Court of Appeals Tenth Appellate District of Texas
10-24-00274-CV
Manhattan Construction Company, Appellant
v.
McCaffety Electric Co., Inc., Appellee
On appeal from the 12th District Court of Walker County, Texas Judge David W. Moorman, presiding Trial Court Cause No. 2130130
JUSTICE HARRIS delivered the opinion of the Court.
MEMORANDUM OPINION
INTRODUCTION
Manhattan Construction Company (“Manhattan”) appeals the trial
court’s interlocutory order denying its motion to stay the underlying lawsuit
and compel arbitration. The suit was filed against Manhattan by appellee
McCaffety Electric Co., Inc. (“McCaffety”), who pleaded claims for suit on
sworn account, breach of contract, and quantum meruit. Because the parties expressly delegated arbitrability to the arbitrator, we reverse and remand the
trial court’s order.
BACKGROUND
Manhattan was the general contractor for the construction of an art
complex at Sam Houston State University (“SHSU”) in Huntsville, Walker
County, Texas. McCaffety entered into a Subcontract Agreement (the
“Subcontract”) with Manhattan to furnish and install all electrical work
related to the project. The Subcontract includes a document titled “Manhattan
General Provisions” (the “General Provisions”). The arbitration paragraph
appears in the General Provisions, under the subheading “3.5 SETTLEMENT
OF DISPUTES,” in the following manner:
3.5.2. All disputes between the parties shall be resolved by litigation, in a court of competent jurisdiction, except that Manhattan may, at its sole option, require that any dispute be submitted to arbitration pursuant to the Construction Industry Rules of the American Arbitration Association except that for disputes equal or less than $500,000, a single arbitrator shall be appointed who will be an attorney with at least (10) years of experience in construction law, and for disputes involving $500,000 or more, there shall be three (3) arbitrators with each being an attorney and having at least ten (10) years of experience in construction law. Manhattan shall not be deemed to have waived any right it may have to arbitrate its disputes with Subcontractor by the filing of litigation against Subcontractor and its surety. At Manhattan’s request, Subcontractor agrees to join in any motion Manhattan may file seeking stay of any suit pending resolution of any arbitration between Subcontractor and Manhattan. In any arbitration between Subcontractor and Manhattan, pretrial discovery shall be allowed to the full extent as permitted by the local rules of civil procedure in the state in which the project is located.
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 2 This agreement was signed by Manhattan and McCaffety.
A dispute arose between McCaffety and Manhattan when Manhattan
allegedly refused to pay McCaffety for work installing a conduit. McCaffety
filed suit on sworn account, breach of contract, and quantum meruit to recover
the unpaid payments.
McCaffety also subcontracted with Convirgent Technologies
(“Convirgent”) to perform certain installations on the SHSU project. While
McCaffety’s lawsuit against Manhattan was pending, Convirgent filed suit
against McCaffety on December 9, 2021, for allegedly failing to pay for the
installations it performed. The trial court granted McCaffety’s motion to
consolidate Convirgent’s claims with McCaffety’s on November 3, 2022. The
parties do not dispute that Convirgent did not sign the arbitration agreement
between Manhattan and McCaffety.
Manhattan moved to compel arbitration and stay the proceedings on
November 9, 2021. Convirgent filed a motion for severance on May 21, 2024.
On May 30, 2024, McCaffety filed its response to Manhattan’s motion to compel
arbitration.
McCaffety argued that the trial court could not compel Convirgent to
arbitrate as a non-signatory. McCaffety contended that sending McCaffety’s
claim to arbitration while litigating Convirgent’s claim separately would place
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 3 a burden on McCaffety and Convirgent. After several hearings and requests
for delay by McCaffety, the trial court issued an order denying both motions on
August 14, 2024. The trial court made no findings or conclusions explaining
its denials. Manhattan then filed a notice of appeal on August 29, 2024.
The sole issue in this appeal is whether the trial court abused its
discretion by denying Manhattan’s motion to compel arbitration of McCaffety’s
claims when the arbitration agreement allows Manhattan to submit “any
dispute” between McCaffety and Manhattan to arbitration “pursuant to the
Construction Industry Rules of the American Arbitration Association.” 1
STANDARD OF REVIEW AND APPLICABLE LAW
We review a trial court’s order denying a motion to compel arbitration
for abuse of discretion. Henry v. Cash Biz, LP, 551 S.W.3d 111, 115 (Tex. 2018);
In re Labatt Food Serv., L.P., 279 S.W.3d 640–43 (Tex. 2009); see also
Hollingsworth v. Swales, No. 10-23-00018-CV, 2025 WL 479545 at *2 (Tex.
App.—Waco Feb. 13, 2025, pet. filed) (publish). A trial court’s failure to
analyze or apply the law correctly constitutes an abuse of discretion. See
1 In its Notice of Appeal, Manhattan cited both the trial court’s order denying its motion to compel and
the order denying Convirgent’s motion to sever as issues on appeal. However, neither party briefed the issue relating to the order denying severance, and an order denying severance is not an appealable interlocutory order. “It is undisputed that because an order denying severance is not a final judgment, it is not appealable.” In re State Farm Mut. Auto. Ins. Co., 395 S.W.3d 229, 236–37 (Tex. App.—El Paso 2012, no pet.). TEX. CIV. PRAC. & REM. CODE § 51.014 allows a party to appeal certain interlocutory orders, but an order denying a motion to sever is not among them. TEX. CIV. PRAC. & REM. CODE ANN. § 51.014. Thus, we do not address the issue of the order denying severance.
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 4 Walker v. Packer, 827 S.W.2d 833, 840 (Tex. 1992). We defer to the trial court’s
factual determinations if they are supported by evidence but review its legal
determinations de novo. Henry, 551 S.W.3d at 115; Rachal v. Reitz, 403 S.W.3d
840, 843 (Tex. 2013); see also Hollingsworth, 2025 WL 479545 at *2.
The parties do not dispute or address which arbitration act, federal or
state, applies here. Because it makes no difference in the disposition of this
appeal, we assume without deciding that the Texas Arbitration Act (“TAA”)
applies to the Subcontract. 2
DISCUSSION
It is well settled that parties can agree to arbitrate “gateway” questions
of arbitrability. HomeAdvisor, Inc. v. Waddell, No. 05-19-00669-CV, 2020 WL
2988565, at *5 (Tex. App.—Dallas June 4, 2020, no pet.); Rent-A-Ctr., W., Inc.
v. Jackson, 561 U.S. 63, 68–69 (2010). These “gateway” questions include all
defenses to arbitration, including the arbitration provision’s scope. See
Waddell, 2020 WL 2988565, at *5; Jackson, 561 U.S. at 68–69. But because
arbitration is a matter of contract, courts must decide in the first instance
whether a valid arbitration agreement exists. TotalEnergies E&P USA, Inc. v.
Free access — add to your briefcase to read the full text and ask questions with AI
Court of Appeals Tenth Appellate District of Texas
10-24-00274-CV
Manhattan Construction Company, Appellant
v.
McCaffety Electric Co., Inc., Appellee
On appeal from the 12th District Court of Walker County, Texas Judge David W. Moorman, presiding Trial Court Cause No. 2130130
JUSTICE HARRIS delivered the opinion of the Court.
MEMORANDUM OPINION
INTRODUCTION
Manhattan Construction Company (“Manhattan”) appeals the trial
court’s interlocutory order denying its motion to stay the underlying lawsuit
and compel arbitration. The suit was filed against Manhattan by appellee
McCaffety Electric Co., Inc. (“McCaffety”), who pleaded claims for suit on
sworn account, breach of contract, and quantum meruit. Because the parties expressly delegated arbitrability to the arbitrator, we reverse and remand the
trial court’s order.
BACKGROUND
Manhattan was the general contractor for the construction of an art
complex at Sam Houston State University (“SHSU”) in Huntsville, Walker
County, Texas. McCaffety entered into a Subcontract Agreement (the
“Subcontract”) with Manhattan to furnish and install all electrical work
related to the project. The Subcontract includes a document titled “Manhattan
General Provisions” (the “General Provisions”). The arbitration paragraph
appears in the General Provisions, under the subheading “3.5 SETTLEMENT
OF DISPUTES,” in the following manner:
3.5.2. All disputes between the parties shall be resolved by litigation, in a court of competent jurisdiction, except that Manhattan may, at its sole option, require that any dispute be submitted to arbitration pursuant to the Construction Industry Rules of the American Arbitration Association except that for disputes equal or less than $500,000, a single arbitrator shall be appointed who will be an attorney with at least (10) years of experience in construction law, and for disputes involving $500,000 or more, there shall be three (3) arbitrators with each being an attorney and having at least ten (10) years of experience in construction law. Manhattan shall not be deemed to have waived any right it may have to arbitrate its disputes with Subcontractor by the filing of litigation against Subcontractor and its surety. At Manhattan’s request, Subcontractor agrees to join in any motion Manhattan may file seeking stay of any suit pending resolution of any arbitration between Subcontractor and Manhattan. In any arbitration between Subcontractor and Manhattan, pretrial discovery shall be allowed to the full extent as permitted by the local rules of civil procedure in the state in which the project is located.
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 2 This agreement was signed by Manhattan and McCaffety.
A dispute arose between McCaffety and Manhattan when Manhattan
allegedly refused to pay McCaffety for work installing a conduit. McCaffety
filed suit on sworn account, breach of contract, and quantum meruit to recover
the unpaid payments.
McCaffety also subcontracted with Convirgent Technologies
(“Convirgent”) to perform certain installations on the SHSU project. While
McCaffety’s lawsuit against Manhattan was pending, Convirgent filed suit
against McCaffety on December 9, 2021, for allegedly failing to pay for the
installations it performed. The trial court granted McCaffety’s motion to
consolidate Convirgent’s claims with McCaffety’s on November 3, 2022. The
parties do not dispute that Convirgent did not sign the arbitration agreement
between Manhattan and McCaffety.
Manhattan moved to compel arbitration and stay the proceedings on
November 9, 2021. Convirgent filed a motion for severance on May 21, 2024.
On May 30, 2024, McCaffety filed its response to Manhattan’s motion to compel
arbitration.
McCaffety argued that the trial court could not compel Convirgent to
arbitrate as a non-signatory. McCaffety contended that sending McCaffety’s
claim to arbitration while litigating Convirgent’s claim separately would place
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 3 a burden on McCaffety and Convirgent. After several hearings and requests
for delay by McCaffety, the trial court issued an order denying both motions on
August 14, 2024. The trial court made no findings or conclusions explaining
its denials. Manhattan then filed a notice of appeal on August 29, 2024.
The sole issue in this appeal is whether the trial court abused its
discretion by denying Manhattan’s motion to compel arbitration of McCaffety’s
claims when the arbitration agreement allows Manhattan to submit “any
dispute” between McCaffety and Manhattan to arbitration “pursuant to the
Construction Industry Rules of the American Arbitration Association.” 1
STANDARD OF REVIEW AND APPLICABLE LAW
We review a trial court’s order denying a motion to compel arbitration
for abuse of discretion. Henry v. Cash Biz, LP, 551 S.W.3d 111, 115 (Tex. 2018);
In re Labatt Food Serv., L.P., 279 S.W.3d 640–43 (Tex. 2009); see also
Hollingsworth v. Swales, No. 10-23-00018-CV, 2025 WL 479545 at *2 (Tex.
App.—Waco Feb. 13, 2025, pet. filed) (publish). A trial court’s failure to
analyze or apply the law correctly constitutes an abuse of discretion. See
1 In its Notice of Appeal, Manhattan cited both the trial court’s order denying its motion to compel and
the order denying Convirgent’s motion to sever as issues on appeal. However, neither party briefed the issue relating to the order denying severance, and an order denying severance is not an appealable interlocutory order. “It is undisputed that because an order denying severance is not a final judgment, it is not appealable.” In re State Farm Mut. Auto. Ins. Co., 395 S.W.3d 229, 236–37 (Tex. App.—El Paso 2012, no pet.). TEX. CIV. PRAC. & REM. CODE § 51.014 allows a party to appeal certain interlocutory orders, but an order denying a motion to sever is not among them. TEX. CIV. PRAC. & REM. CODE ANN. § 51.014. Thus, we do not address the issue of the order denying severance.
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 4 Walker v. Packer, 827 S.W.2d 833, 840 (Tex. 1992). We defer to the trial court’s
factual determinations if they are supported by evidence but review its legal
determinations de novo. Henry, 551 S.W.3d at 115; Rachal v. Reitz, 403 S.W.3d
840, 843 (Tex. 2013); see also Hollingsworth, 2025 WL 479545 at *2.
The parties do not dispute or address which arbitration act, federal or
state, applies here. Because it makes no difference in the disposition of this
appeal, we assume without deciding that the Texas Arbitration Act (“TAA”)
applies to the Subcontract. 2
DISCUSSION
It is well settled that parties can agree to arbitrate “gateway” questions
of arbitrability. HomeAdvisor, Inc. v. Waddell, No. 05-19-00669-CV, 2020 WL
2988565, at *5 (Tex. App.—Dallas June 4, 2020, no pet.); Rent-A-Ctr., W., Inc.
v. Jackson, 561 U.S. 63, 68–69 (2010). These “gateway” questions include all
defenses to arbitration, including the arbitration provision’s scope. See
Waddell, 2020 WL 2988565, at *5; Jackson, 561 U.S. at 68–69. But because
arbitration is a matter of contract, courts must decide in the first instance
whether a valid arbitration agreement exists. TotalEnergies E&P USA, Inc. v.
2 “Whether a case is governed by the Federal Arbitration Act (FAA) or the TAA, many of the underlying
substantive principles are the same.” Forest Oil Corp. v. McAllen, 268 S.W.3d 51, 56 n. 10 (Tex. 2008); see also LDF Const., Inc. v. Bryan, 324 S.W.3d 137, 144-45 (Tex. App. —Waco 2010, no pet.) (applying a two-step test determining the validity and scope of an arbitration agreement under the Federal Arbitration Act (“FAA”)); Teal Constr. Co./Hillside Villas Ltd. v. Darren Casey Ints., Inc., 46 S.W.3d 417, 420 (Tex. App. —Austin 2001, pet. denied) (applying the same two-step test under the TAA).
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 5 MP Gulf of Mexico, LLC, 667 S.W.3d 694, 720 (Tex. 2023) (citing Henry Schein,
Inc. v. Archer & White Sales, Inc., 586 U.S. 63, 69 (2019)). If a valid agreement
exists, and the agreement delegates the arbitrability issue to the arbitrator, a
court must enforce the delegation of the arbitrability issue. Henry Schein, Inc.,
586 U.S. at 69; see also TotalEnergies, 667 S.W. 3d at 720–21.
“The question of whether claims and defenses in a suit are arbitrable is
a separate question from which decisionmaker—the courts or the arbitrator—
is the one to decide whether the claims and defenses are arbitrable.” CPG 220
Holdings 2014, LLC v. Mulcahy, 709 S.W.3d 728, 733 (Tex. App.—Austin 2025,
pet. filed) (citing TotalEnergies, 667 S.W.3d at 701). “The who-decides-
arbitrability question must be answered before the arbitrability question itself
is answered.” Id.
I. Valid Arbitration Agreement
We must decide in the first instance whether a valid arbitration
agreement exists. TotalEnergies, 667 S.W.3d at 720. The validity of an
arbitration agreement is a legal question subject to de novo review. CPG 220
Holdings 2014, LLC v. Mulcahy, 709 S.W.3d 728, 733 (Tex. App.—Austin 2025,
pet. filed). An arbitration agreement under the TAA must be supported by
mutual assent, though it need not meet all the formal requirements of a
contract. Rachal, 403 S.W.3d at 845; see also Hollingsworth, 2025 WL 479545
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 6 at *2. A party usually manifests its assent by signing an agreement. Rachal,
403 S.W.3d at 845; Mid-Continent Cas. Co. v. Global Enercom Mgmt., Inc., 323
S.W.3d 151, 157 (Tex. 2010) (per curiam); see also Hollingsworth, 2025 WL
479545 at *2.
Here, Manhattan and McCaffety both signed the Subcontract containing
the arbitration provision. Because the arbitration agreement was signed by
both parties and McCaffety raised no specific challenge to the agreement’s
validity, Manhattan met its burden of proving a valid agreement to arbitrate.
See LDF Const., Inc. v. Bryan, 324 S.W.3d 137, 144–45 (Tex. App.—Waco 2010,
no pet.); BFS Group, LLC v. Holman, No. 05-24-00523-CV, 2025 WL 625501,
at *6 (Tex. App.—Dallas Feb. 26, 2025, no pet.) (”[T]he uncontested existence
of Holman's signature on the arbitration agreement meets the evidentiary
standard necessary to prove the prima facie existence of an arbitration
agreement.”).
II. Delegation of Arbitrability
Recently, the Texas Supreme Court addressed the issue of delegating
gateway arbitrability issues to an arbitrator. In TotalEnergies, the Court
stated,
[A]s a general rule, an agreement to arbitrate disputes in accordance with rules providing that the arbitrator “shall have the power” to determine “the arbitrability of any claim” incorporates those rules into the agreement and clearly and unmistakably
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 7 demonstrates the parties’ intent to delegate arbitrability issues to the arbitrator.
TotalEnergies E&P USA, Inc. v. MP Gulf of Mexico, LLC, 667 S.W.3d 694, 712
(Tex. 2023). An agreement that merely refers to the American Arbitration
Association (“AAA”) or similar rules or permits the parties to request
assistance from the AAA does not bind the parties to those rules. Id. at 708–
09.
In TotalEnergies, the Court held that an arbitration agreement expressly
stating that arbitration must be conducted “in accordance with” the rules of
the AAA incorporated those rules into the agreement as if they were set forth
in the agreement itself. Id. at 709. The rules were then binding, absent any
conflict between the rules and the terms of the agreement. Id. The AAA rules,
in turn, provided that the arbitrator “shall have the power to rule on his or her
own jurisdiction, including any objections with respect to the existence, scope,
or validity of the arbitration agreement or to the arbitrability of any claim or
counterclaim.” Id. The Court held that the agreement expressly delegated
arbitrability issues to the AAA. Id. at 712.
Here, the General Provisions provide that Manhattan may “require that
any dispute be submitted to arbitration pursuant to the Construction Industry
Rules of the American Arbitration Association.” (emphasis added). Black’s
Law Dictionary defines “pursuant to” as “in accordance with,” which is the
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 8 exact same language the Texas Supreme Court in TotalEnergies found to
successfully incorporate the AAA rules. Pursuant to, Black’s Law Dictionary
(8th ed. 2004); see also Taylor Morrison of Tex., Inc. v. Skufca, 650 S.W.3d 660,
667, 683 (Tex. App.—Houston [1st Dist.] 2021, no pet.) (holding that
arbitration agreement expressly stating disputes “shall be resolved by and
pursuant to the arbitration rules and procedures” of the AAA delegated
arbitrability to the arbitrator. (emphasis added)). Thus, we hold that by using
the words “pursuant to,” the parties incorporated the Construction Industry
Rules of the American Arbitration Association into their agreement. Further,
the broad language “any dispute” shows that the AAA rules apply to any
dispute between Manhattan and McCaffety, including arbitrability disputes.
See TotalEnergies, 667 S.W.3d at 712 (holding that “arising out of” language
was sufficiently broad to cover arbitrability issues).
In turn, Construction Industry Rule 9(a) of the American Arbitration
Association provides “The arbitrator shall have the power to rule on his or her
own jurisdiction, including any objections with respect to the existence, scope,
or validity of the arbitration agreement.” AM. ARBITRATION ASS’N
CONSTRUCTION INDUSTRY ARBITRATION RULES AND MEDIATION PROCEDURES,
R-9(a), 18 (2015). Thus, following the Texas Supreme Court’s holding in
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 9 TotalEnergies, we hold that the parties clearly and expressly delegated
arbitrability issues to the arbitrator.
McCaffety’s sole argument is that separating the cases by sending
McCaffety’s claims to arbitration while litigating Convirgent’s claims would
place a burden on McCaffety. This argument seems to challenge the
enforceability of the arbitration agreement. But because the parties clearly
delegated arbitrability issues to the AAA, we must respect and enforce the
terms of the parties’ contract and refer the issue to the arbitrator.
Philadelphia Indem. Ins. Co. v. White, 490 S.W.3d 468, 471 (Tex. 2016).
CONCLUSION
We hold that because the parties clearly and unmistakably delegated to
the AAA arbitrator the decision of whether the parties’ dispute must be
resolved by arbitration, the trial court abused its discretion by denying
Manhattan’s motion to compel arbitration. Accordingly, the trial court’s Order
Denying Motion to Stay Proceedings and Compel Arbitration is reversed, and
this case is remanded to the trial court with instructions to grant Manhattan’s
motion and compel Manhattan and McCaffety to arbitration.
LEE HARRIS Justice
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 10 OPINION DELIVERED and FILED: October 16, 2025 Before Chief Justice Johnson, Justice Smith, and Justice Harris Reversed and remanded CV06
Manhattan Constr. Co. v. McCaffety Elec. Co., Inc. Page 11