Mapco, Inc. v. Williams

581 S.W.2d 402, 1979 Mo. App. LEXIS 2309
CourtMissouri Court of Appeals
DecidedApril 2, 1979
DocketNo. KCD 29763
StatusPublished
Cited by10 cases

This text of 581 S.W.2d 402 (Mapco, Inc. v. Williams) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mapco, Inc. v. Williams, 581 S.W.2d 402, 1979 Mo. App. LEXIS 2309 (Mo. Ct. App. 1979).

Opinion

WASSERSTROM, Judge.

Mapco, Inc. initiated this litigation in January, 1977, by its petition to condemn a fifty foot easement on defendants’ land upon which Mapco had already implanted its pipelines in the summer of 1976. The landowner defendants answered to the condemnation petition and counterclaimed for ejectment. The trial court held a hearing on Mapco’s petition, following which defendants filed a motion to dismiss Mapco’s cause of action. The trial court sustained that motion and ordered the ruling be final for purposes of appeal. This appeal by Mapco promptly followed.

The major operative facts are not in dispute. In 1974, preparatory to construction of the proposed Smithville Reservoir and Dam by the United States Corps of Engineers, the Corps and Mapco entered into discussions relative to the relocation of an eight inch and a ten inch pipeline already in place on a private easement owned by Map-co. The purpose of the relocation would be to accommodate the proposed lake which would be created by the dam. In the course of those discussions, which were conducted on behalf of Mapco by its Chief Pipeline Engineer Leiber, the Corps produced a map identified in evidence as Exhibit No. 4. Mapco eventually acceded to a relocation route desired by the Corps which was marked upon Exhibit No. 4. Exhibit No. 4 also showed the boundaries of existing right of way owned by the Corps, and the route of the agreed relocation of the Mapco two pipelines was shown to be entirely within the Corps’ existing right of way without intruding upon any neighboring private property.

In 1975, Mr. Leith B. Watkins came to work for Mapco as an Engineer and succeeded to the primary duties of carrying out the relocation project. During 1975, he had occasion to use Exhibit No. 4 for the purpose of preparing certain cost estimates. However, as the project neared the signing of a contract and actual performance of the work, Watkins requested additional topographic maps of the area and the Corps did furnish such maps to Watkins, one of which was identified in evidence as Exhibit No. 7. From that point on, Watkins proceeded to work with Exhibit No. 7 for survey purposes in the laying out of the route to be staked by the surveyors on the ground. Unfortunately, Exhibit No. 7 did not as furnished by the Corps reflect the boundary of the Corps’ existing right of way, and Watkins through error laid out a route for the pipeline relocation which encroached 580 feet on defendants’ land. Watkins submitted to the Corps an “alignment sheet” which showed the exact relocation route as prepared by him and which was attached to the construction specifications. Apparently the alignment sheet was not objected to nor called to Watkins’ attention for correction.

A contract covering the relocation work was executed by the Corps and Mapco on April 1, 1976. Mapco was to be reimbursed for expenses in the sum of $830,000, none of which was for the purpose of acquiring any additional right of way. The route of the relocated line was designated on Exhibit C attached to the contract, and it was the same as that on Exhibit No. 4 in that the route indicated passed south of and did not touch defendants’ property.

Watkins testified that he at all times intended to relocate the pipelines entirely on government property and that he was unaware during the preparation of Exhibit No. 7 and the doing of the actual work that the relocation would go outside the Corps’ existing right of way. He also testified that if he had been aware that the final relocation route passed onto private property, he would have modified the route so as to avoid that result.1 Mapco first became [405]*405aware that the final relocation route was on defendants’ property only after the relocation project had already become completed. At that point, in response to a demand by defendants’ attorney that the pipelines be removed from defendants’ land, Mapco offered to purchase a fifty foot easement for $3,000. Defendants rejected that offer, but stated they were willing to sell for $25,000. Mapco found the counteroffer unacceptable and instead filed this suit for condemnation under Section 523.010, RSMo 1969.

As with respect to the basic facts outlined above, so also the parties agree as to the following basic legal principles which serve to mark out and limit the battleground of this litigation: (1) The questions of whether the taking of any given private property is “necessary” for the condemnor’s purpose and the extent and exact location of the property to be taken are matters for political or legislative determination which have been delegated to the condemning authority by virtue of the statute granting the right of eminent domain. Kansas & T. Coal Ry. Co. v. Northwestern Coal & Mining Co., 161 Mo. 288, 61 S.W. 684 (banc 1901); American Tel. & Tel. Co. v. St. Louis, I. M. & S. Ry. Co., 202 Mo. 656, 101 S.W. 576 (1907); State ex rel. State Highway Commission v. Curtis, 359 Mo. 402, 222 S.W .2d 64 (Mo. banc 1949); State ex rel. Coffman v. Crain, 308 S.W.2d 451 (Mo.App. 1958).2 (2) The courts may inquire into those questions relating to “necessity” only if the protesting landowner alleges and proves that the condemnor’s claim of necessity constitutes fraud, bad faith or an arbitrary and unwarranted abuse of discretion. State ex rel. State Highway Commission v. Curtis, supra; State ex rel. Coffman v. Crain, supra; Phillips Pipe Line Co. v. Brandstetter, 241 Mo.App. 1138, 263 S.W.2d 880 (1954).

It is with respect to the application of the second rule just stated to the facts of this case that the parties part company. Defendants insist that Mapco could have relocated the pipeline solely on government land, that the contract for relocation so contemplated, that Mapco itself so intended, and that its failure to do so must be considered an abuse of discretion. The trial court so concluded, stating: “Under the facts as stated above, plaintiff’s unlawful action in relocating its pipelines on defendants’ land instead of on government ground constitutes an unwarranted abuse of discretion in its determination of necessity to acquire an easement from defendants. * * Any claim by plaintiff that present necessity now exists as a result of its mistake in relocation is disallowed as being in bad faith in light of the above-stated facts.”

Those conclusions by the trial court cannot stand in light of the facts that the relocation had already been completed at the time the petition for condemnation was filed, that the improvement is one of a permanent nature, and that it is devoted to a public purpose. Under these circumstances, Mapco must be permitted to acquire the necessary rights to preserve the improvement in question even though the installation was originally accomplished by virtue of a trespass.

The governing principle is ruled by Harris v. L. P. and H. Construction Co., 441 S.W.2d 377 (Mo.App.1969). In that case a telephone utility entered upon plaintiffs’ land without legal authority, cut down trees and erected telephone lines. The plaintiff landowners brought suit in two counts, the first of which sought statutory damages for trespass and the second prayed ejectment and damages. The defendant utility assert[406]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Relaxation, Inc. v. RIS, Inc.
452 S.W.3d 743 (Missouri Court of Appeals, 2015)
Group v. Level 3 Communications, L.L.C.
111 S.W.3d 492 (Missouri Court of Appeals, 2003)
City of Kansas City v. Hon
972 S.W.2d 407 (Missouri Court of Appeals, 1998)
State ex rel. Rantz v. Sweeney
901 S.W.2d 289 (Missouri Court of Appeals, 1995)
Pogue v. Associated Electric Cooperative, Inc.
760 S.W.2d 169 (Missouri Court of Appeals, 1988)
City of Blue Springs v. Central Development Ass'n
684 S.W.2d 44 (Missouri Court of Appeals, 1984)
Barr v. Kamo Elec. Corp., Inc.
648 S.W.2d 616 (Missouri Court of Appeals, 1983)
Wright v. Edison
619 S.W.2d 797 (Missouri Court of Appeals, 1981)
Shaw v. Burlington Northern, Inc.
617 S.W.2d 455 (Missouri Court of Appeals, 1981)
Missouri Public Service Co. v. H & W Investment Co.
602 S.W.2d 41 (Missouri Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
581 S.W.2d 402, 1979 Mo. App. LEXIS 2309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mapco-inc-v-williams-moctapp-1979.