Manuel F. Spencer & Son, Inc. v. Commonwealth

450 N.E.2d 1105, 16 Mass. App. Ct. 290, 1983 Mass. App. LEXIS 1389
CourtMassachusetts Appeals Court
DecidedJune 30, 1983
StatusPublished
Cited by1 cases

This text of 450 N.E.2d 1105 (Manuel F. Spencer & Son, Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manuel F. Spencer & Son, Inc. v. Commonwealth, 450 N.E.2d 1105, 16 Mass. App. Ct. 290, 1983 Mass. App. LEXIS 1389 (Mass. Ct. App. 1983).

Opinion

Kaplan, J.

Our main task on these appeals is to make our way through their procedural entanglements. At the end of the trail lie a few narrow substantive questions.

We begin with a bare sketch of the facts. 2 The Commonwealth contracted with Ashland Oil, Inc. (Ashland), for the reconstruction of an eleven mile stretch of Route 3 from Duxbury to Plymouth. Ashland, as general contractor, entered into two contracts, dated March 15 and June 30,1978, with Manuel F. Spencer & Son, Inc. (Spencer), as subcontractor, by which the latter was to do certain drainage work.

*292 The venture required cooperation between the two companies. Spencer was to install subsurface drainage structures, then Ashland was to pave them over with a layer of gravel topped by a layer of bituminous concrete. The next step was for Spencer to dig through these layers in order to do further work connected with the drainage structures and to lay manholes, grates, and other openings at the road level. The joint effort apparently broke down in the summer of 1978. Ashland began to omit the gravel layer in favor of the concrete, which increased Spencer’s burden in reaching the drainage structures and carrying out the other jobs of the second stage of its work. Further, Ashland, in order to expedite its own work, required Spencer on various occasions at considerable expense to discontinue operations and relocate. Around March, 1979, Ashland commenced withholding payments due to Spencer on the ground, apparently, that Spencer was not fulfilling its obligations, and this in turn caused Spencer to fail in its duty under the subcontracts to make payments of “health and welfare benefits contributions” to its employees’ union. On April 9, 1979, Ashland cancelled the subcontracts — unjustifiably, as Spencer claimed.

Here began some procedural sorties. Spencer, under the statute providing in given situations for direct payment by awarding authorities to subcontractors (G. L. c. 30, § 39F), made demand on the Commonwealth by letter of August 28, 1979 (with copy to Ashland) for $97,343.03 as the balance owing to it in connection with the subcontracts. The demand was considered by the responsible Commonwealth department to be insufficient under the statute for lack of a breakdown of items (see § 39F[l][d]). Ashland responded by a letter of September 6, 1979, to the Commonwealth (copy to Spencer) which was considered to be insufficient for the same reason (it was also unsworn). 3 The Commonwealth did not make direct payment. 4

*293 To enforce its alleged direct-payment claim, Spencer brought suit against the Commonwealth in Superior Court on October 3, 1979 (see § 39F[4]). When the Commonwealth answered, raising among other things the inadequacy of Spencer’s demand, Spencer moved for summary judgment. At this point, Ashland, a nonparty, moved in the action to be added as a party under Mass.R.Civ.P. 19(a), 365 Mass. 765 (1974) (“Persons to be Joined if Feasible”), asserting that it owed nothing to Spencer and that it might suffer prejudice if the action were carried on in its absence. The judge denied Ashland’s motion, pointing to the statement in § 39F(4), as inserted by St. 1972, c. 774, § 2: “A subcontractor shall enforce a claim for direct payment ... by a petition in equity in the superior court against the awarding authority and the general contractor shall not be a necessary party” (emphasis supplied). 5 He also denied without prejudice a supplementary oral motion by Ashland to intervene in the action under Mass.R.Civ.P. 24(a), 365 Mass. 769 (1974) — this on the ground that Ashland had not tendered the pleading required for intervention by Mass. R.Civ.P. 24(c), 365 Mass. 770 (1974). The judge likewise denied, without prejudice, Spencer’s motion for summary judgment, mentioning the insufficiency of Spencer’s demand letter.

Instead of perfecting its motion to intervene in Spencer’s action, Ashland on June 11, 1980, commenced an action in Superior Court against Spencer, praying a declaration of the rights and duties of the parties. A second judge, viewing the actions of Spencer vs. Commonwealth and Ashland vs. Spencer 6 as companions, led the parties to prepare a *294 single “statement of the issues” in both actions in lieu of an elaboration of the pleadings.

The two actions were tried to a third judge sitting without a jury. Although the actions were in fact tried together rather than in sequence, no order of consolidation was entered. The Commonwealth was early excused from participating since it expressed no preference as between Spencer and Ashland. Evidence was taken for eight days. The judge made findings, rulings of law, and order for judgment in Ashland vs. Spencer to the effect that Ashland was not justified in terminating Spencer and was, instead, itself guilty of breaches of its duties toward Spencer in respect of both the physical performance and the withholding of payments; that Ashland was liable to Spencer in the amount of $78,252.13; and that Ashland had no claim against Spencer. Correspondingly, in Spencer vs. Commonwealth the judge held for Spencer against the Commonwealth in the same amount. Ashland’s motion for a new trial in Ashland vs. Spencer was denied. It moved again (after judgment) to intervene in Spencer vs. Commonwealth and that motion was also denied.

Thereafter, on May 21,1981, Ashland sued the Commonwealth in Superior Court alleging that it had substantially completed its contract; that the Commonwealth had accepted the work; and that a balance of $78,252.13 was due it, for which it prayed judgment. A motion by the Commonwealth to dismiss, reciting res judicata as a ground, was denied, but a fourth judge finally allowed summary judgment in the Commonwealth’s favor on that ground (adding that Ashland had made an inadequate response to Spencer’s demand).

The following matters are before us. In Spencer vs. Commonwealth, the Commonwealth has waived appeal, but we have a purported appeal by Ashland from the judgment for Spencer, with Ashland also claiming error in the denial of its joinder motion under rule 19(a) and its motions *295 to intervene under rule 24(a). 7 In Ashland vs. Spencer, Ashland appeals from the judgment for Spencer and the denial of its new trial motion. 8 In Ashland vs. Commonwealth, Ashland appeals from the judgment.

Ashland offers a farrago of legal arguments but they do not come to much. It reasserts that Spencer’s demand was faulty, while apparently minimizing the troubles with its own response. The Commonwealth, having once taken the position that Spencer’s demand was inadequate, now, in its brief to this court argues the contrary and criticizes Ashland’s response. 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marhefka v. Zoning Board of Appeals of Sutton
947 N.E.2d 1090 (Massachusetts Appeals Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
450 N.E.2d 1105, 16 Mass. App. Ct. 290, 1983 Mass. App. LEXIS 1389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manuel-f-spencer-son-inc-v-commonwealth-massappct-1983.