Mands Construction Co. v. Domus Inc.

CourtSuperior Court of Pennsylvania
DecidedJuly 29, 2015
Docket94 EDA 2015
StatusUnpublished

This text of Mands Construction Co. v. Domus Inc. (Mands Construction Co. v. Domus Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mands Construction Co. v. Domus Inc., (Pa. Ct. App. 2015).

Opinion

J-A17033-15

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MANDS CONSTRUCTION COMPANY IN THE SUPERIOR COURT OF PENNSYLVANIA Appellant

v.

DOMUS INC. AND PHILADELPHIA REDEVELOPMENT AUTHORITY

Appellees No. 94 EDA 2015

Appeal from the Judgment Entered February 6, 2015 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): October Term, 2012 No. 001129

BEFORE: GANTMAN, P.J., BENDER, P.J.E., and OTT, J.

MEMORANDUM BY GANTMAN, P.J.: FILED JULY 29, 2015

Appellant, Mands Construction Company (“Mands”), appeals from the

judgment entered in the Philadelphia County Court of Common Pleas, in

favor of Appellee, Domus Inc. (“Domus”).1 We affirm.

The relevant facts and procedural history of this case are as follows.

The Board of Directors of Mount Vernon Manor, an apartment complex, hired

Domus as the contractor to renovate seventy-five (75) units within thirteen

(13) buildings. The contract was federally funded. Projects receiving federal

funds are subject to the Davis-Bacon Act (“DBA”). The DBA requires

employers to file certified payrolls, ensures wage standards are met, and ____________________________________________

1 The Philadelphia Redevelopment Authority (“PRA”) is not a party to this appeal. J-A17033-15

limits the amount of hours employees can be required to work. Penalties for

violating the DBA include “debarment,” which would prevent Domus from

conducting future work on federally funded projects.

Domus hired Mands as the subcontractor to complete demolition work

on the property. Mands bid $300,000.00 for this work, and the parties

signed the contract on March 8, 2012. After Domus amended the contract

and removed a portion of the work, the total bid was $276,261.00.

The text of the contract between Domus and Mands incorporated the

DBA requirements. The contract also required the use of union labor.

Mands did not belong to a union, and hired a negotiator to arrange for

Mands to become a union company solely for this project. The negotiation

failed, so Domus and Mands amended the contract to arrange for Domus to

pay union benefits starting in week two while Mands continued to negotiate

with the union.

Mands began the job on September 6, 2012. On September 7, 2012,

a representative from the PRA visited the job site. The representative

interviewed each of the workers and reviewed the wages they should

receive. The representative also spoke with Gerald Washington, the

manager of this project and vice-president of operations for Mands,

regarding the prevailing rate of pay. Several employees of Mands

subsequently called the PRA and complained they were receiving $100.00

per day instead of the prevailing wage, which was $47.85 per hour. Mands

-2- J-A17033-15

terminated the complaining employees following these calls, allegedly for

other reasons.

After Domus learned of the PRA’s involvement, Domus contacted

Mands and asked for the certified payrolls. Domus sent Mands a letter on

September 13, 2012, warning Mands that Domus would terminate their

contract if Mands failed to follow the DBA standards. Mands did not turn

over any certified payrolls. Based on copies of the fronts of checks and sign-

in sheets Mands submitted, Thomas Pyle, the project manager for Domus,

estimated Mands’ labor costs for the project. Mr. Pyle calculated Mands

should have paid its employees $26,987.00 in wages for the 8% of the

project Mands had completed to date. The checks Mands submitted

reflected payment totaling only $8,965.60. On September 19, 2012, Domus

sent Mr. Washington a letter terminating Mands for cause, due to its failure

to comply with the DBA.

On October 9, 2012, Mands filed a complaint against Domus for

wrongful termination and a request for a preliminary injunction halting all

work on the project until Mands’ reinstatement as subcontractor, and for lost

profits. Domus filed an answer and a brief in opposition of the preliminary

injunction on October 23, 2012. On November 1, 2012, the court denied

Mands’ request for a preliminary injunction. Mands amended its complaint

on November 21, 2012, adding the PRA as a defendant, based on its alleged

lack of meaningful review when investigating the employee complaints.

-3- J-A17033-15

Mands amended the complaint a second time on December 27, 2012, and a

third time on February 4, 2013. On February 26, 2013, Mands and the PRA

stipulated Mands sought only a declaratory judgment that it did not violate

the DBA but sought no monetary damages from the PRA. On March 15,

2013, Domus filed a petition to compel arbitration. Mands filed an answer

on April 3, 2013. On April 23, 2013, the court denied the petition to compel

arbitration. The court dismissed the PRA from the case on June 25, 2014.

Dismissal of the PRA is not before us on appeal.

On August 25, 2014, the court held a non-jury trial. At trial, Mr.

Washington testified for Mands and claimed he had paid workers the

prevailing wage through Paychex, a payroll agency. He submitted copies of

the front of several checks as evidence. Mr. Washington testified to an

estimated profit between $140,000.00 and $150,000.00 on the project

based on Mands’ original bid of $300,000.00.

Mr. Pyle testified for Domus, stating Mands could not possibly have

made this profit, based on labor calculations done at the prevailing rate of

pay. Mr. Pyle’s calculations showed a labor cost alone of $230,000.00. He

also testified to dumpster costs of about $38,000.00, which Domus would

have deducted from the total contract. Mr. Pyle stated the remaining

$8,000.00 would likely have gone to expenses like gas and tools, leaving

Mands with no profit margin.

Following the trial, the court ordered the parties to submit proposed

-4- J-A17033-15

findings of fact and conclusions of law. The court found in favor of Domus

on October 27, 2014; the court issued Rule 236 notice on October 28, 2014.

On November 7, 2014, Mands timely filed a post-trial motion for a new trial.

Domus filed an answer on November 14, 2014, and on the same day, the

court denied Mands’ motion. On December 11, 2014, Mands filed a

premature notice of appeal with this Court. On February 6, 2015, the court

entered judgment in favor of Domus.2 The court did not order, and Mands

did not file, a concise statement of errors complained of on appeal pursuant

to Pa.R.A.P. 1925(b).

Mands raises two issues for our review:

WHETHER THE TRIAL COURT ABUSED ITS DISCRETION IN CONCLUDING THAT [MANDS] WAS JUSTIFIABLY TERMINATED ON SEPTEMBER 19, 2012 FOR VIOLATING THE DAVIS-BACON ACT?

WHETHER THE TRIAL COURT ABUSED ITS DISCRETION WHEN IT CONCLUDED THAT [MANDS] HAD NOT ____________________________________________

2 Ordinarily, an appeal properly lies from the entry of judgment, not from the order denying post-trial motions. See generally Johnston the Florist, Inc. v. TEDCO Constr. Corp., 657 A.2d 511, 516 (Pa.Super. 1995). Nevertheless, a final judgment entered during the pendency of an appeal is sufficient to perfect appellate jurisdiction. Drum v. Shaull Equipment and Supply, Co., 787 A.2d 1050 (Pa.Super. 2001), appeal denied, 569 Pa. 693, 803 A.2d 735 (2002). Here, the court denied Mands’ post-trial motion on November 14, 2014.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chalkey v. Roush
805 A.2d 491 (Supreme Court of Pennsylvania, 2002)
Pines Plaza Bowling, Inc. v. Rossview, Inc.
145 A.2d 672 (Supreme Court of Pennsylvania, 1958)
Smith v. Penbridge Associates, Inc.
655 A.2d 1015 (Superior Court of Pennsylvania, 1995)
Kraisinger v. Kraisinger
928 A.2d 333 (Superior Court of Pennsylvania, 2007)
Biddle v. Johnsonbaugh
664 A.2d 159 (Superior Court of Pennsylvania, 1995)
Com. v. Cacho
916 A.2d 630 (Supreme Court of Pennsylvania, 2006)
Accu-Weather, Inc. v. Prospect Communications, Inc.
644 A.2d 1251 (Superior Court of Pennsylvania, 1994)
Gorski v. Smith
812 A.2d 683 (Superior Court of Pennsylvania, 2002)
Stalsitz v. Allentown Hospital
814 A.2d 766 (Superior Court of Pennsylvania, 2002)
Peck v. Delaware County Board of Prison Inspectors
814 A.2d 185 (Supreme Court of Pennsylvania, 2002)
Capoferri Ex Rel. Capoferri v. Children's Hospital of Philadelphia
893 A.2d 133 (Superior Court of Pennsylvania, 2006)
Chen v. Chen
893 A.2d 87 (Supreme Court of Pennsylvania, 2006)
Melton v. Melton
831 A.2d 646 (Superior Court of Pennsylvania, 2003)
Stamerro v. Stamerro
889 A.2d 1251 (Superior Court of Pennsylvania, 2005)
Drum v. Shaull Equipment and Supply Co.
787 A.2d 1050 (Superior Court of Pennsylvania, 2001)
Jahanshahi v. Centura Development Co., Inc.
816 A.2d 1179 (Superior Court of Pennsylvania, 2003)
Scobell Inc. v. Schade
688 A.2d 715 (Superior Court of Pennsylvania, 1997)
Kripp v. Kripp
849 A.2d 1159 (Supreme Court of Pennsylvania, 2004)
Merion Spring Co. v. Muelles Hnos. Garcia Torres, S.A.
462 A.2d 686 (Supreme Court of Pennsylvania, 1983)
MacE v. Atlantic Refining & Marketing Corp.
785 A.2d 491 (Supreme Court of Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Mands Construction Co. v. Domus Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mands-construction-co-v-domus-inc-pasuperct-2015.