Manaia v. Potomac Electric Power Co.

163 F. Supp. 671, 1958 U.S. Dist. LEXIS 4015
CourtDistrict Court, D. Maryland
DecidedJuly 18, 1958
DocketCiv. A. No. 9057
StatusPublished
Cited by5 cases

This text of 163 F. Supp. 671 (Manaia v. Potomac Electric Power Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manaia v. Potomac Electric Power Co., 163 F. Supp. 671, 1958 U.S. Dist. LEXIS 4015 (D. Md. 1958).

Opinion

R. DORSEY WATKINS, District Judge.

From adverse judgments on jury verdicts for personal injuries to five of the plaintiffs and for the deaths of two other persons,1 from current transmitted through the boom of a crane which came into close proximity with a power line of the defendant, Potomac Electric Power Company (Pepco), that company in due time moved for judgment n. o. v. or in the alternative for a new trial. It will therefore be necessary to review the facts in the aspects most favorable to plaintiffs, and determine whether they afford a reasonable basis for the verdicts, in light of the admonition of the Court of Appeals of this Circuit as to the limited authority of trial judges to disturb jury verdicts. Burcham v. J. P. Stevens & Co., 4 Cir., 1954, 209 F.2d 35, 38.

[673]*673Facts

Pepeo is a public utility company, engaged in the generation and distribution of electric energy. Among its facilities are a sub-station in Wheaton, Maryland, on the Old Bladensburg Road, near its intersection with Fern Street. A 33,000 volt, three-wire electric line, supported by cross-arms on poles, crosses Fern Street at approximately 30 feet south of Old Bladensburg Road, and enters the sub-station. The lowest wire at its critical point is 31 to 3½ feet above the surface of Fern Street.

In the first part of 1955 Fern Street was an unpaved dirt road, extending for approximately one and one-half blocks south of Old Bladensburg Road. Montgomery County decided to have Fern Street paved, and on February 15, 1955, sent notice to abutting property owners, including Pepeo, of a paving assessment. On June 8, 1955, a general plan of the proposed paving of Fern Street, and the adjacent territory, was sent to utility companies, including Pepeo, having facilities in the vicinity. This called for the paving of Fern Street from Old Bladensburg Road south. While most of the paving was to be of concrete, consisting of four ten-feet wide strips, the northern portion, including the part directly2 under Pepco’s 33,000 volt line, was to be paved with macadam. It required that “arrangements be made for prompt relocation of such utilities as may be fouled by proposed street improvements,” and stated that it was hoped work on the street would be started not later than June 20, 1955.

About the middle of July, 1955, the contract for the paving of Fern Street was closed with Sligo Engineering Company (Sligo), employer of the plaintiffs, and notice to proceed was given it.

On July 20, 1955, a revised plan of Fern Street was sent Pepeo. This was identical, as far as measurements were concerned, with the print in the letter of June 8, 1955, but contained the legend “use cone.3 finishing machine on slabs.”

Fern Street was graded by Sligo during the period August 1-4, 1955, and some of Pepco’s poles were moved by Pepeo during this period. Among these was the pole on the west side of Fern Street carrying the 33,000 volt wires. This was moved six-tenths of a foot west, so as to place it a distance of two and one-tenth feet from the curb, because of proximity to the paving operation. . The moving of the pole was not related to any relocation of the overhead wires, and at no time prior to the casualties was Pepeo ever asked or directed by anyone to change the location of its overhead Fern Street wires, or to reduce or cut off the voltage running through them.

Shortly before the first of September 1955 a representative of Pepeo was present on the then graded but unpaved Fern Street. He was met by a Montgomery County inspector, who questioned him about the underground facilities of Pepeo in the street. Specifically he was asked about the voltage of the wires in the underground conduits (which are 13,-200-volt insulated lines). Nothing was asked or said about the voltage in the overhead uninsulated lines. At that time no crane was present on the job, nor is there any evidence that a crane had been on Fern Street at any previous time.

At a time fixed only as one week or one day before September 2, 1955, Louis [674]*674Manaia 4 brought in a crane, took a concrete finishing machine off a trailer, and put it on the east shoulder of Fern Street, south of the 33,000 volt lines.

In a paving project of this kind, after grading, rails or forms are laid. These serve the dual purpose of fixing the width and approximate depth of the lane or slab of concrete poured, and of supporting a concrete finishing machine. Such machines, specified for use in this paving, are often used in concrete paving. These are four-wheeled machines, weighing a ton or more. They are approximately 12 feet long, adjustable in width to that of the lane or strip of concrete being laid and to be finished, are equipped with a chain driven blade, and are self-propelled. Their wheels run on the rails or sides of the lanes. The blade smooths, or “finishes”, the surface of the poured concrete. When one slab is finished, they can be driven off under their own power. Normally, one lane is then skipped, and work continued from either end of the next lane.

While on September 2, 1955, a few finishing machines were equipped with hydraulic lifts so that no extra equipment was needed to place them on the rails, it was customary to position them by use of either a front-end loader; an excavating shovel; the boom of a shovel; or a crane, the latter being most frequently used. In such cases the finisher would ordinarily be lifted by a metal cable attached to the end of the cable boom.

Sligo’s crane, used to place the finisher, prior to September 2, 1955, on the east side of Fern Street south of the 33,000 volt wires was a new one, purchased in July 1955, and had a 40-foot boom. It was not equipped with an electric signal-ling device which would give warning of the approach of the boom to electrically charged wires.

Sligo had other paving work in the general vicinity of Fern Street, which it intended to finish before starting the concreting of Fern Street. No actual notice was given Pepeo by anyone as to when the concrete work would begin on Fern Street, or that a crane would be used.5

On September 2, 1955, at about 10:30 a. m., Sligo’s crane was driven to Fern Street by George Manaia, one of the plaintiffs. It was backed in, stopping with the front, or truck, almost at Bladensburg Road. The crane itself was under the control of Louis Manaia, George’s father, and a defendant. He had been instructed by Manuel Leal, superintendent of Sligo, to put the concrete finishing machine, brought in the day or week before, on the forms. The spot where the finishing machine was to be placed, and the location of the crane, were determined by Leal.

. The Montgomery County inspector, who first learned “positively” that a crane would be used when it came onto Fern Street that morning, called to Leal’s attention that the crane would be working under wires. Although the inspector did not know the voltage of the wires, he cautioned Leal, but would have permitted Leal to proceed, even if the inspector had known the wires carried high voltage.

The point selected by Leal for the placing of the finishing machine on the form was north of where the concrete would begin.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
163 F. Supp. 671, 1958 U.S. Dist. LEXIS 4015, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manaia-v-potomac-electric-power-co-mdd-1958.