Manhattan State Bank v. C. J. Moritz, Inc.

238 Ill. App. 103, 1925 Ill. App. LEXIS 228
CourtAppellate Court of Illinois
DecidedJuly 11, 1925
DocketGen. No. 7,482
StatusPublished

This text of 238 Ill. App. 103 (Manhattan State Bank v. C. J. Moritz, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manhattan State Bank v. C. J. Moritz, Inc., 238 Ill. App. 103, 1925 Ill. App. LEXIS 228 (Ill. Ct. App. 1925).

Opinion

Mr. Justice Partlow

delivered the opinion of the court.

The original bill in this case was filed in the circuit court of Will county by The Manhattan State Bank, The Western Wheel Scraper Works and several small claimants, to obtain a lien against a fund in the hands of the State of Illinois due appellee, C. J. Moritz, Inc., on account of a hard road contract with the State. A demurrer to the bill was sustained as to the Bank and the Scraper Works, and overruled as to the other claimants. The Scraper Works elected to stand by the bill and it was dismissed. Appellant, The Manhattan State Bank, filed an amended bill, to which a demurrer was sustained, the amended bill of the Bank was also dismissed for want of equity, and from that decree appellant,' The Manhattan State Bank, prosecutes this appeal.

The amended bill alleged that Moritz had a contract with the State of Illinois for the improvement of a portion of State bond issue route number 44, in Will county, for a consideration of $205,140.06. Afterwards, in violation of the terms of the contract, Moritz sublet the grading work to James F. Ryan for the portion between Wilton Center and the Elgin, Joliet & Eastern Railroad Company crossing, near the City of Joliet. Ryan began the grading on August 21, 1922, and continued until December 13, 1922, when he was adjudged a bankrupt and abandoned his contract. On August 21, 1922, Ryan was without sufficient money to pay his laborers and other expenses necessary to carry on the work, and on that day a verbal agreement was made between Ryan, Moritz and the Bank to the effect that the Bank should make the necessary advances from time to time to Ryan of money to carry on the contract, and that for the protection of the Bank a written agreement should be entered into between them providing that the proportion of the money that became due to Moritz from the State, from time to time, as the work progressed, that belonged to Ryan by reason of his contract, should be paid to the Bank, and after deducting the amount the Bank had from time to time loaned Ryan, the balance should be paid to. Ryan; that the contract should specifically authorize the State of Illinois, acting through its Department of Public Works and Buildings, to send this money to the Bank; that the Bank should commence the advancement of money immediately, and that the written contract should be executed later. In pursuance of this verbal agreement, the Bank advanced to Ryan $4,000, which was used by him in the payment of his laborers and expenses under the contract, which work would have entitled the persons to whom the money was due to a hen as provided in section 23 of the Mechanics’ Lien Act [Cahill’s St. ch. 82, ft 23] had they not been paid with the money furnished by the Bank. In pursuance of this agreement the Bank caused to be prepared a written contract evidencing the intention of the parties, which agreement was signed by Ryan and the Bank, and afterwards, on October 1, 1922, submitted to Moritz for execution, and Moritz refused to sign the same. All of the money advanced by the Bank to Ryan was advanced and loaned prior to the refusal of Moritz to execute the written agreement, and was advanced in reliance upon the verbal agreement made between the parties. Moritz knew that the Bank intended to advance the money to Ryan in reliance upon the verbal understanding, and all the money was advanced in reliance upon the contract being executed by Moritz. The bill further alleged that Byan actually earned, under his subcontract with Moritz, $10,000 and that said money was actually paid by the Department of Public Works and Buildings to Moritz. The bill prayed for the establishment of a lien as provided by section 23 of the Mechanics’ Lien Act on the funds in the hands of the Department of Public Works and Buildings; that a general accounting be had of the amount of money received by Moritz that was in fact earned by Byan on his subcontract, or the amount which was earned by him which was applied to some other source; and that Moritz be decreed to pay the amount thereof to the Bank.

It is claimed by appellant that the amended bill stated a good cause of action for relief under general equity principles; that the demurrer to the amended bill admitted all of the facts well pleaded; that the facts alleged and admitted constitute a fraud perpetrated by appellee; that fraud is one of the ordinary grounds of jurisdiction of a court of equity; that the acts of the parties amounted to an equitable assignment of the money earned by Byan from appellee; that this money was paid by the State to appellee; that- appellee should be required to disclose the amount, and to account for the same, which is another ground of equity jurisdiction; that the acts of the parties created an equitable contract in favor of appellant, in that a representation of a future intention, absolute in form, was made by appellee for the purpose of influencing the conduct of appellant, and it was then acted upon by appellant, and a court of equity will enforce such a contract; that had the $4,000 not been loaned by appellant to Byan, the persons receiving the same would have been entitled to a lien under section 23 of the Mechanics’ Lien Act, and a court of equity will subrogate the demand of appellant to the rights that these persons would have had.

The demurrer to the amended bill was apparently sustained upon the grounds that the facts stated did not entitle appellant to equitable relief for the reason that it had an adequate remedy at law. Appellant in its brief says: “While as to the complainants other than the appellant, the proceeding is to enforce a lien under section 23 of the Mechanic’s Lien Act, yet, it is a bill in equity,- and not a statutory proceeding, and is governed by general chancery practice, and is not governed by any other provision of the Mechanic’s Lien Act.” Notwithstanding this statement, the bill alleges that after the oral contract was made the bank advanced to Ryan $4,000, which was used by him in payment of his laborers and expenses, which work would have entitled the persons to whom the money was due to a lien under section 23 of the Lien Act, had they not been paid with money furnished by the bank; that a court of equity will subrogate the demand of appellant to the rights which these persons would have had. The prayer is for the establishment of a lien as provided in section 23, on the funds in the hands of the Department of Public Works and Buildings.

Section 23 provides that any person who shall furnish material, apparatus, fixtures, machinery or labor to any contractor having a contract for a public improvement for the State shall have a lien on the money, bonds or warrants due, or to become due, such contractor under such contract. In Hoier v. Kaplan, 313 Bl. 448, in construing this section, it was held that the proceeding being purely statutory, a lien will be allowed only for such items as come strictly within the provisions of the section, and that the statute will not be construed to include cases not provided for by its language even though they may fall within its reason. There is nothing in the statute which provided for a lien for money furnished a contractor to pay bills. The only lien provided is to those who furnish material, apparatus, fixtures, machinery or labor. The claim of appellant does not come within the language of the statute, although it may fall within its reason, but, notwithstanding this fact, the bill prays that a mechanic’s hen shall be allowed under section 23.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Taylor
20 Ill. 650 (Illinois Supreme Court, 1858)
Belden v. Perkins
78 Ill. 449 (Illinois Supreme Court, 1875)
Barnes v. Johnson
84 Ill. 95 (Illinois Supreme Court, 1876)
Laflin v. Howe
112 Ill. 253 (Illinois Supreme Court, 1885)
County of Cook v. Davis
32 N.E. 176 (Illinois Supreme Court, 1892)
James T. Hair Co. v. Daily
43 N.E. 1096 (Illinois Supreme Court, 1896)
Wilson v. Turner
45 N.E. 820 (Illinois Supreme Court, 1896)
Gleason & Bailey Manufacturing Co. v. Hoffman
48 N.E. 143 (Illinois Supreme Court, 1897)
First National Bank v. Gatton
50 N.E. 121 (Illinois Supreme Court, 1898)
Crown Coal & Tow Co. v. Thomas
52 N.E. 1042 (Illinois Supreme Court, 1898)
Donovan v. Purtell
75 N.E. 334 (Illinois Supreme Court, 1905)
Miller v. Russell
79 N.E. 434 (Illinois Supreme Court, 1906)
Board of Highway Commissioners v. City of Bloomington
253 Ill. 164 (Illinois Supreme Court, 1911)
Forster v. Brown Hoisting Machinery Co.
266 Ill. 287 (Illinois Supreme Court, 1914)
Wright v. McKinney
122 N.E. 813 (Illinois Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
238 Ill. App. 103, 1925 Ill. App. LEXIS 228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manhattan-state-bank-v-c-j-moritz-inc-illappct-1925.