Mann v. Wilson

1926 OK 437, 246 P. 464, 117 Okla. 239, 1926 Okla. LEXIS 786
CourtSupreme Court of Oklahoma
DecidedMay 4, 1926
Docket16254
StatusPublished
Cited by8 cases

This text of 1926 OK 437 (Mann v. Wilson) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mann v. Wilson, 1926 OK 437, 246 P. 464, 117 Okla. 239, 1926 Okla. LEXIS 786 (Okla. 1926).

Opinion

Opinion 'by

THOMPSON, O.

This is an appeal from a judgment of the district court of Kay county, Okla., setting aside a former judgment in this cause and granting a new trial on petition of E. E. Wilson, receiver for the Junction Oil & Gas Company, a corporation (Walter Franks successor of E. E. AVilson, receiver), and A. H. Woods, defendants in error, defendants in the original action, against AV. K. Mann, plaintiff in error, plaintiff in the original action, he having obtained said original judgment in the trial of the cause.

The plaintiff in error, AV. K. Mann, will be referred to in this opinion as plaintiff, and the defendants in error as defendants, as they appeared in the original action.

On the 5th day of April, 1921, the plaintiff filed his action against the defendants to recover the sum of $15,740, claimed to be due upon written contract with defendants to drill an oil well for them. The written contract was attached to the petition and made a part thereof as though set out at length therein. The contract was in the usual form as to what the plaintiff was to furnish in drilling the well, and what the defendants were to furnish, and the full amount to 'be paid to the plaintiff, as designated in the contract, was $10,575. Among other things in the written contract appears the following:

“The well shall be considered completed should the work be stopped at the order of the party of the second part.”

The original petition avers that, after the plaintiff had drilled.the well down some-' thing over 1,300 feet, the defendants failed to furnish the necessary casing and pipe for use in drilling said well, and that, on February 9, 1921, the defendant, the Junction Oil & Gas Company, through its said receiver and agent, E. E. AVilson, directed that the work be stopped, and it was claimed in the plaintiff’s petition that because of the contract and order so given, so far as he was concerned, the contract was fully performed, and that he was entitled to the sum of $16,575, less certain payments that had been paid to him.

Upon examination of the written contract, which was referred to in the petition, a part of which is heretofore quoted, the further clause is found:

“It is further understood and agreed that this contract supersedes and takes the place of a certain contract, hereto lore, to wit, on the 6th day of February, 1919, between the party of the second part and AV. IC. Mann; * * * that, under said contract a well has been drilled to the depth of about 2,600 feet, and that the casing has been placed therein.”

And then proceeds to provide that the defendants should pull said casing at their expense and move the rig, drilled under the contract of February 6, 1919.

A demurrer to the petition was filed by the defendants and was overruled on July 20, 1921, and on July 23rd, separate demurrers were filed by the defendants. On August 8th, answer was filed by the defendants, and the separate demurrers were then overruled, and a second answer was filed on December 22nd, in which answer the defendants denied generally the allegations of the petition, and pleaded payment for all services, work, and labor done by plaintiff on the contract, and that the claim of plaintiff had. been fully satisfied.

On the 1st day of March, 1923, being a continuance of the December, 1922, term of district court of Kay county, the cause came on for trial before the court, a jury having been specially waived, and the following stipulation was entered into by the parties in open court:

“The defendants admit that the contract for drilling an oil and gas well as sued upon in this case was duly and properly executed between the plaintiff and the Junction Oil & Gas Company, and that the plaintiff has under said contract proceeded to and did start a well, and that he. drilled as under the terms of this contract to a depth of 1,365 feet, at which time the Junction Oil & Gas Company went into the hands of a receiver, and that the district court of Kay county. Okla., appointed E. E. AVilson of Blackwell, Okla., as receiver for the Junction Oil ¿é Gas Company, who duly qualified as such receiver and immediately ordered the plaintiff in this case to cease further operations on said well.
“The defendants further admit that the Junction Oil & Gas Company and the receiver, E. E. Wilson, representing the same, did not furnish any casing for the continuation of the operation of said well as required under the terms of the contract, and that the plaintiff in this case drilled no further than 1,365 feet, and the defendants further admit that there has been no payment to the plaintiff by the Junction Oil & Gas Company or the receiver thereof, as per the terms of this contract: that the order of the said receiver was the only cause for the work of the plaintiff performing the terms of the contract ceasing.
*241 ‘‘It is further agreed that a trial of the said cause hy jury is hereby waived, and that said cause may be tried to the court.”

The same attorney represented the defendants at the trial and in all subsequent proceedings.

The testimony of the plaintiff, W. K. Mann, was taken, being the only testimony presented to the court at the trial, in which he testified, in substance, that the first well of 2,600 feet was drilled, under contract of February 6, 1919, out of which the contract sued upon originated; that he had drilled on two wells, and that he had expended «.bout $25,000; that on the present well he had spent about 15 days drilling the same at a cost of $50 per day, but that he had expended large amounts for material, preparing to drill the well, rigging up and purchasing lines to drill the well sued upon, and that it would have cost about $2,500 more to complete the well, had he been al lowed to proceed.

At the close of all the evidence, the court took the case under advisement, and on March 7, 1923, rendered its judgment in favor of the plaintiff and against the defendants in the sum of $13,200, with interest thereon at the rate of six per cent, per an-num from the 9th day of February, 1921, and for costs. No exception was reserved hy defendants, and no motion for new trial was filed.

The term of court at which the judgment was rendered expired, and on the 5th day of June, 1923, thereafter, the defendants filed motion to modify the judgment, in which it is recited that the receiver, E. E. Wilson, ordered the drilling to cease because of lack of funds, and that he, acting as an officer of the court, had the right to stop the drilling, and that the judgment, under the evidence, ■ showed that the plaintiff was entitled to a judgment in the amount of $8,-000, signed by G-. A. Chappell, attorney for defendants. This motion was overruled on the 12th day of November, 1923, and, on the 10th day of December, 1923, the defendants filed a petition for a 'new trial, in which, among other things, it is said that the defendants, .on the 4th day of December, 1923, learned, for the first time, that there was a former contract other than the one sued upon, and sets out specifically in said peri-» tion that when the plaintiff had reached a depth of 1,453 feet in. the well drilled, under the contract sued upon, che receiver, E. E. Wilson, “acting on the instruction of the court, instructed the said W. K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Culver v. Mid-Continent Casualty Company
1974 OK 79 (Supreme Court of Oklahoma, 1974)
Fowler v. City of Seminole
1950 OK 97 (Supreme Court of Oklahoma, 1950)
Campbell v. Apple
1937 OK 5 (Supreme Court of Oklahoma, 1937)
The Wheeling Lake Erie Ry. Co. v. Richter
3 N.E.2d 408 (Ohio Supreme Court, 1936)
Farmers National Bank of Sulphur v. Bell
54 P.2d 1072 (Supreme Court of Oklahoma, 1936)
L. S. Cogswell Lbr. Co. v. Manahan
274 P. 871 (Supreme Court of Oklahoma, 1929)
Smith v. Garis
1927 OK 74 (Supreme Court of Oklahoma, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
1926 OK 437, 246 P. 464, 117 Okla. 239, 1926 Okla. LEXIS 786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mann-v-wilson-okla-1926.