Manekin Construction, Inc. v. Maryland Department of General Services

163 A.3d 214, 233 Md. App. 156, 2017 WL 2806288, 2017 Md. App. LEXIS 646
CourtCourt of Special Appeals of Maryland
DecidedJune 28, 2017
Docket0600/16
StatusPublished
Cited by1 cases

This text of 163 A.3d 214 (Manekin Construction, Inc. v. Maryland Department of General Services) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manekin Construction, Inc. v. Maryland Department of General Services, 163 A.3d 214, 233 Md. App. 156, 2017 WL 2806288, 2017 Md. App. LEXIS 646 (Md. Ct. App. 2017).

Opinion

Berger, J.

This appeal arises from the circuit court’s order affirming the decision of the Maryland Board of Contract Appeals (the “Board”) to grant summary decision in favor of the Department of General Services of Maryland (“DGS”), appellee. On June 9, 2010, appellant Manekin Construction, LLC (“Mane-kin”) was awarded a contract with DGS to construct a two-story barrack and a one-story garage for the Maryland State Police in Hagerstown, Maryland. The contract price totaled more than eight million dollars and was subject to mutually agreed upon Proposed Change Orders (“PCOs”). As we discuss in detail below, Manekin submitted PCO No. 68 to DGS requesting additional compensation during the construction of the project. After the project was complete, Manekin submitted a “Request for Equitable Settlement” on March 18, 2013. After DGS’s procurement officer denied Manekin’s claim for compensation, Manekin appealed to the Board. On September 17, 2016, during a hearing on the merits of the claim, the Board stopped the proceedings and granted DGS’s Third Motion for Summary Decision. The Circuit Court for Howard County affirmed the Board’s decision. This appeal followed.

The primary issue we must decide on appeal is whether the Board erred when it stopped the evidentiary hearing and granted summary decision in favor of DGS. More specifically, we must decide whether the Board improperly made findings of fact on disputed issues, including whether Manekin knew or should have known that DGS disputed or rejected Manekin’s request for compensation detailed in PCO No. 68. For the *159 reasons explained below, we hold that the Board erred in its decision to grant summary decision in favor of DGS.

BACKGROUND AND PROCEDURAL HISTORY

Construction of the barrack and garage took place from June 21, 2010 until the project was substantially complete on or around July 26, 2012. Approximately every two weeks throughout the construction process, Manekin and DGS officials held meetings (“Progress Meetings”) to discuss Mane-kin’s progress and other issues. During performance of the construction, Manekin encountered certain difficulties that it attributed to delays caused by DGS (among other reasons) and submitted numerous PCOs, thereby requesting additional compensation. On November 2, 2011, Manekin notified DGS of the “cumulative impact and ripple effect of’ certain factors. On December 7, 2011, Manekin submitted PCO No. 68, requesting compensation for the “additional time, and associated general conditions costs resulting from changes” discussed in the November 2, 2011 letter. A letter attached to PCO No. 68 detailed the changes requested, including the five “impact factors” that affected the cost of the project. Manekin and DGS discussed PCO No. 68 at three Progress Meetings, during which the issue was designated as “void” in the minutes for Progress Meetings and in the “PCO Log.”

After the completion of the project, on or around March 18, 2013, Manekin sent a “Request for Equitable Settlement” to DGS requesting compensation for additional time caused by the same five impact factors as outlined in PCO No. 68. DGS denied the request in a letter dated April 3, 2013. DGS indicated in its letter, “if you wish to further pursue this matter, you may do so in accordance with COMAR [Code of Maryland Regulations] 21.10.04 and the Contract Documents, General Conditions, Section 6.13, ‘Disputes and Contract Claims.’ ” On April 10, 2013, Manekin submitted its notice of claim, and on April 29, 2013, submitted its formal claim to the procurement officer. The procurement officer denied Mane-kin’s claim on November 12, 2013, finding that the notice of claim was not submitted within thirty days of when Manekin *160 knew or should have known of the basis of a claim. Manekin timely appealed to the Board.

On September 17, 2016, the Board stopped the proceedings and granted DGS’s pending Third Motion for Summary Decision, finding that Manekin knew of the basis of its claim by no later than March 1, 2012, which was more than thirty days before Manekin submitted its notice of claim. On September 21, 2015, the Board issued a written order. Manekin filed a petition for judicial review in the Circuit Court for Howard County. After a hearing on April 21, 2016, the circuit court affirmed the Board’s grant of summary decision in a written opinion issued on April 27, 2016.

DGS Contract & Relevant COMAR Provisions

The “Department of General Services General Conditions for Construction Contracts (Revised March 2007)” contains the conditions of the contract between DGS and Manekin. As required, the contract incorporates the language of COMAR 21.07.02.05-1. 1 Under a section of the contract entitled “6.13 Disputes and Contract Claims (COMAR 21.07.02.05-1),” the contract provides that it is “subject to the provisions of State Finance and Procurement Article, Title 15, Subtitle 2, Annotated Code of Maryland, and COMAR 21.10.” The following are other pertinent provisions incorporated in the contract from COMAR 21.07.02.05-1:

B. Except as otherwise provided in this contract or by law, all disputes arising under or as a result of a breach of this contract that are not disposed of by mutual agreement shall be resolved in accordance with this clause.
C. As used herein, claim means a written demand or assertion by one of the parties seeking, as a legal right, the payment of money, adjustment or interpretation of contract terms, or other relief, arising under or relating to this *161 contract. A voucher, invoice, or request for payment that is not in dispute when submitted is not a claim under this clause. However, if the submission subsequently is not acted upon in a reasonable time, or is disputed as to liability or amount, it may be converted to a claim for the purpose of this clause.
D. Within 30 days after Contractor knows or should have known of the basis for a claim relating to this contract, Contractor shall file a written notice of claim with the procurement officer.
⅜ * *
F. The claim shall set forth all the facts surrounding the controversy. Contractor, at the discretion of the procurement officer, may be afforded an opportunity to be heard and to offer evidence in support of the claim.

PCO No. 68

On December 7, 2011, Manekin submitted PCO No. 68 providing two methods for calculating the amount of compensation it asserted to be due for the five impact factors discussed in PCO No. 68—a “Change Order Analysis” and a “Measured Mile Approach.” Manekin notes in the PCO that, although these two methods produced two different time calculations, they were intended to provide a basis for further negotiations. Manekin relied on its “General Requirements Costs” of $1,315.00 per day, as provided in the original contract with DGS, and requested 96 days of “Contract Time Extension” plus other expenses, for a total of $128,134.00. Within the PCO, however, Manekin “reserve[d] the right to request compensation for all direct and indirect costs attributable to this delay impact.” At the end of PCO No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaarei Tfiloh v. Mayor & Council of Baltimore
183 A.3d 845 (Court of Special Appeals of Maryland, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
163 A.3d 214, 233 Md. App. 156, 2017 WL 2806288, 2017 Md. App. LEXIS 646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manekin-construction-inc-v-maryland-department-of-general-services-mdctspecapp-2017.