Mar Tech Mechanical, Ltd. v. Chianelli Building Corp.

54 Va. Cir. 569, 2001 Va. Cir. LEXIS 223
CourtNorfolk County Circuit Court
DecidedMarch 6, 2001
DocketCase No. (Law) L00-2234
StatusPublished
Cited by1 cases

This text of 54 Va. Cir. 569 (Mar Tech Mechanical, Ltd. v. Chianelli Building Corp.) is published on Counsel Stack Legal Research, covering Norfolk County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mar Tech Mechanical, Ltd. v. Chianelli Building Corp., 54 Va. Cir. 569, 2001 Va. Cir. LEXIS 223 (Va. Super. Ct. 2001).

Opinion

By Judge Charles D. Griffith, Jr.

Plaintiff Mar Tech Mechanical is a subcontractor in the business of providing various services and materials for building projects. In its Motion for Judgment filed September 21, 2000, Plaintiff alleges it contracted with Defendant Chianelli Building Corporation (CBC), a general contractor, for woric to be performed on a public school project. Plaintiff has sued Defendant CBC under various theories and has also sued Defendant Liberty Mutual Insurance Company, which issued a payment bond for the project Defendants have filed demurrers to each count of the Motion for Judgment

Standards for Demurrer

A demurrer challenges the legal sufficiency of factual allegations and shall be granted if the plaintiff’s pleadings do not state a cause of action or fail to state facts upon which relief can be granted. Va. Code § 8.01-273 (Michie 1950); Fun v. Virginia Military Inst., 245 Va. 249, 427 S.E.2d 181 (1993). A demurrer admits the truth of all facts properly pleaded and all reasonable factual inferences fairly and justly drawn from the facts alleged must be considered in aid of the pleading. Fox v. Custis, 236 Va. 69, 372 S.E.2d 373 [570]*570(1988). Further, the Virginia Supreme Court has warned the trial courts against incorrectly short-circuiting litigation at the pretrial level by deciding the dispute without permitting the parties to reach a trial on the merits. CaterCorp, Inc. v. Catering Concepts, Inc., 246 Va. 22, 431 S.E.2d 277 (1993).

The fundamental rule of pleading is that the facts must be so stated as to fairly apprise the court and the defendant of the nature of the cause of action upon which the plaintiff relies. If the facts are sufficient in substance, but deficient in detail, the defendant’s remedy is not by demurrer, but by motion for a bill of particulars. Miller v. Grier S. Johnson, Inc., 191 Va. 768, 776, 62 S.E.2d 870, 874 (1951). Under the Rules of the Supreme Court, a pleading “shall state the facts on which the party relies in numbered paragraphs, and it shall be sufficient if it clearly informs the opposite party of the true nature of the claim or defense.” Sup. Ct. R. 1:4(d). On demurrer, a court may consider the substantive allegations of the pleading as well as any accompanying exhibit mentioned in the pleading. Flippo v. F & L Land Co., 241 Va. 15, 17, 400 S.E.2d 156 (1991).

Breach of Contract: CBC

Plaintiffs first count claims that Defendant CBC breached the subcontract by failing to pay Plaintiff for any work performed under the contract. See Motion for Judgment, ¶ 24. Specifically, Plaintiff alleges that Defendant CBC forced Plaintiff to cease working on the project for a period of time but did not allow Plaintiff a corresponding extension of time in order to complete the project. See Motion for Judgment, ¶ 17-18. Plaintiff alleges that because it could not complete the project by the agreed-upon date, Defendant CBC refused to pay for any work done on the project. See Motion for Judgment, ¶ 28-29.

Defendants have demurred to the breach of contract claim, alleging that Plaintiffs allegations constitute an attempt to recover under an implied covenant of the contract See Demurrer, ¶ A, 1-2. Defendants also allege that any such claims are prohibited because Plaintiff failed to meet certain conditions precedent under the subcontract, including notice and timeliness requirements. See Demurrer, ¶ A, 3-5. Defendants argue that in order for Plaintiff to properly plead a breach of contract Plaintiff must point to a specific contract section that was breached and may not rely on the allegation that Defendant CBC forced Plaintiff to cease work. See Brief in Support of Demurrer and Plea in Bar (Defendants’ Brief) at 3.

[571]*571Defendants’ own arguments undercut their assertion that the forced cessation of the project does not constitute a breach of contract. In their brief, Defendants argue that “Mar Tech quit work on the schools. The decision to do so was Mar Tech’s, not CBC’s. Ultimately, either Mar Tech’s quitting will be found justified or not. If justified, it may have a contractual remedy.” See Defendants’ Brief at 3 (emphasis in original). Defendants have thus pointed out the crucial discrepancy of fact in this case, whether Plaintiff’s work cessation was or was not voluntary, and have correspondingly conceded that Plaintiff may have a contractual remedy.

Additionally, specific contract sections govern the alleged work cessation and may provide a basis for Plaintiff’s recoveiy. The Subcontract Agreement provides:

Article II. The Contract Documents — The terms and provisions of this Agreement with respect to the work to be performed and furnished by the Subcontractor hereunder are intended to be and shall be in addition to and not in substitution for any of the terms and provisions of the General Contract and the other Contract Documents.

The General Contract, which governs this dispute by virtue of Article II of the Subcontract Agreement, states:

8.3. Delays and Extensions of Time 8.3.1. If the Contractor is delayed at any time in progress of the Work by an act or neglect of the Owner or Architect, or of an employee of either, or of a separate contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Contractor’s control, or by delay authorized by the Owner pending arbitration, or by other causes which the Architect determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Architect may determine. [Emphasis added.]

Defendants concede that the terms of the General Contract are incorporated into the Subcontract in their own brief. See Defendants’ Brief at 4 (“Articles I, II, and XIX [of the Subcontract] incorporate the General Conditions of the contract between the Owner and CBC____”). Because the General Contract compels extensions of time when work orders are altered, Plaintiff has sufficiently pleaded a breach of the contract by alleging Defendant CBC forced the work to stop and then disallowed a work extension.

[572]*572 Violation of Va. Code § 11-62.11: CBC

Va. Code § 11-62.11 requires all construction contracts awarded by divisions of the state government to include certain payment provisions. Specifically, the code section requires contracts to contain provisions requiring a contractor to, within seven days after receipt of funds from the agency, either pay a proportionate share to subcontractors or to notify the agency and subcontractor in writing of its intention to withhold such payment. See Va. Code § 11-62.11. Plaintiff alleges that because this provision does not appear in the subcontract, it has a private right of action sounding in breach of contract under the statute against Defendant CBC. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enomoto v. Space Adventures, Ltd.
624 F. Supp. 2d 443 (E.D. Virginia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
54 Va. Cir. 569, 2001 Va. Cir. LEXIS 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mar-tech-mechanical-ltd-v-chianelli-building-corp-vaccnorfolk-2001.