Maplewood Planing Mill & Stair Co. v. Pennant Construction Co.

344 S.W.2d 629, 1961 Mo. App. LEXIS 642
CourtMissouri Court of Appeals
DecidedMarch 21, 1961
DocketNo. 30487
StatusPublished
Cited by6 cases

This text of 344 S.W.2d 629 (Maplewood Planing Mill & Stair Co. v. Pennant Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maplewood Planing Mill & Stair Co. v. Pennant Construction Co., 344 S.W.2d 629, 1961 Mo. App. LEXIS 642 (Mo. Ct. App. 1961).

Opinion

OWEN, Special Judge.

Appellant Justice D. Zahner recovered judgment in the circuit court of the City of St. Louis on July 28, 1959, for $3,552.89 against Pennant Construction Company but was denied a lien against premises owned by respondent Sophia Fox Kenamore, located at 5297 Washington Boulevard and 608 Union Boulevard in the City of St. Louis, on which appellant, a painting contractor, had done work and furnished materials at the request of the president of the Pennant Construction Company, general contractor. The general contract between Pennant Construction Company and Sophia Fox Kenamore,' owner of record and her late husband, Dr. Bruce D. Kenamore, was entered into in August, 1955. Dr. Kena-more died on March 29, 1957. According to his agreement with Pennant Construction Company, appellant was to receive compensation on the basis of the prevailing rate for painters ($3.65 per hour) for-time spent on the job by him and his helpers in addition to reimbursement for materials furnished. Some work was done by-appellant on October 14, 1955, consisting-of priming windows and then on November 18, 1955, the work of painting began and was concluded on or about March 15,. 1956. Total charge by appellant for labor and materials on this job according to his. mechanic’s lien and his petition was $4,-200.38 and payments were made on the account of $730 on December 3, 1955, $414. on February 13, 1956 and $132.20 on March 15, 1956, said payments totalling $1,276.20-leaving a balance due of $2,924.18. Mechanic’s lien was filed on June 14, 1956 for-this amount with the Clerk of the Circuit. Court in St. Louis.

On August 31, 1956, appellant filed his. petition to enforce mechanic’s lien in the Circuit Court of St. Louis against Pennant. Construction Company and Sophia Fox. Kenamore alleging that Pennant Construction Company is justly indebted to him in. the sum of $2,924.18 for materials furnished and work and labor done by plaintiff at the special instance and request of" defendant, Pennant Construction Company,., in painting and redecorating the building - owned by Sophia Fox Kenamore, averring-the demand became due on March 15, 1956 - and that within four months thereafter • plaintiff filed said account with the Clerk-of the Circuit Court, on June 14, 1956, and.. [631]*631that more than ten days prior to filing said account, and on May 24, 1956, plaintiff gave Sophia Fox Kenamore notice in writing that he held a claim against said building.

On December 12, 1956, appellant filed a motion in the Circuit Court to consolidate his cause with another suit which had been previously filed by Maplewood Planing Mill and Stair Company, an action in equity for the determination and enforcement of a mechanic’s lien against the same parties, but in which appellant had not been joined. The motion was sustained and the causes were consolidated on March 16, 1957. This -consolidation has no effect upon this appeal, as this cause was tried independently of the other cause and separate judgment was entered.

On November 3, 1958, defendant Sophia Fox Kenamore, filed her answer, stating that she had no information concerning any indebtedness of Pennant Construction Company for work claimed to have been performed by plaintiff between October 14, 1955 and February 3, 1956, but asserting that the time worked by plaintiff appellant on February 6, 1956, and subsequently was under a separate contract between plaintiff appellant and Bruce D. Kenamore and that on February 3, 1956, plaintiff had abandoned his claimed contract with Pennant Construction Company and that the credits of $414.00 on February 13, 1956 and $132.20 on March 15, 1956, were paid to plaintiff appellant by Bruce D. Kenamore under a separate contract between plaintiff and Dr. Kenamore; that plaintiff appellant has attempted to hook the work performed on and after February 6, 1956, under separate contract with Dr. Kenamore on to his lien statement against Pennant Construction Company unlawfully and for the sole purpose of claiming to have filed a mechanic’s lien within the statutory period allowed by the laws of the State of Missouri; and that the lien is barred under the statutes and unenforceable.

Pennant Construction Company did not file any pleadings and was not represented at the trial. The question for determination here is whether appellant was entitled to a lien against the property of Sophia Fox Kenamore.

It appears from the evidence that appellant had been paid $730 by Pennant Construction Company on December 23, 1955, for a bill rendered on December 10, 1955. On January 3, 1956, he sent a bill for $817.-60 to Pennant and another for a like amount on January 20, 1956, and another for $642.40 on February 4, 1956. His bill for materials, sent to Pennant on March 15, 1956, was for $652.58. These bills were not paid. On February 13, 1956, he received $414.00 and on March 15 (or 23), 1956, he received $132.20. Both of these bills were paid by Dr. Kenamore. These two bills are for labor performed on February 6, 7, 8, 9 and 10 and March 12, 13, 14 and 15 (or March 20, 21, 22 and 23), 1956, a total of 148 hours at $3.65 per hour and in addition $6 for a gallon of paint plaintiff appellant had purchased.

Plaintiff appellant, during the trial, testified that he informed Mr. Anderson, President of the Pennant Construction Company and Dr. Kenamore that he was going to quit on February 3, 1956. While he testified at the trial tha.t he expected Pennant Construction Company to pay for work performed after that date he was confronted with testimony in his deposition that he expected to be paid by Dr. Kena-more for the work performed after February 3, 1956. He admitted -he had so testified. Offered in evidence was a copy of a bill from plaintiff appellant to Dr. Kena-more dated March 23, 1956, for $132.20 which is noted “Paid 3/23/56 J.D.Z.” Plaintiff testified that materials purchased during the time he was working under the agreement with Pennant Construction Company were used on and after February 6, 1956.

There is some question concerning whether the last four days of work were on March 12, 13, 14 and 15 or March 20, 21, 22 and 23 but it would appear the latter [632]*632is correct because the receipted bill offered in evidence shows these days and appellant admitted he did not work both weeks. And this bill contains an item for $24 for the balance on a previous bill for which he received payment. This bill is addressed to Dr. Kenamore and it appears to us the reference to a previous bill would serve to establish, inasmuch as it was paid by Dr. Kenamore, that the-prior bill was likewise addressed to him.

We feel that the evidence reasonably establishes the fact that appellant did abandon his contract or agreement with Pennant Construction Company on February 3, 1956, and that any work he did after that date was not done for Pennant Construction Company. Strengthening this conclusion is the fact that the bills rendered by him to Dr. Kenamore on February 13, 1956, for $414.00 and March 23, 1956, for $132.20 were paid by Dr. Kenamore on the dates presented. And on the bill dated March 23, 1956, there is the notation “Balance on previous bill — $24.00.” It is established that the bill of February 13, 1956, should have been for $438. At the time of the rendering of the first bill to Dr. Kenamore there was owing the appellant from Pennant Construction Company for labor and materials, a balance of y2,930.18, none of which is' mentioned on the bill from appellant to Dr. Kenamore which was offered in evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Soper v. Bopp
990 S.W.2d 147 (Missouri Court of Appeals, 1999)
Nachtweih v. Maravilla
861 S.W.2d 164 (Missouri Court of Appeals, 1993)
Jenni v. E.R.B. Land, Inc.
541 S.W.2d 743 (Missouri Court of Appeals, 1976)
Null v. Gray
534 S.W.2d 823 (Missouri Court of Appeals, 1976)
DeMott v. Dillingham
512 S.W.2d 918 (Missouri Court of Appeals, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
344 S.W.2d 629, 1961 Mo. App. LEXIS 642, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maplewood-planing-mill-stair-co-v-pennant-construction-co-moctapp-1961.