Malo v. BOWLERS COUNTRY CLUB. INC.

283 N.E.2d 806, 152 Ind. App. 413, 1972 Ind. App. LEXIS 997
CourtIndiana Court of Appeals
DecidedJune 16, 1972
Docket571A93
StatusPublished
Cited by6 cases

This text of 283 N.E.2d 806 (Malo v. BOWLERS COUNTRY CLUB. INC.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Malo v. BOWLERS COUNTRY CLUB. INC., 283 N.E.2d 806, 152 Ind. App. 413, 1972 Ind. App. LEXIS 997 (Ind. Ct. App. 1972).

Opinion

Sullivan, J.

The action was brought below by plaintiff-appellant (Malo) against defendant-appellee (Bowlers) to foreclose a mechanics lien. The lien was filed after Bowlers *414 allegedly failed to pay Malo for architectural services rendered in connection with the erection of a bowling, recreation and restaurant facility. Trial was had to the court without a jury. On December 24, 1970, judgment was entered in favor of the defendant Bowlers. Malo timely filed his motion to correct errors, which on March 2,1971 was overruled.

In substance, appellant-Malo has presented two issues for resolution:

(1) Whether the evidence established as a matter of law Malo’s right to recover a fee based upon 70% of the estimated construction cost. 1
(2) Whether the trial court properly excluded evidence of volunteer, i.e., unpaid, work done subsequent to the completion of the contract covering the erection of the building structure sought to be adduced by plaintiff during cross-examination of defendant’s witness.

The appeal here is by the plaintiff from a negative judgment. The burden is therefore upon appellant to show that the decision of the trial court is contrary to law. Pokraka v. Lummus Co. (1951), 230 Ind. 523, 104 N. E. 2d 669. Senst v. Bradley (1971), 150 Ind. App. 113, 275 N. E. 2d 573. Stated differently, it is not necessary that there be evidence to sustain a negative judgment. The standard to be applied in appellate review of a negative judgment was stated in Senst, supra:

“It is only where the évidence is without conflict and leads to only one conclusion and the Trial Court reached a contrary conclusion that the decision will be disturbed as contrary to law, i.e.', that is where it affirmatively appears that reasonable men could not have arrived at the same judgment or conclusion. In this context, this Court, as a reviewing Court, will consider only the evidence most favorable to the decision of the Trial Court.” (Citations omitted) 275 N. E. 2d 576.

*415 APPELLANT HAS NOT SHOWN HIS RIGHT TO RECOVERY AS A MATTER OF LAW

Article 6 of the contract between the parties expressly states that project construction cost which is the primary factor in computing the architect’s fee would'be determined, if possible, by the “lowest acceptable bona fide Contractor’s proposal received for any or all portions of the project.” Article 6 reads in part as follows:

“6.1 Project Construction as herein referred to means the total cost of all work designed or specified by the Architect, but does not include any payments made to the Architect or consultants.
6.2 Project Construction Cost shall be based upon one of the following sources ivith precedence in the order listed:
6.2.1 Lowest acceptable bona fide Contractor’s proposal received for any or all portions of the Project.
6.2.2 Semi-Detailed or Detailed Estimate of Project Construction Cost as defined in paragraph 6.4 below.
6.2.3 The Architect’s latest Statement of Probable Project Construction Cost based on current area, volume or other unit costs.
6.4 If a fixed limit of Project Construction Cost is stated herein, or if otherwise authorized by the Owner, estimates of the Probable Project Construction Cost prepared in semi-detailed or detailed form by an experienced estimator will be secured by the Architect during the Design Development or Construction Document Phase.” (Emphasis supplied.)

Bowlers argues that actual cost of work completed equals something “in the neighborhood of $43,000.” As a result of detailed examination of the record we have been able to extract costs which approximate that amount:

Concord Builders__________________________ $34,183.00
(less $1189 for galvanized roof in lieu of Butler-
Cote finish)_______________________________________$32,994.00
N & S Concrete Construction______________________$ 5,525.00
Valley Concrete________________________________ 1,466.86
Nelson Engineering_____________________________ 1,081.34
Total actual cost____________________________$41,081.34

*416 The contract between Malo and Bowlers provided under Article 8 that payments to the architect were to be made in “proportion to services performed” and in accordance with the following percentages at the completion of the various enumerated phases of the project:

Execution of the Agreement __________ 5%
Schematic Design Phase____________________________________ 15 %
Design Development Phase _______________________ 35%
Construction Documents Phase_____________________ 75%
Receipt of Bids ..._________________________________80%
Construction Phase ____________________________100%

In connection therewith, Article 10 of the contract clearly states that either party has the right to terminate the contract and provides that in such event due to the fault of other than the architect, the architect shall be paid for services to termination date. 2 Malo argues that his services were terminated during the construction phase of the contract and that a reading of Articles 8 and 10 in pari materia supports his claim for 85% of his fee less 15% representing mechanical services not performed. Applying Malo’s basic fee rate of 4i/^% of the project construction cost, plus an additional 2% for the several separate project contracts let, 3 to a total actual cost of $41,081.34 results in an allowable contract fee of $1869.20 if we were to assume as stated by Malo that he completed 70% of his work.

Bowlers argues, however, that the applicable percentage due Malo is limited to the last phase completed by him, i.e., the “design development phase” representing 35% of completed architectural work. The record sustains Bowlers’ con *417 tention. The certificate of compliance contained a notation that certain plans required at the “construction documents phase” were to follow; however, there is a dispute whether those plans were ever submitted. The trial court quite obviously found from the conflicting evidence that Malo had failed to prove completion of 70% of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Herman
460 N.E.2d 1021 (Indiana Court of Appeals, 1984)
Barbre v. Indianapolis Water Co.
400 N.E.2d 1142 (Indiana Court of Appeals, 1980)
Wyneken v. Long
400 N.E.2d 1147 (Indiana Court of Appeals, 1980)
L. S. Ayres & Co. Et Al. v. IPALCO Et Al.
351 N.E.2d 814 (Indiana Court of Appeals, 1976)
Kody Engineering Co. v. Fox & Fox Insurance Agency, Inc.
303 N.E.2d 307 (Indiana Court of Appeals, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
283 N.E.2d 806, 152 Ind. App. 413, 1972 Ind. App. LEXIS 997, Counsel Stack Legal Research, https://law.counselstack.com/opinion/malo-v-bowlers-country-club-inc-indctapp-1972.