Majestic Plumbing & Consulting Corp. v. Half Hollow Hills Central School District

282 A.D.2d 749, 724 N.Y.S.2d 619, 2001 N.Y. App. Div. LEXIS 4207
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 30, 2001
StatusPublished
Cited by1 cases

This text of 282 A.D.2d 749 (Majestic Plumbing & Consulting Corp. v. Half Hollow Hills Central School District) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Majestic Plumbing & Consulting Corp. v. Half Hollow Hills Central School District, 282 A.D.2d 749, 724 N.Y.S.2d 619, 2001 N.Y. App. Div. LEXIS 4207 (N.Y. Ct. App. 2001).

Opinion

—In a proceeding pursuant to CPLR article 78 to review a determination by Half Hollow Hills Central School District rejecting the petitioner’s bid, Half Hollow Hills Central School District and Jack C. Hirsh, Inc., appeal from a judgment of the Supreme Court, Suffolk County (Costello, J.), dated December 20, 1999, which annulled the determination and directed that the subject contract be awarded to the petitioner.

Ordered that the appeal by Jack C. Hirsch, Inc., is dismissed as abandoned (see, 22 NYCRR 670.8 [c], [e]); and it is further,

Ordered that the judgment is reversed, on the law, the determination is confirmed, and the proceeding is dismissed on the merits; and it is further,

Ordered that the appellant Half Hollow Hills Central School District is awarded one bill of costs payable by the respondent.

The rejection by the appellant Half Hollow Hills Central School District (hereinafter the School District) of the petitioner’s bid was not arbitrary or capricious. It is well settled that a municipality may properly set the requirements for bidding in its bid documents and may disqualify a bidder for failure to comply with the bidding requirements (see, Edenwald Contr. Co. v City of New York, 86 Misc 2d 711, affd 47 AD2d 610). The petitioner’s qualifications were not included in the bid package as required by the bidding process and, therefore, the School District’s rejection of the bid had a rational basis (see, Matter of City of Long Beach v Smith of Long Is., 158 AD2d 454). Accordingly, the Supreme Court erred in directing that the contract be awarded to the petitioner (see, Matter of DeBonis v Hudson Val. Community Coll., 55 AD 2d 778). Altman, J. P., Krausman, Luciano and Cozier, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E.W. Tompkins Co. v. State University of New York
61 A.D.3d 1248 (Appellate Division of the Supreme Court of New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
282 A.D.2d 749, 724 N.Y.S.2d 619, 2001 N.Y. App. Div. LEXIS 4207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/majestic-plumbing-consulting-corp-v-half-hollow-hills-central-school-nyappdiv-2001.