Mallard v. Duke

126 S.E. 525, 131 S.C. 175, 1925 S.C. LEXIS 101
CourtSupreme Court of South Carolina
DecidedFebruary 12, 1925
Docket11682
StatusPublished
Cited by4 cases

This text of 126 S.E. 525 (Mallard v. Duke) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mallard v. Duke, 126 S.E. 525, 131 S.C. 175, 1925 S.C. LEXIS 101 (S.C. 1925).

Opinion

The opinion of the Court was delivered by

Mr. Justice Marion.

“This is an action for the recovery of the rental of a brick building leased by plaintiff to defendants. The complaint alleges that on May 15, 1920, the parties entered into a written lease for a period of three years, beginning June 1, 1920, or as soon thereafter as the building should be completed ; that the building was completed and defendants went into possession on July 1, 1920; that they remained in possession and paid the rent up to January 31, 1922, but failed to pay.the rent for the period from February 1, 1922, to January 31, 1923, for the collection of which the action is brought.”

The defendants, by their answer, “denied liability on two grounds: (1) Because the landlord had failed to complete the building according to agreement, by reason of which failure the building turned out to be unfit for use, and the tenants vacated on that account; (2) because the building became untenantable within the meaning of the lease, on which account they vacated, and were thereby absolved from further liability for rent under the terms of the lease. The tenants also interposed a counterclaim based on the fact that they had put an expensive tile floor in the building, the value of which was lost to them by reason of their having to vacate.”

The rulings of the trial Court which are charged to be erroneous, and the contentions thereupon predicated, are thus stated by appellants’ counsel:

“His Honor, the trial Judge, let in the evidence to sustain the first defense and the counterclaim, but, when he refused to direct a verdict for plaintiff, he stated that he would not submit to the jury either the first defense or the counterclaim, but only the second defense, and that, in connection with it, he would charge the jury that, even if they found the premises were untenantable, their verdict should be for *183 the plaintiff for the full amount of the rent if they found that defendants had waived their right to vacate by remaining in possession after discovering the condition of the premises. When he came to charge the jury, these were the only issues submitted to them. Defendants contend that his Honor was in error in withdrawing the first defense and the counterclaim from the jury, and in charging that the law of waiver was applicable to the second defense. There are other questions raised by the appeal, which will be hereafter considered, but the main questions are those just stated.”

The facts, broadly outlined, out of which the controversy arises, are as follows: The lease was of a two-story brick building then in process of erection, entered into on.May 15, 1920, for a term of three years and provided that rent should “commence the 1st day of June, 1920, or as soon as the building is completed.” The defendants were permitted, over plaintiff’s objection, to introduce testimony to the effect that, prior to or at the time of the making of the written contract, the plaintiff’s agent assured them that the building “would be first class in every particular and up to date.” The building was leased for the purpose of operating therein a tearoom or restaurant. Before signing the lease the defendants inspected the building. One of the defendant’s witnesses testified:

“The lease was signed up after we had gone over the building; the walls were up and the roof was on, but the floors had not been put down. The outside part was finished, but there was considerable inside work to do.”

“Before taking possession the premises were frequently visited by defendants. On July 1, 1920, defendants took possession. From the outset they failed to pay the rent stipulated in the contract. The plaintiff allowed a deduction from the July rent of $125, on account of delay. A controversy as to alleged defects in the building arose and continued until December 31, 1920, on which date a com *184 promise settlement was effected. By the terms of this settlement, conducted by the attorneys of the respective parties, the plaintiff made an additional allowance, or deduction, for rent due under the contract, of $650, and the defendants agreed “to resume payment of rent, according to the terms of the lease, on January 1, 1921.” Thereafter they paid the rent each month. On January 1, 1921, the defendants sublet the first floor to one Gaddy, and thereafter operated their tearoom on the second floor until March 1, 1921, when they moved to the Ottaray Hotel and sublet the second floor. On February 1, 1922, Gaddy vacated. Defendants thereupon repudiated the lease, tendered the keys to the building,- and refused to make further payments of rent. Subject, as she avers, to the understanding that such action should be without prejudice to either side, plaintiff undertook to relet the property. Subsequently this action was brought to recover the rent alleged to be due by defendants for the period of time covered by the lease, commencing February 1, 1922, when the premises were abandoned.

Assuming, for the purpose of this opinion, that the points made and the questions discussed in appellants’ printed argument are sufficiently raised by the exceptions, those contentions will be considered in the order presented in argument.

The first defense, directed to the contention, that there had been a failure on the part of the plaintiff to complete the building in accordance with the representation of the plaintiff’s agent that the completed building would be first class and modern in every respect, is predicated upon evidence which appellants say was to this effect:

“That the landlord’s architect planned to waterproof the exposed western' wall with plaster board and cement, to build up the flues above the parapet and put caps on them, and to install a ventilator on the first floor; that he was taken off the job by the landlord after the lease was signed but before the building was completed; that these things were *185 never done; that had they been done the interior of the building would have been dry in wet weather; that the failure to do them resulted in rain water .penetrating the walls and moisture condensing on the walls, rendering the premises uncomfortable and dangerous to health and useless for a tearoom, or any ordinary use; and by reason thereof the defendants and their subtenants vacated and surrendered the premises.”

The alleged misrepresentation of plaintiff’s agent as to the general character of the completed building is charged in the answer- to have been such a fraudulent misrepresentation as entitled the defendants to a rescission of the contract for fraud. That the foregoing evidential showing by defendants was not of itself sufficient to support an inference of fraud would seem too clear to warrant discussion; nor does the record disclose other evidence which, considered in connection with the testimony of defendants above referred to, would warrant a finding of fraud. The alleged representation was at most a mere promise as to a future event or condition, the alleged non-fulfillment of which involved details of architectural construction and supposed consequences which it does not appear that either the plaintiff or her agent had in mind, or could reasonably have foreseen, at the time the representation was made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young Ex Rel. Estate of Young v. Morrisey
329 S.E.2d 426 (Supreme Court of South Carolina, 1985)
Charles v. B & B Theatres
106 S.E.2d 455 (Supreme Court of South Carolina, 1959)
Rowland & Sons, Inc. v. Bock
148 S.E. 549 (Supreme Court of South Carolina, 1929)
Acme Manufacturing Co. v. Massey
146 S.E. 605 (Supreme Court of South Carolina, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
126 S.E. 525, 131 S.C. 175, 1925 S.C. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mallard-v-duke-sc-1925.