplier whose bid was higher than
Marbucco's, Marbucco sued in New Hampshire Superior Court, seeking
damages for its bid preparations costs and lost profits.
Suffolk removed the action to the district court based on
the parties' diversity of citizenship. By the time of trial,
Marbucco had abandoned its claim for bid preparation costs and
instead sought only lost profits, which it asserted to be
approximately $71,000. Upon conclusion of the evidence, the
district court provided the following instruction to the jury
regarding Marbucco's claim:
The Plaintiff is making a claim for damages based on what
is known as the doctrine of promissory estoppel. In
order to prove a claim of promissory estoppel the
plaintiff must [prove] by a preponderance of the evidence
that, one: the defendant's employee made a promise to the
plaintiff. Two: the defendant reasonably expected that
its employee's promise would cause the plaintiff to act
on the promise. Three: the plaintiff relied to its
detriment on the defendant's promise. Four: the
plaintiff's reliance on the promise was reasonable under
the circumstances. And five: the defendant acted in bad
faith.

Marbucco contends that the district court erred in
instructing the jury that bad faith was a necessary element of its
claim, limited, as it was, to lost profits. It contends, based on
the Supreme Court of New Hampshire's decision in Marbucco v. City
of Manchester, 632 A.2d 522 (N.H. 1993), that New Hampshire law
requires a plaintiff seeking lost profits under a promissory
estoppel theory to prove a defendant's bad faith only if the
defendant is a municipality. We do not read City of Manchester as
necessarily so limited. In that case, the New Hampshire court
faced what it characterized as a question of first impression:
whether a disappointed low bidder on a municipal contract could
recover money damages from the municipality for failure to award it
the contract, and if so, what measure of damages. See id. at 524-
25. The court ruled that damages could be recovered, noting that
"[m]unicipalities are generally subject to the same financial
consequences for their misconduct as private corporations." Id. at
24 (citation omitted). Regarding the appropriate measure of
damages, the court stated:
In the ordinary case, the damages that an unsuccessful
low bidder may recover should be limited to those it
sustained directly by reason of its justifiable reliance
upon the municipality's promise to award the contract to
the lowest responsible bidder submitting all essential
information prior to the bidding deadline, if it awarded
it at all. Hence, damages ordinarily should be limited
to the expenses incurred by the low bidder in its
fruitless participation in the competitive bidding
process, i.e, its bid preparation costs. To permit the
recovery of greater damages in such cases could drain the
public fisc in response to mere carelessness on the part
of low level government officials. If a disappointed low
bidder complies with all requirements of the bid
instructions but is deprived of the contract through some
conduct of the awarding authority tantamount to bad
faith, however, then the recovery of lost profits should
be the measure of damages.

Id. at 525 (citations omitted).
Marbucco places special emphasis on this passage in
arguing that the bad faith requirement applies only when the
defendant is a municipality. This, we think, conflates merely one
rationale animating the City of Manchester decision with the
holding of the case itself. To be sure, the City of Manchestercourt noted certain concerns when a municipal defendant is sued for
failing to award a competitive bid, e.g., the possibility of
damages "draining the public fisc" or the municipality's eroding
the "public confidence in government . . . [by acting] in bad
faith." See id. But these concerns can be understood as relating
to the particular circumstances pertaining to that case, not as
essential ingredients of the legal principle being applied. The
legal basis of City of Manchester was, we believe, the court's
recognition -- regardless whether the subcontractor was a public or
private entity -- that bid preparation costs are the "ordinary"
remedy for a promissory estoppel claim, leaving lost profits for
exceptional cases where bad faith (or something akin to bad faith)
is proven. The New Hampshire court cited to the Restatement
(Second) of Contracts in support of its determination that
justifiable reliance could give rise to a promissory estoppel claim
in the case of a disappointed bidder. See Restatement (Second) of
Contracts, 90, comment d, illustrations 8 & 9; City of
Manchester, 634 A.2d at 524. The Restatement makes no distinction
in this aspect of the law between public and private entities.
Indeed, it would be inconsistent with the court's earlier statement
that "[m]unicipalities are generally subject to the same financial

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Rule Industries, Inc.
878 F.2d 535 (First Circuit, 1989)
John S. Porter v. Harold Nutter
913 F.2d 37 (First Circuit, 1990)
United States v. Jesus Paredes-Rodriguez
160 F.3d 49 (First Circuit, 1998)
Murphy v. Financial Development Corp.
495 A.2d 1245 (Supreme Court of New Hampshire, 1985)
Marbucco Corp. v. City of Manchester
632 A.2d 522 (Supreme Court of New Hampshire, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Marbucco Corp. v. Suffolk Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marbucco-corp-v-suffolk-construction-ca1-1999.