Manning, Maxwell & Moore, Inc. v. American Can Co.

182 A.D. 709, 169 N.Y.S. 713, 1918 N.Y. App. Div. LEXIS 7903

This text of 182 A.D. 709 (Manning, Maxwell & Moore, Inc. v. American Can Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manning, Maxwell & Moore, Inc. v. American Can Co., 182 A.D. 709, 169 N.Y.S. 713, 1918 N.Y. App. Div. LEXIS 7903 (N.Y. Ct. App. 1918).

Opinion

Shearn, J.:

The defendant counterclaims for breach by the plaintiff of a written contract between the parties for the manufacture by the plaintiff and the purchase by the defendant of 750,000 complete sets of shrapnel fuse parts to be delivered to the defendant “as rapidly as possible,” delivery to be “ completed on or before February 1, 1917.” It is alleged that plaintiff “ did not continue to deliver to the defendant said shrapnel fuse parts as rapidly as possible,' but wholly failed and neglected so to do and did not deliver to defendant prior to February 1, 1917, more than 108,000 complete sets of such parts.” Also that plaintiff “ was guilty of gross and inexcusable negligence, bad faith and wrongful conduct in connection with the manufacture and delivery of said shrapnel fuse parts, did not use its best efforts in good faith to manufacture and deliver said shrapnel fuse parts as rapidly as possible, and caused and permitted unnecessary and inexcusable delays in the manufacture and delivery thereof; ” that “ by reason of the neglect and failure of the plaintiff in performing said agreement and making delivery of shrapnel fuse parts as pro[711]*711vided therein, the defendant has been damaged to the extent of one million six hundred thousand dollars ($1,600,000).” The Special Term granted in part plaintiff’s motion for a bill of particulars of this counterclaim and denied it in part. The particulars sought were nineteen in number. All were granted except 1, 4, 5, 8, 9, 10 and 12, which were denied. Both parties appeal.

No. 1 was properly denied because it is covered by the allegation of failure to deliver more than 108,000 complete sets of the parts as rapidly as possible, and the claim showing wherein it was possible to make earlier deliveries is covered by the other particulars of the claim which the court ordered the defendant to furnish.
No. 2 should be modified so as to call only for a general description of the shrapnel fuse parts that plaintiff did not continue to deliver as rapidly as possible. It would be a burdensome and unnecessary requirement to specify each of the parts separately, running perhaps into thousands.
No. 3 should not have been granted, for not only does the plaintiff know how many complete sets were delivered but the' defendant has sufficiently indicated its claim by specifying that not more than 108,000 were’ delivered.
Nos. 4, 5, 8 and 9 should have been granted. These call for particulars of defendant’s claim of negligence and bad faith in connection with the manufacture and delivery. .These allegations cannot be regarded as superfluous, for the contract was to deliver as rapidly as possible and where defendant claims gross negligence and bad faith as the cause for the delay in deliveries, the plaintiff is clearly entitled to have these generalities made specific so that the issues will be limited and it will know what to meet. For the same reasons Nos. 6 and 7 were properly granted.
No. 10 was improperly denied. It goes to the heart of defendant’s claim of negligence; it does not call for evidence but is calculated to make definite the claim and limit the proof.
No. 11 was properly granted so that it may appear whether the delays were substantial and so that the plaintiff may be apprised of the claim. For the same reason No. 12 was improperly denied.
Nos. 13 to 19, inclusive, call for (in different terms) [712]*712specifications of items of damage. In our opinion all of these requirements were improper and unnecessary because there is no allegation or claim of special damage.

The order should be modified in accordance herewith, and as modified affirmed, without costs.

Clarke, P.. J., Laughlin, Dowling and Smith, JJ., concurred.

Order modified as stated in opinion, and as modified affirmed, without costs. Order to be settled on notice.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
182 A.D. 709, 169 N.Y.S. 713, 1918 N.Y. App. Div. LEXIS 7903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manning-maxwell-moore-inc-v-american-can-co-nyappdiv-1918.