Manley-Stearns Construction Co. v. City of Miami

75 So. 27, 73 Fla. 863
Supreme Court of Florida·Decided April 17, 1917·Published

Opinion

Whitfield, J.

The partnership brought an • action against the city on a contract. In four counts it is in effect alleged that in 1913 the Creosoted Wood Block Paving Company, a corporation, was awarded a contract, based upon an advertisement for bids, for grading and paving certain streets of the city consisting of “wood block surface pavement, set on one inch mortar cushion,” to be paid for at a stated rate of compensation; that such contract provided for the maintenance of such streets for five years after final completion of the paving, as shown by portions of the contract herein set out; that the paving was completed and accepted by the city and payment therefor made; that thereafter a written tripartite agreement with the city was made whereby the plaintiffs were substituted for the Creosoted Wood Block Paving Company as to the maintenance of the pavement and the latter company was released by the city from its contract of maintenance, the contract of substitution being set out herein; that thereafter the Creosoted Wood Block Paving Company assigned and transferred' in writing to the plaintiffs all of its “right, title, claim, interest and demand * under said contract;” that in 1915, and within five years after the final completion of the paving, the city found that a necessity arose for opening, removing and replacing” a stated portion of the pavement on-designated streets; “that no demand was made by said defendant of said Creosoted Wood Block Paving Company or of plaintiffs for permission for the opening' of said pave[865]*865ment; that said plaintiffs were ready and willing to remove and replace said pavement as aforesaid * * in person or through some duly accredited agent and, when necessity arose, as found by said City Council as aforesaid, the said plaintiffs offered to do the said work of opening, removing and replacing said sections of pavement as aforesaid, and the'said Creosoted Wood Block Paving Company from the time of taking- its said contract with said defendant, and the said plaintiffs from the time of the execution of the said contract of November 5, 1914, between it, said Creosoted Wood Block Paving Company and said defendant, have always performed and fulfilled all things on their part and behalf in the said contract to be performed and fulfilled and plaintiffs were at all times ready and willing and offered to open, remove and replace said pavement as aforesaid, * * and have always been read}*- and willing to perform and complete the whole of said work so found to be necessary, in pursuance of said contracts, all of which premises the said defendant has had notice.

Yet the plaintiffs in fact say that the said defendant contriving and wrongfully intending to injure the said plaintiffs did not, nor would, perform the said contracts, nor its said promises and undertakings, but did craftily and subtly thereby deceive the said plaintiffs in this, to-wit: that the said defendant, after • having found that said necessity arose for opening, removing and replacing said sections of pavement as aforesaid, did not, nor would, make demand upon said plaintiffs for the opening, removing or replacing of said sections of pavement aforesaid, and did not, nor would permit the opening, removing or replacing of said sections of pavement by the plaintiffs, in person or through some duly accredited agent of plaintiff, but authorized and permitted said sections of [866]*866pavement to be opened, removed and replaced by others, over the objection and against the protest made by said plaintiffs to said defendant, and the said defendant then and there wrongfully discharged the said plaintiffs from the performance of its said agreement and undertaking to open, remove and replace said sections of pavement aforesaid * * and refused and still continues to refuse, to pay the said plaintiffs the compensation it agreed to pajr to plaintiffs when said pavement was opened, removed and replaced, as provided for in said contracts aforesaid, whereby the said plaintiffs have lost and been deprived of the profits and advantages which they otherwise mig'ht and would have derived and acquired from the opening, removing and replacing of said pavement.”

Damages are claimed.

The portions of the contracts referred to are as follows :

“Pavement Guarantees.

“(95) Upon the final completion of the work, the Contractor’s tender of same for acceptance, he shall certify that all work which had been required and all materials used in the construction of the pavements was of ■ such 'character as to insure that no repairs would be needed on account of the action of the elements or the usual wear incideiit to traffic, for a period of five (5) years, during which time any cracks, irregularities, settlements, depressions, soft spots, and the apparent disintegration of any composition pavement or the unevenness, settlement, undue expansion or injurious cracks in the brick, asphalt, or wooden block paving, shall be promptly corrected by the Contractor without cost to the city, upon the demand of the proper authorities, and in the event that after a reasonable notice the Contractor declines or [867]*867neglects to make the corrections or repairs deemed necessary, the city authorities may proceed to have the same done or do the work with their own employees and the cost thereof shall be paid by the contractor upon demand.

“(96) Openings And Repairs.-— Should, in the.opinion of the Board, any necessity arise for removing, repairing or replacing- any section of the pavement, for the laying of water, gas or other mains, or the repair of same, or of any other purpose, upon official demand, the Contractor shall grant permission for the opening of the pavement by properly authorized persons or shall promptly attend to the same in person or through some duly accredited agent, provided, however, that in the event of an emergency, the City or any of its public service corporations shall have the right under this contract and bond to open any section of the pavement for immediate replacement or repair of underground properties or utilities and any section of pavement disturbed in such a manner shall be promptly repaired upon the requisition of the-proper city officials. For all emergency or other repairs, in full compensation thereof, there shall be paid within thirty (30) days to the Contractor during the term of the guarantee, and in addition to the original contract-prices, the further sums in accordance with the following^

“For each separate amount as ordered less than twenty (20) yards, 20 per cent.

“For each separate amount as ordered more than twenty (20) and less than fifty (50) yards, 15 per cent.

“For- each seperate amount as ordered in excess of fifty (50) yards, 10 per cent.

“At the option of the city, if, after seven (7) days notice, the Contractor declines or refuses to renew or repair any work ordered or required by the city or its public service corporations through its duly authorized offi[868]*868cial, same may be done or performed or materials furnished for such restoration or repair and the cost of same shall be charged to the-Contractor, who shall not complain of the character of the work done by the said city or its agents, as a reason for a release of the obligations for maintenance or guarantee under this agreement.” ■

“Whereas, the Creosoted Wood Block Paving Company, is under contract with the City of Miami, for tire maintenance of the wood block pavement on the following streets, to-wit:

“On 12th Street from.

Free access — add to your briefcase to read the full text and ask questions with AI

Manley-Stearns Construction Co. v. City of Miami, 75 So. 27, 73 Fla. 863 (Fla. 1917).

75 So. 27 (Manley-Stearns Construction Co. v. City of Miami) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.