Malcolm Bradsher Co., Inc. v. Deheulle
This text of Malcolm Bradsher Co., Inc. v. Deheulle (Malcolm Bradsher Co., Inc. v. Deheulle) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
SUPERlOR COURT CIVIL ACTION STATE OF MAINE DOCKET NO.RE-04-011
#&"m MALCOLM DSHER CO., INC., Plaintiff A . - .g.d .. .a ,' ORDER AND DECISION
MICHAEL DEHEULLE and IDRRAINE DEHEULLE, Defendants
In November of 2002 the parties entered into a contract where the plaintiff provide a variety of excavation and construction services for the defendants regarding
their property in York. The written agreement had a price of $40,000 but failed to
include many of the mandatory contracbal provisions required by Maine's home
construction contracts statute found at 10 M.R.S.A. §§1486-et seq. It did list the price
and contained a "general description of the work and the to be used", 10 M.R.S.A. §1487(6). Problems developed reasonably quickly once work started. There were disputes
regarding the extent of the work to be done, the qualib of the work, the timeliness of
the work, and the attentiveness of Malcolm Bradsher, who is the president of the
plaintiff excavation and site work company. Disputes existed regarding change orders,
when payments should be made and whether the plaintiff was doing a poor job or whether the defendants were unduly demanding. In time the plaintiff was fired, some
of the remaining work was done by another contractor, and this litigation began.
The plaintiff has filed a four-count complaint and the defendants have brought a
five-count counterclaim. A non-jury hearing has been held. I have now reviewed the
evidence twice on separate days.
The evidence in this case makes it very difficult to determine wl-uch side is
correct and what the damages, if any, should be.
It is difficult to determine exactly what was agreed to initially. The site work
proposal listed types of work and an estimated price but provided few details. The
contract called for "Backfill, including underdrain." There was no indication of how
much fill and of what type of material. There was to be "foundation excavation" but it
became uncertain how much work was included. Likewise there was to be a gravel
driveway but there were no details regarding its construction.
Mr. Deheulle sent a letter of May 8, 2003 to Malcolm Bradsher's foreman, which
stated, "At the time I met with Malcolm, we agreed on a cubic yard amount of fill,
which I believe was an allowance of 600 yards." This letter helped to clarify what the
agreement was but did little to clarify the whole contract.
I cannot with sufficient certainty determine what the scope of the initial contract
was. The evidentiary difficulties increase because there are claimed extras that the
plaintiff alleges were agreed to and done but not paid for. No change order exists to
substantiate this.
The proposal drafted by the plaintiff, which formed their contract, might be
adequate in those cases where everyone gets along. It was completely inadequate in
this case where disputes arose. The problems on this job demonstrate the wisdom of the Maine legislature in requiring, for now nearly 20 years, that contracts be in writing
with mandatory provisions. I am left with substantial uncertainty regarding what was
agreed to and what work was done.
The plaintiff kept poor records. Additionally Mr. Bradsher's changes in his
testimony between his deposition and his trial testimony cast additional doubt on the
reliability of h s recollection. One area that is particularly troubling involves the extent
of clay that was improperly placed over the septic system. The testimony of Mr.
Bradsher on this point was not credible.
Since the plaintiff has not adequately established what was agreed to, what was
done or what is owed it has not met its burden of proving any of its claims by a
preponderance of the evidence. None of its legal theories provide it with a viable claim.
In examining the defendants' counterclaim I find many of the same problems. While
the defendants did not draft the contract I am still unable to adequately determine what
was required. There were changes made to the contract without proper documentation
though the extent of the changes is unclear. Some work was done well, some work was
done adequately, some work was done poorly and some work was left undone. It is not
possible to determine, however, what was contractually required and match it against
work done or not done. No damages can be awarded to the defendants.
It is correct that the home construction law's contractual requirements were not
met, 10 M.R.S.A. 51487, and that such a violation constitutes "...prima facie evidence of
a violation of the Unfair Trade Practices Act ...". 10 M.R.S.A. §1490(1). Whle
attorney's fees are available, 5 M.R.S.A. §213(2), it would not be proper to award them
here when no damages are otherwise awarded. See Dudley v. Wyler, 647 A.2d 90, 92
(Me. 1994). YORK COUNTY SUPERIOR COURT RE-04-0 1 1 The entries are:
Judgment for the defendants on the complaint. Judgment for the plaintiff on the counterclaim. No costs to any party.
Dated: August 9,2005
~&L.J? Paul A. Fritzsche " Justice, Superior Court
PLAINTIFF: P a t r i c k Bedard, Esq. PO Box 366 E l i o t Me 03903
DEFENDANTS : Gregory Orso, Esq. PO Box 545 York Me 03909
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Malcolm Bradsher Co., Inc. v. Deheulle, Counsel Stack Legal Research, https://law.counselstack.com/opinion/malcolm-bradsher-co-inc-v-deheulle-mesuperct-2005.