This text of 53 P.3d 1011 (Manke Lumber Co. v. CENT. PUGET SOUND GROWTH MANAGEMENT HEARINGS BOARD) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manke Lumber Co. v. CENT. PUGET SOUND GROWTH MANAGEMENT HEARINGS BOARD, 53 P.3d 1011 (Wash. Ct. App. 2002).

Opinion

53 P.3d 1011 (2002)

MANKE LUMBER COMPANY, INC., a Washington corporation, and Mr. and Mrs. Warren E. Posten, Sr., Appellants,
v.
CENTRAL PUGET SOUND GROWTH MANAGEMENT HEARINGS BOARD, an agency of the State of Washington; Kitsap County, a Washington municipal corporation, Respondents.

No. 26580-0-II.

Court of Appeals of Washington, Division 2.

May 17, 2002.
Reconsideration Denied and Publication Ordered June 20, 2002.

*1013 William Lynn, Attorney at Law, Tacoma, WA, Warren E. Posten, Attorney at Law, Keyport, WA, Margaret Archer, Attorney at Law, Tacoma, WA, for Appellants.

Samuel Plauche, Attorney at Law, Seattle, WA, Evelyn Sue Tanner, Deputy Pros. Attorney, Port Orchard, WA, Kitteridge Oldham, Attorney at Law Asst, Seattle, WA, Alan D. Copsey, Asst. Attorney General, Sharon Eckholm, Asst. Attorney General, Olympia, Wa, for Respondents.

James R. Schwarz, Asst. Attorney General, Olympia, WA, for Plaintiff, State Dept. of Natural Resources.

*1012 HOUGHTON, J.

Manke Lumber Company, Inc. and Warren Posten, Sr. appeal from a superior court decision affirming a Central Puget Sound Growth Management Hearings Board determination that Kitsap County's Comprehensive Plan land designations complied with the Growth Management Act. We affirm.

I. FACTS

A. Background

This appeal involves Kitsap County's (the County) third attempt to comply with the Growth Management Act (GMA). The County's two previous attempts resulted in invalidation of its Comprehensive Plan. In the County's first attempt at complying with the GMA, the Central Puget Sound Growth Management Hearings Board (Board) invalidated the County's 1994 Comprehensive Plan (1994 Plan) in its entirety. Clerk's Papers (CP) at 604, 665 (Bremerton v. Kitsap County, CPSGMHB No. 95-3-0039c, Final Decision and Order). In the County's second attempt, the Board determined that significant portions of the County's 1996 Comprehensive Plan (1996 Plan) did not comply with the GMA and that the Plan was invalid. CP at 672, 722-23 (Port Gamble v. Kitsap County, CPSGMHB No. 97-3-0024c, Finding of Noncompliance and Determination of Invalidity). Among other things, the Board invalidated the Rural Element and Land Use Element(s), including the County's land use map and rural densities. CP at 722 (Bremerton v. Kitsap County, CPSGMHB XX-X-XXXXck95-3-0039c).

After numerous public hearings and county commissioner meetings, the County adopted the 1998 Comprehensive Plan (1998 Plan) on May 7, 1998. The Board found that the 1998 Plan was in compliance with the GMA.[1] It then rescinded the previous order of invalidity arising from the Bremerton case.[2] CP at 737, 833 (Alpine v. Kitsap County, CPSGMHB No. 98-3-0032c, Order Rescinding Invalidity and Final Decision and Order).

Manke Lumber Company, the Department of Natural Resources (DNR), and Warren Posten, Sr. appealed the Board's final decision and order to the Kitsap County Superior Court. The superior court rejected the petitioners' arguments that the Board erred and it affirmed the Board's decision. DNR did not appeal the superior court's decision, leaving Manke and Posten as the remaining appellants.

B. The Manke Appeal

Manke owns approximately 2,000 acres of land in Kitsap County, some of it on the banks of Hood Canal. Under the 1998 Plan, most of Manke's land is subject to the Interim Rural Forest (IRF) designation.[3] The *1014 County designated 52,157[4] out of a possible total of 238,559 acres in the County as IRF in its 1998 Plan (approximately 22 percent of the total amount of land in the County). The 1998 Plan defines IRF land as "larger parcels of land in contiguous blocks that are forested in character, that have been actively managed for forestry and harvested, and that are currently taxed as timber lands under state and county programs." Administrative Record (AR) at 8016.

In developing its 1998 Plan, the County completely discarded the Rural Element portion of its invalid and later repealed 1996 Plan. Instead, the County devised a new system to categorize its rural lands. Under the 1996 Plan, Manke's shoreline properties were designated Rural Wooded, which allowed a density of one dwelling unit per 1 to 2.5 acres.[5] The 1998 Plan designated Manke's shoreline properties (along with approximately 50,000 additional acres) as IRF, with a density of 1 dwelling unit per 20 acres.

Manke argues that the County's designation of its shoreline properties as IRF is invalid because the County failed to consider several factors in its planning. Specifically, Manke asserts that the IRF designation of its shoreline properties was arbitrary and lacked evidentiary support. In this appeal, Manke does not challenge the general validity of the IRF designation; rather, it challenges only the applicability of the designation to its own shoreline properties.

C. The Posten Appeal

Posten owns a parcel of land in the Keyport area on the banks of Dyes Inlet. He operates a marina, boat dock, marine repair business, parking lot, and garage. He also has a single family residence on the property. Posten's commercial activities are allowed under a 1984 unclassified use permit (UUP) and a shoreline substantial development permit (SDP).

The 1998 Plan and zoning ordinance designated all waterfront property in the Keyport area as Rural Residential. Posten's property was zoned commercial (Business General) before adoption of the 1998 Plan. The 1998 Plan and a zoning ordinance allow water-dependent and water-related uses within the shoreline via a conditional use permit (CUP)[6] and SDP, regardless of the zone classification. Expansion of these uses is allowed if a CUP is obtained.

The 1998 Plan did not designate Keyport as an urban growth area (UGA). The intent was that designated UGAs would accommodate most of the projected population growth in the County over the next 20 years. Keyport was designated a UGA under the repealed 1996 Plan, but in its efforts to develop a comprehensive plan that complied with the GMA, the County deleted Keyport as a UGA.

Posten appeals Keyport's removal from a UGA designation.

II. ANALYSIS

A. Standard of Review

We review the Board's decisions by applying the standards of the Administrative Procedure Act (APA) directly to the record before it, sitting in the same position as the superior court. King County v. Cent. Puget Sound Growth Mgmt. Hearings Bd., 142 Wash.2d 543, 553, 14 P.3d 133 (2000). The party asserting that the Board erroneously interpreted or applied the law, or that the Board's decision is not supported by substantial *1015 evidence, carries the burden of demonstrating the error. King County, 142 Wash.2d at 553, 14 P.3d 133; RCW 34.05.570(1)(a). We review the Board's legal conclusions de novo, giving substantial weight to its interpretation of the statutes it administers. King County, 142 Wash.2d at 553, 14 P.3d 133. We review the Board's findings of facts for substantial evidence under RCW 34.05.570(3)(e).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shantanu Neravetla, M.d. v. State Of Wa, Dept. Of Health
394 P.3d 1028 (Court of Appeals of Washington, 2017)
Edward Coyne v. Growth Management Board
Court of Appeals of Washington, 2016
Clallam County v. Dry Creek Coalition
161 Wash. App. 366 (Court of Appeals of Washington, 2011)
Clark County v. Western Washington Growth Management Hearings Board
161 Wash. App. 204 (Court of Appeals of Washington, 2011)
Clark County v. WESTERN WASH. GROWTH MGT.
254 P.3d 862 (Court of Appeals of Washington, 2011)
Spokane County v. GROWTH MNGMT. HEARINGS
250 P.3d 1050 (Court of Appeals of Washington, 2011)
Davidson Serles & Associates v. City of Kirkland
159 Wash. App. 616 (Court of Appeals of Washington, 2011)
DAVIDSON SERLES v. City of Kirkland
246 P.3d 822 (Court of Appeals of Washington, 2011)
Brinnon Group v. Jefferson County
159 Wash. App. 446 (Court of Appeals of Washington, 2011)
Spokane County v. Eastern Washington Growth Management Hearings Board
250 P.3d 1050 (Court of Appeals of Washington, 2011)
Suquamish Tribe v. CENTRAL PUGET SOUND
235 P.3d 812 (Court of Appeals of Washington, 2010)
Suquamish Tribe v. Central Puget Sound Growth Management Hearings Board
156 Wash. App. 743 (Court of Appeals of Washington, 2010)
Kitsap County v. Central Puget Sound Growth Management Hearings Board
138 Wash. App. 863 (Court of Appeals of Washington, 2007)
Kitsap County v. CENTRAL PUGET SOUND BOARD
158 P.3d 638 (Court of Appeals of Washington, 2007)
Thurston County v. Western Washington Growth Management Hearings Board
137 Wash. App. 781 (Court of Appeals of Washington, 2007)
Thurston County v. WESTERN WASH. BD.
154 P.3d 959 (Court of Appeals of Washington, 2007)
Lewis County v. Western Washington Growth Management Hearings Board
157 Wash. 2d 488 (Washington Supreme Court, 2006)
Lewis County v. WESTERN WA. GROWTH MANAGEMENT HEARINGS BD.
139 P.3d 1096 (Washington Supreme Court, 2006)
Western Wash. Engineers v. Apprenticeship and Training Council
123 P.3d 533 (Court of Appeals of Washington, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
53 P.3d 1011, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manke-lumber-co-v-cent-puget-sound-growth-management-hearings-board-washctapp-2002.