Judgment rendered June 29, 2022. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 54,550-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
MANAGEMENT GROUP FOUR, Plaintiff-Appellant L.L.C.
versus
L B ELECTRIC, L.L.C. Defendant-Appellee
Appealed from the Forty-Second Judicial District Court for the Parish of DeSoto, Louisiana Trial Court No. 81,360
Honorable Nicholas E. Gasper, Judge
HYMEL, DAVIS & PETERSEN, L.L.C. Counsel for Appellant, By: Michael Reese Davis Management Seven, Tim P. Hartdegen L.L.C.
LAW OFFICE OF KATHLEEN E. PETERSEN, LLC By: Kathleen E. Petersen
LUNN IRION LAW FIRM, LLC Counsel for Appellee By: James A. Mijalis W. Orie Hunter, III
Before PITMAN, THOMPSON, and MARCOTTE, JJ.
THOMPSON, J., concurs with written reasons. PITMAN, J.
Management Seven, L.L.C. (“M7”)1 appeals the judgment of the trial
court, which sustained a peremptory exception of peremption and found that
six back-up generators in several nursing homes became component parts of
the immovable after their installation and that suits on their defective
installation were subject to a five-year peremptive period. For the following
reasons, we affirm.
FACTS
Between June and December 2011, M7, a company domiciled in
DeSoto Parish, was the managing agent for six Louisiana health care
facilities in various parishes in North Louisiana. These facilities were
nursing homes and rehabilitation centers located in the parishes of DeSoto
(2), Vernon (1), East Carroll (1), Allen (1), and Calcasieu (1). During that
time, M7 purchased “standby,” or back-up, emergency generators for each
of the six health care facilities. The cost of the generators was more than
$489,000. After the purchase of the generators, M7 entered into oral
contracts with L.B. Electric, L.L.C. (“LB”) to install each of these generators
in accordance with professional standards, including the mandatory
standard, electrical, safety, building and fire codes.
M7 expected LB to properly install each generator to the
manufacturer’s specification and in full compliance with all required
mandatory standards and codes. After the generators were installed between
August 2011 and May 2012, M7 began using them for their intended
1 The original petition filed in this matter incorrectly named Management Four, L.L.C. as the plaintiff, but an amended petition corrected plaintiff’s name to Management Seven, L.L.C. purposes. M7 claimed that between 2017 and 2019, there were problems
with four of the six generators. ARCCO of Baton Rouge performed repairs
on those four generators at a cost of $76,241.72. The amount alleged due
included the cost of repairs and the replacement of the ATS switch on all of
the generators (this switch on the generator in Calcasieu Parish was replaced
three times) and the rental of temporary replacement generators to use while
the back-up generators were down for repairs. When ARCCO repaired the
Calcasieu generator in late May 2019, it informed M7 that the generator had
experienced “multiple controller failure,” possibly due to the lack of proper
grounding.
At a cost of $4,100, M7 hired an electrical engineer to inspect the
generators at all six facilities, and he found that none of them installed by
LB between 2011 and 2012 were properly grounded. The engineer reported
that among the hidden defects included were ground rods missing between
the generator and transfer switches and/or existing switchboards.
M7 hired Scotty Carline Electric, Inc., of Many, Louisiana, to fix the
grounding defects of all six generators at a cost of $52,335.05. In May
2020, M7 filed suit against LB for breach of contract and negligent
installation, alleging that it was liable to them for the costs of $76,241.72 for
the 2017-2019 repairs and rentals, $4,100 for the engineer who inspected the
generators and $52,335.05 to correct the installation problems.
LB answered and filed a peremptory exception raising the objection of
peremption based on La. R.S. 9:2772. It argued that the statute imposed a
five-year peremptive period within which plaintiffs had to bring an action
against any person performing or furnishing the design, planning,
supervision, inspection or observation of construction or the construction of 2 immovables, or improvement to immovable property. The statute also states
that the five-year period ends at the fifth anniversary of the date of registry
in the mortgage office of acceptance of the work by the owner or, if no
acceptance is recorded within six months from the date the owner has
occupied or taken possession of the improvement, in whole or in part, more
than five years after the improvement has been occupied by the owner.
The trial court heard and sustained the exception of peremption in
favor of LB, finding that the generators would be considered a component
part of the immovable and that La. R.S. 9:2772 operated to perempt M7’s
claims after five years.
M7 appeals the ruling of the trial court sustaining the exception of
peremption and dismissing its suit against LB.
DISCUSSION
M7 argues that the trial court erred in holding that the installation of
the generators constituted construction of an immovable or an improvement
to an immovable within the meaning of La. R.S. 9:2772 and in finding that
the peremptive period of five years found in La. R.S. 9:2772 applied to
defeat its cause of action against LB. It contends that the emergency
generators are not immovables; and for the statute to apply, they have to be
component parts of the healthcare facilities under La. C.C. art. 466. It
argues that by their nature, the back-up generators are not permanently
attached and do not complete the buildings so as to become component parts
of the facilities.
M7 further argues that La. C.C. art. 466 states that when a decision is
made regarding whether something is a component part, the specific use of a
building is not to be considered, nor is any specific industrial or commercial 3 activity that may happen to be conducted within the building to be
considered. Extrapolating from that statement, it contends that the issue
presented is whether, according to societal expectations, a back-up generator
serves to complete a commercial building. It asserts that these emergency
generators do not and are simply useful in the event of a power outage and
are not component parts of the healthcare facilities. It argues that they
remain movables, and La. R.S. 9:2772 only applies to immovables.
LB argues that under La. C.C. art. 466, the back-up generators qualify
as both improvements to immovable property and as component parts of the
buildings to which they provide energy in times of electrical system failures.
It contends that they are component parts of the immovable electrical
systems to which they are attached and that the judgment of the trial court
was correct in interpreting both La. C.C. art. 466 and La. R.S. 9:2772 to find
that M7’s causes of action are perempted.
LB asserts that the last payment made by a facility in DeSoto Parish
was May 14, 2012, and that the original petition was filed on May 12, 2020,
years after the five-year peremptive period provided for in La. R.S. 9:2772.
It argues that M7 failed to meet its burden of proving its causes of action
Free access — add to your briefcase to read the full text and ask questions with AI
Judgment rendered June 29, 2022. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 54,550-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
MANAGEMENT GROUP FOUR, Plaintiff-Appellant L.L.C.
versus
L B ELECTRIC, L.L.C. Defendant-Appellee
Appealed from the Forty-Second Judicial District Court for the Parish of DeSoto, Louisiana Trial Court No. 81,360
Honorable Nicholas E. Gasper, Judge
HYMEL, DAVIS & PETERSEN, L.L.C. Counsel for Appellant, By: Michael Reese Davis Management Seven, Tim P. Hartdegen L.L.C.
LAW OFFICE OF KATHLEEN E. PETERSEN, LLC By: Kathleen E. Petersen
LUNN IRION LAW FIRM, LLC Counsel for Appellee By: James A. Mijalis W. Orie Hunter, III
Before PITMAN, THOMPSON, and MARCOTTE, JJ.
THOMPSON, J., concurs with written reasons. PITMAN, J.
Management Seven, L.L.C. (“M7”)1 appeals the judgment of the trial
court, which sustained a peremptory exception of peremption and found that
six back-up generators in several nursing homes became component parts of
the immovable after their installation and that suits on their defective
installation were subject to a five-year peremptive period. For the following
reasons, we affirm.
FACTS
Between June and December 2011, M7, a company domiciled in
DeSoto Parish, was the managing agent for six Louisiana health care
facilities in various parishes in North Louisiana. These facilities were
nursing homes and rehabilitation centers located in the parishes of DeSoto
(2), Vernon (1), East Carroll (1), Allen (1), and Calcasieu (1). During that
time, M7 purchased “standby,” or back-up, emergency generators for each
of the six health care facilities. The cost of the generators was more than
$489,000. After the purchase of the generators, M7 entered into oral
contracts with L.B. Electric, L.L.C. (“LB”) to install each of these generators
in accordance with professional standards, including the mandatory
standard, electrical, safety, building and fire codes.
M7 expected LB to properly install each generator to the
manufacturer’s specification and in full compliance with all required
mandatory standards and codes. After the generators were installed between
August 2011 and May 2012, M7 began using them for their intended
1 The original petition filed in this matter incorrectly named Management Four, L.L.C. as the plaintiff, but an amended petition corrected plaintiff’s name to Management Seven, L.L.C. purposes. M7 claimed that between 2017 and 2019, there were problems
with four of the six generators. ARCCO of Baton Rouge performed repairs
on those four generators at a cost of $76,241.72. The amount alleged due
included the cost of repairs and the replacement of the ATS switch on all of
the generators (this switch on the generator in Calcasieu Parish was replaced
three times) and the rental of temporary replacement generators to use while
the back-up generators were down for repairs. When ARCCO repaired the
Calcasieu generator in late May 2019, it informed M7 that the generator had
experienced “multiple controller failure,” possibly due to the lack of proper
grounding.
At a cost of $4,100, M7 hired an electrical engineer to inspect the
generators at all six facilities, and he found that none of them installed by
LB between 2011 and 2012 were properly grounded. The engineer reported
that among the hidden defects included were ground rods missing between
the generator and transfer switches and/or existing switchboards.
M7 hired Scotty Carline Electric, Inc., of Many, Louisiana, to fix the
grounding defects of all six generators at a cost of $52,335.05. In May
2020, M7 filed suit against LB for breach of contract and negligent
installation, alleging that it was liable to them for the costs of $76,241.72 for
the 2017-2019 repairs and rentals, $4,100 for the engineer who inspected the
generators and $52,335.05 to correct the installation problems.
LB answered and filed a peremptory exception raising the objection of
peremption based on La. R.S. 9:2772. It argued that the statute imposed a
five-year peremptive period within which plaintiffs had to bring an action
against any person performing or furnishing the design, planning,
supervision, inspection or observation of construction or the construction of 2 immovables, or improvement to immovable property. The statute also states
that the five-year period ends at the fifth anniversary of the date of registry
in the mortgage office of acceptance of the work by the owner or, if no
acceptance is recorded within six months from the date the owner has
occupied or taken possession of the improvement, in whole or in part, more
than five years after the improvement has been occupied by the owner.
The trial court heard and sustained the exception of peremption in
favor of LB, finding that the generators would be considered a component
part of the immovable and that La. R.S. 9:2772 operated to perempt M7’s
claims after five years.
M7 appeals the ruling of the trial court sustaining the exception of
peremption and dismissing its suit against LB.
DISCUSSION
M7 argues that the trial court erred in holding that the installation of
the generators constituted construction of an immovable or an improvement
to an immovable within the meaning of La. R.S. 9:2772 and in finding that
the peremptive period of five years found in La. R.S. 9:2772 applied to
defeat its cause of action against LB. It contends that the emergency
generators are not immovables; and for the statute to apply, they have to be
component parts of the healthcare facilities under La. C.C. art. 466. It
argues that by their nature, the back-up generators are not permanently
attached and do not complete the buildings so as to become component parts
of the facilities.
M7 further argues that La. C.C. art. 466 states that when a decision is
made regarding whether something is a component part, the specific use of a
building is not to be considered, nor is any specific industrial or commercial 3 activity that may happen to be conducted within the building to be
considered. Extrapolating from that statement, it contends that the issue
presented is whether, according to societal expectations, a back-up generator
serves to complete a commercial building. It asserts that these emergency
generators do not and are simply useful in the event of a power outage and
are not component parts of the healthcare facilities. It argues that they
remain movables, and La. R.S. 9:2772 only applies to immovables.
LB argues that under La. C.C. art. 466, the back-up generators qualify
as both improvements to immovable property and as component parts of the
buildings to which they provide energy in times of electrical system failures.
It contends that they are component parts of the immovable electrical
systems to which they are attached and that the judgment of the trial court
was correct in interpreting both La. C.C. art. 466 and La. R.S. 9:2772 to find
that M7’s causes of action are perempted.
LB asserts that the last payment made by a facility in DeSoto Parish
was May 14, 2012, and that the original petition was filed on May 12, 2020,
years after the five-year peremptive period provided for in La. R.S. 9:2772.
It argues that M7 failed to meet its burden of proving its causes of action
were not perempted because the petition alleges that the health care facilities
began using the six back-up generators for their intended purposes as soon
as they were installed.
La. R.S. 9:2772 states, in pertinent part, as follows:
A. Except as otherwise provided in this Subsection, no action, whether ex contractu, ex delicto, . . . shall be brought against any person performing or furnishing . . . the design, planning, supervision, inspection, or observation of construction or the construction of immovables, or improvement to immovable property [.]
4 (1)(a) More than five years after the date of registry in the mortgage office of acceptance of the work by owner.
(b) If no such acceptance is recorded within six months from the date the owner has occupied or taken possession of the improvement, in whole or in part, more than five years after the improvement has been thus occupied by the owner.
Peremption is a period of time fixed by law for the existence of a
right. La. C.C. art. 3458. The right is extinguished upon the expiration of
the peremptive period. Id. When the peremptive period has run, the cause
of action itself is extinguished unless timely exercised. Rando v. Anco
Insulations Inc., 08-1163 (La. 5/22/09), 16 So. 3d 1065. The following rules
governing the burden of proof as to prescription apply to peremption. Id. If
prescription is evident on the face of the pleadings, the burden shifts to the
plaintiff to show the action has not prescribed. Id. If evidence is introduced
at the hearing on the peremptory exception of prescription, the district
court’s findings of fact are reviewed under the manifest error-clearly wrong
standard of review. Id. If the findings are reasonable in light of the record
reviewed in its entirety, an appellate court may not reverse even though
convinced that had it been sitting as the trier of fact, it would have weighed
the evidence differently. Id.
Tracts of land and their component parts are immovables. La. C.C.
art. 462. Things incorporated into a tract of land, a building or other
construction so as to become an integral part of it, such as building
materials, are its component parts. La. C.C. art. 465.
La. C.C. art. 466 provides in part as follows:
Things that are attached to a building and that, according to prevailing usages, serve to complete a building of the same general type, without regard to its specific use, are its 5 component parts. Component parts of this kind may include doors, shutters, gutters, and cabinetry, as well as plumbing, heating, cooling, electrical, and similar systems.
Things that are attached to a construction other than a building and that serve its principal use are its component parts.
In Chesney v. Entergy Louisiana, L.L.C., 49,816 (La. App. 2 Cir.
5/27/15), 166 So. 3d 1204, the court concluded that an overhead high
voltage power line involved in plaintiff’s injury was an immovable, or
improvement to an immovable, within the meaning of La. R.S. 9:2772. The
Chesney court concluded that the power cable attached to a pole imbedded
in the ground was an immovable and was deemed to be a component part
within the meaning of La. C.C. art. 465. The court opined that the power
cable carried electricity to the landfill and served the power pole’s principal
use. A purchaser of the landfill would expect the power cable to be
conveyed with the property along with the rest of the power system, and the
power was essential to the facility’s operation. Hence, the cable was a
component part of the power system under La. C.C. art. 466. After finding
that the cable and pole were component parts of the immovable, this court
stated:
Because the power system, including the uninsulated power line that Chesney’s truck contacted, was an improvement to an immovable within the meaning of La. R.S. 9:2772, the trial court correctly determined that the plaintiffs’ claims that fall within the scope of this article are perempted.
In the case at bar, we find that the emergency generators installed by
LB became component parts of the electrical system of the nursing homes.
The generators were hard-wired into the electrical systems of the buildings
to which they provided back-up power when the systems failed, as well as
having a natural gas connection to power the generators. Furthermore, as in
6 Chesney, supra, a purchaser of the nursing homes/rehabilitation centers
would expect these generators to be conveyed in a sale. The generators were
critical to the continuing operation of the health care facilities when the
original systems failed.
We also find that under La. R.S. 9:2772, M7’s causes of action have
been perempted by the passage of more than five years from the date the
improvement was occupied by the owner. A review of the pleadings in this
case indicate that the last payment M7 made to LB on behalf of the DeSoto
facility was May 14, 2012. The original petition in this case was filed on
May 12, 2020, far later than the five-year preemptive period found in La.
R.S. 9:2772.
This assignment of error is without merit.
CONCLUSION
For the foregoing reasons, the judgment of the trial court sustaining
the peremptory exception of peremption in favor of L.B. Electric, L.L.C, and
dismissing the suit of Management Seven, L.L.C., is affirmed. Costs of this
appeal are assessed to Management Seven, L.L.C.
AFFIRMED.
7 THOMPSON, J., concurring.
I write separately to acknowledge that the advent of technology is
shrinking the size and enhancing the efficiency of alternative power sources,
such as generators and battery back-ups. Generators have historically been
cumbersome to attach and disconnect. The installation or removal process
may have caused damage to the immovable the generator serves. In those
former instances, a generator lost its nature as a movable and rightfully
became a component part of the immovable.
We have witnessed the development and exponential growth in the
power and life of batteries – from flashlights, to vehicles, to home solar
panel systems. We have progressed from satellite antennae being the size of
a vehicle to small and portable systems, such as streaming via WIFI.
Likewise, there have been significant advancements in technology that
reduce the size and increase the output of standby generators. Generators
are now designed for easy installation and replacement or removal. Today’s
generators might spend their entire existence a good distance away from the
immovable, and are easily disconnected from that distance without ever
approaching the immovable. Certainly, continuation of these technological
developments will necessitate a serious review of what is a component part
and what is not. Modern inventions and improvements thereon do not
necessarily fit neatly into the current language of La. C. C. art. 466, and this
problem will intensify as time passes and technology advances.
I concur in the result of this matter, because regardless of any desire to
delve into considerations such as independent existence of the generator, its
remote location from the immovable, and the ease of removal and
replacement, there is no escaping the conclusion that when the power goes 1 out and the generator cranks and starts to send power to the building, it could
easily be considered part of the “electrical system” of the immovable. A
generator’s classification as a component part of an immovable may not
have been envisioned or contemplated by La. C. C. art. 466, but that is what
the clear and unambiguous language of the code article provides.
Technological advances will continue to require continued discussion and
analysis. As for the specific facts in the matter before us, I concur this is the
proper result.