Mands Construction Co. v. Domus Inc.

Superior Court of Pennsylvania·Decided July 29, 2015·No. 94 EDA 2015·Unpublished

Opinion

J-A17033-15

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MANDS CONSTRUCTION COMPANY IN THE SUPERIOR COURT OF PENNSYLVANIA

Appellant

v.

DOMUS INC. AND PHILADELPHIA REDEVELOPMENT AUTHORITY

Appellees No. 94 EDA 2015

Appeal from the Judgment Entered February 6, 2015 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): October Term, 2012 No. 001129

BEFORE: GANTMAN, P.J., BENDER, P.J.E., and OTT, J. MEMORANDUM BY GANTMAN, P.J.: FILED JULY 29, 2015 Appellant, Mands Construction Company (“Mands”), appeals from the judgment entered in the Philadelphia County Court of Common Pleas, in favor of Appellee, Domus Inc. (“Domus”).1 We affirm.

The relevant facts and procedural history of this case are as follows.

The Board of Directors of Mount Vernon Manor, an apartment complex, hired Domus as the contractor to renovate seventy-five (75) units within thirteen (13) buildings. The contract was federally funded. Projects receiving federal funds are subject to the Davis-Bacon Act (“DBA”). The DBA requires

employers to file certified payrolls, ensures wage standards are met, and

1 The Philadelphia Redevelopment Authority (“PRA”) is not a party to this appeal.

J-A17033-15

limits the amount of hours employees can be required to work. Penalties for violating the DBA include “debarment,” which would prevent Domus from conducting future work on federally funded projects.

Domus hired Mands as the subcontractor to complete demolition work on the property. Mands bid $300,000.00 for this work, and the parties signed the contract on March 8, 2012. After Domus amended the contract and removed a portion of the work, the total bid was $276,261.00.

The text of the contract between Domus and Mands incorporated the DBA requirements. The contract also required the use of union labor. Mands did not belong to a union, and hired a negotiator to arrange for Mands to become a union company solely for this project. The negotiation failed, so Domus and Mands amended the contract to arrange for Domus to pay union benefits starting in week two while Mands continued to negotiate with the union.

Mands began the job on September 6, 2012. On September 7, 2012, a representative from the PRA visited the job site. The representative interviewed each of the workers and reviewed the wages they should receive. The representative also spoke with Gerald Washington, the manager of this project and vice-president of operations for Mands, regarding the prevailing rate of pay. Several employees of Mands subsequently called the PRA and complained they were receiving $100.00 per day instead of the prevailing wage, which was $47.85 per hour. Mands

J-A17033-15

terminated the complaining employees following these calls, allegedly for other reasons.

After Domus learned of the PRA’s involvement, Domus contacted Mands and asked for the certified payrolls. Domus sent Mands a letter on September 13, 2012, warning Mands that Domus would terminate their contract if Mands failed to follow the DBA standards. Mands did not turn over any certified payrolls. Based on copies of the fronts of checks and sign- in sheets Mands submitted, Thomas Pyle, the project manager for Domus, estimated Mands’ labor costs for the project. Mr. Pyle calculated Mands should have paid its employees $26,987.00 in wages for the 8% of the project Mands had completed to date. The checks Mands submitted reflected payment totaling only $8,965.60. On September 19, 2012, Domus sent Mr. Washington a letter terminating Mands for cause, due to its failure to comply with the DBA.

On October 9, 2012, Mands filed a complaint against Domus for wrongful termination and a request for a preliminary injunction halting all work on the project until Mands’ reinstatement as subcontractor, and for lost profits. Domus filed an answer and a brief in opposition of the preliminary injunction on October 23, 2012. On November 1, 2012, the court denied Mands’ request for a preliminary injunction. Mands amended its complaint on November 21, 2012, adding the PRA as a defendant, based on its alleged lack of meaningful review when investigating the employee complaints.

J-A17033-15

Mands amended the complaint a second time on December 27, 2012, and a third time on February 4, 2013. On February 26, 2013, Mands and the PRA stipulated Mands sought only a declaratory judgment that it did not violate the DBA but sought no monetary damages from the PRA. On March 15, 2013, Domus filed a petition to compel arbitration. Mands filed an answer on April 3, 2013. On April 23, 2013, the court denied the petition to compel arbitration. The court dismissed the PRA from the case on June 25, 2014. Dismissal of the PRA is not before us on appeal.

On August 25, 2014, the court held a non-jury trial. At trial, Mr.

Washington testified for Mands and claimed he had paid workers the prevailing wage through Paychex, a payroll agency. He submitted copies of the front of several checks as evidence. Mr. Washington testified to an estimated profit between $140,000.00 and $150,000.00 on the project based on Mands’ original bid of $300,000.00.

Mr. Pyle testified for Domus, stating Mands could not possibly have made this profit, based on labor calculations done at the prevailing rate of pay. Mr. Pyle’s calculations showed a labor cost alone of $230,000.00. He also testified to dumpster costs of about $38,000.00, which Domus would have deducted from the total contract. Mr. Pyle stated the remaining $8,000.00 would likely have gone to expenses like gas and tools, leaving Mands with no profit margin.

Following the trial, the court ordered the parties to submit proposed

J-A17033-15

findings of fact and conclusions of law. The court found in favor of Domus on October 27, 2014; the court issued Rule 236 notice on October 28, 2014. On November 7, 2014, Mands timely filed a post-trial motion for a new trial. Domus filed an answer on November 14, 2014, and on the same day, the court denied Mands’ motion. On December 11, 2014, Mands filed a premature notice of appeal with this Court. On February 6, 2015, the court entered judgment in favor of Domus.2 The court did not order, and Mands did not file, a concise statement of errors complained of on appeal pursuant to Pa.R.A.P. 1925(b).

Mands raises two issues for our review:

WHETHER THE TRIAL COURT ABUSED ITS DISCRETION IN CONCLUDING THAT [MANDS] WAS JUSTIFIABLY TERMINATED ON SEPTEMBER 19, 2012 FOR VIOLATING THE DAVIS-BACON ACT?

WHETHER THE TRIAL COURT ABUSED ITS DISCRETION WHEN IT CONCLUDED THAT [MANDS] HAD NOT

2 Ordinarily, an appeal properly lies from the entry of judgment, not from the order denying post-trial motions. See generally Johnston the Florist, Inc. v. TEDCO Constr. Corp., 657 A.2d 511, 516 (Pa.Super. 1995). Nevertheless, a final judgment entered during the pendency of an appeal is sufficient to perfect appellate jurisdiction. Drum v. Shaull Equipment and Supply, Co., 787 A.2d 1050 (Pa.Super. 2001), appeal denied, 569 Pa. 693, 803 A.2d 735 (2002). Here, the court denied Mands’ post-trial motion on November 14, 2014. Mands filed a notice of appeal on December 11, 2014, prior to the entry of final judgment. The court entered final judgment on February 6, 2015. Thus, Mands’ notice of appeal was actually premature when filed, but it related forward to February 6, 2015, the date the final judgment was entered. See Pa.R.A.P. 905(a) (stating notice of appeal shall be treated as filed on day of entry). Hence, there are no jurisdictional impediments to our review.

J-A17033-15

DEMONSTRATED AND WAS NOT ENTITLED TO DAMAGES?

(Mands’ Brief at 4).

Free access — add to your briefcase to read the full text and ask questions with AI

Mands Construction Co. v. Domus Inc., (Pa. Ct. App. 2015).

Mands Construction Co. v. Domus Inc. (Mands Construction Co. v. Domus Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chalkey v. Roush
805 A.2d 491 (Supreme Court of Pennsylvania, 2002)
Pines Plaza Bowling, Inc. v. Rossview, Inc.
145 A.2d 672 (Supreme Court of Pennsylvania, 1958)
Smith v. Penbridge Associates, Inc.
655 A.2d 1015 (Superior Court of Pennsylvania, 1995)
Kraisinger v. Kraisinger
928 A.2d 333 (Superior Court of Pennsylvania, 2007)
Biddle v. Johnsonbaugh
664 A.2d 159 (Superior Court of Pennsylvania, 1995)
Com. v. Cacho
916 A.2d 630 (Supreme Court of Pennsylvania, 2006)
Accu-Weather, Inc. v. Prospect Communications, Inc.
644 A.2d 1251 (Superior Court of Pennsylvania, 1994)
Gorski v. Smith
812 A.2d 683 (Superior Court of Pennsylvania, 2002)
Stalsitz v. Allentown Hospital
814 A.2d 766 (Superior Court of Pennsylvania, 2002)
Peck v. Delaware County Board of Prison Inspectors
814 A.2d 185 (Supreme Court of Pennsylvania, 2002)
Capoferri Ex Rel. Capoferri v. Children's Hospital of Philadelphia
893 A.2d 133 (Superior Court of Pennsylvania, 2006)
Chen v. Chen
893 A.2d 87 (Supreme Court of Pennsylvania, 2006)
Melton v. Melton
831 A.2d 646 (Superior Court of Pennsylvania, 2003)
Stamerro v. Stamerro
889 A.2d 1251 (Superior Court of Pennsylvania, 2005)
Drum v. Shaull Equipment and Supply Co.
787 A.2d 1050 (Superior Court of Pennsylvania, 2001)
Jahanshahi v. Centura Development Co., Inc.
816 A.2d 1179 (Superior Court of Pennsylvania, 2003)
Scobell Inc. v. Schade
688 A.2d 715 (Superior Court of Pennsylvania, 1997)
Kripp v. Kripp
849 A.2d 1159 (Supreme Court of Pennsylvania, 2004)
Merion Spring Co. v. Muelles Hnos. Garcia Torres, S.A.
462 A.2d 686 (Supreme Court of Pennsylvania, 1983)
MacE v. Atlantic Refining & Marketing Corp.
785 A.2d 491 (Supreme Court of Pennsylvania, 2001)