Manzano Oil Corp. v. Chesapeake Operating, Inc.

178 F. Supp. 2d 1217, 2001 WL 1661628
CourtDistrict Court, D. New Mexico
DecidedAugust 27, 2001
Docket00-178-WWD/KBM
StatusPublished
Cited by2 cases

This text of 178 F. Supp. 2d 1217 (Manzano Oil Corp. v. Chesapeake Operating, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manzano Oil Corp. v. Chesapeake Operating, Inc., 178 F. Supp. 2d 1217, 2001 WL 1661628 (D.N.M. 2001).

Opinion

MEMORANDUM OPINION AND ORDER

DEATON, United States Magistrate Judge.

This matter comes before the Court upon Defendant’s Motion for Partial Summary Judgment filed July 27, 2001 (Doc. 28). Plaintiffs oppose the motion. Defendant (“Chesapeake”), seeks a declaratory judgment on an oil and gas lease finding that Defendant took action necessary under the lease to extend the primary term beyond its expiration date. For reasons discussed below I find that Defendant did take such action as was necessary to extend the term of the lease.

*1218 BACKGROUND

Plaintiffs and Defendant filed Agreed Stipulations with the Court on November 2, 2000. Unless otherwise indicated, facts asserted in this portion of the opinion are derived from the Agreed Stipulation. Information set out in the “Statement of Additional Material Facts” portion of Defendant’s Brief in Chief which is not disputed will be treated as undisputed facts and relied on in this opinion. When this information is used it will be identified by its source (“AMF” for Additional Material Facts) and the paragraph number; viz., AMF¶ 2.

Weslynn McCallister Howay as lessor, executed an Oil and Gas Lease (“the Lease”) dated August 3, 1995, in favor of Defendant as lessee covering certain lands. Howay and Defendant executed an Agreement to Amend Oil and Gas Lease to Correct Legal Description dated September 24,1996.

Howay as lessor executed an Oil and Gas Lease (“the Top Lease”) dated December 8, 1997, in favor of Plaintiff Magnolia Royalty Company, Inc. (“Magnolia”), lessee, for the identical property described in the lease dated August 3, 1995. On April 13, 1998, Magnolia conveyed overriding royalty interests in the Top Lease to certain individuals and other entities, most, if not all, of whom are Plaintiffs in this law suit. On June 1, 1997, one of those corporate entities and two individuals, by assignments and conveyances, conveyed one-half of their respective interests in the Top Lease to Manzano Oil Corporation, the first named Plaintiff in this law suit.

In May of 1998, Defendant employed a surveyor to survey and prepare a well location, and the property surveyed was within the Lease. AMF¶ 2-4. Defendant could not drill on the Lease land without obtaining a zoning variance, and it did not attempt to obtain a variance in connection with the Lease land. AMF¶ 5.

On May 22, 1998, Defendant purchased a three acre parcel of land adjoining the Leased Lands in order to directionally drill a well from the surface of the purchased parcel to a producing formation within the Leased Lands. Defendant had been advised by the City Manager of Lov-ington, Bob Carter, that a variance would not be granted on the Lease land because of its proximity to a residential area containing “baseball fields and different things.” AMF¶ 7. Defendant had worked with Bob Carter before and believed, from experience, that absent Carter’s approval, any application for a variance would fail. AMF¶ 6. On May 28, 1998, Defendant petitioned the zoning authority of the City of Lovington to obtain a special permit or variance to permit the drilling contemplated above on the purchased land, and the City of Lovington granted the variance related to the “Warehouse 10-1 [directional] well” on June 29, 1998. The City of Lovington requested that Defendant delay drilling the well until after the City’s Fourth of July celebration which was being held in a park next to the drill site. AMFt 14. On May 29, 1998, Defendant sought a permit to drill the Warehouse 10-1 well from the New Mexico Oil Conservation Division. Counsel for Plaintiff Bahlburg Exploration, Inc., wrote to the New Mexico Oil Conservation Division to request that the Division “not permit the drilling of the well prior to Chesapeake (sic.)[Defendant’s] receiving all necessary regulatory approvals.” AMF¶ 11. Plaintiff Bahlburg Exploration filed a protest of Defendant’s application to the Oil Conservation Division (“Division”) requesting that the Division refrain from granting Defendant preliminary approval to drill the well. AMF¶ 16. Defendant sent its directional drilling plan to the Division on *1219 June 12, 1998; and the application for permit to drill was approved June 17, 1998. Effective July 9, 1998, Defendant, Plaintiff Corporations and others entered into a Drilling Development Agreement on the property in the lease.

The Warehouse 10-1 well was spudded on July 27, 1998 on the three acre parcel aforementioned; and on August 12, 1998, the drill bit penetrated the subsurface of the land in the Lease. In a letter to Defendant dated October 13, 1998, counsel for the Non-Operators (now Plaintiffs) on the Lease informed Defendant, inter alia, that “the captioned lease [the Lease] has expired due to the fact that no drilling operations were being conducted on, and there was no production from, the lands covered by the lease or lands pooled therewith at the expiration of its primary term.” A copy of the Top Lease was included in the letter. Defendant’s cumulative costs incurred in drilling the Warehouse 10-1 well totaled $245,071 as of August 3, 1998, the date the three year Lease expired.

DISCUSSION.

The question presented in the Defendant’s Motion for Partial Summary Judgment is whether, as a matter of law, Defendant Chesapeake Operating, Inc., as lessee, took action necessary under the Lease dated August 3, 1995, to extend the primary term of that Lease beyond its August 3, 1998, expiration date. In addition to seeking a dismissal with prejudice of Plaintiffs Complaint, Defendant also requests that the Court grant partial summary judgment on its counterclaim seeking a declaration that the lease is still in effect. See Amended Ans. & Counterclaim, Count I, “Declaratory Judgment”.

Summary judgment issues only where there is no genuine dispute as to a material fact and the moving party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Moya v. United States, 35 F.3d 501, 503 (10th Cir.1994). Summary judgment is appropriate where no facts are in dispute, but only the legal significance of the facts, which is the case here. See Rummel v. Lexington Ins. Co., 123 N.M. 752, 758, 945 P.2d 970 (1997).

Paragraph five of the Lease provides, in pertinent part, that Defendant, the lessee, is “granted the right... to pool or combine this lease, the land covered by it or any part or horizon thereof with any other land, leases, mineral estates or parts thereof for the production of oil or gas.” Paragraph five also contains the following language, to wit:

Drilling operations on or production from any part of any such unit shall be considered for all purposes, except the payment of royalty, as operations conducted upon or production from the land described in this lease. (Emphasis supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neuhard v. Range Resources-Appalachia, LLC
29 F. Supp. 3d 461 (M.D. Pennsylvania, 2014)
Anderson v. Hess Corp.
649 F.3d 891 (Eighth Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. Supp. 2d 1217, 2001 WL 1661628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manzano-oil-corp-v-chesapeake-operating-inc-nmd-2001.