Maine Public Utilities Commission v. Federal Energy Regulatory Commission

625 F.3d 754, 393 U.S. App. D.C. 182, 2010 U.S. App. LEXIS 23113
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 5, 2010
Docket06-1403, 06-1427, 07-1193
StatusPublished
Cited by1 cases

This text of 625 F.3d 754 (Maine Public Utilities Commission v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maine Public Utilities Commission v. Federal Energy Regulatory Commission, 625 F.3d 754, 393 U.S. App. D.C. 182, 2010 U.S. App. LEXIS 23113 (D.C. Cir. 2010).

Opinion

Opinion for the court filed by SILBERMAN, Senior Circuit Judge.

SILBERMAN, Senior Circuit Judge:

These consolidated petitions for review are before us once again. The Maine Public Utilities Commission and the Attorneys General of Connecticut and Massachusetts, representing energy customers, challenged FERC’s approval of a settlement agreement that redesigned New England’s electricity capacity market. Although we rejected most of petitioners’ challenges, we granted their petition regarding the argument that the settlement agreement’s Mobile-Sierra provision — which requires FERC to adjudicate challenges to rates resulting from an auction procedure arising out of the settlement agreement under the Mobile-Sierra public interest standard — deprived non-settling parties of their rights under the Federal Power Act to challenge rates under the statute’s presumably more searching “just and reasonable” standard. See Me. Pub. Utils. Comm’n v. FERC, 520 F.3d 464, 477 (D.C.Cir.2008) (per curiam). We held that the Mobile-Sierra doctrine could not apply to rate challenges brought by non-parties to the settlement agreement. See id. The Supreme Court granted certiorari on this general issue and reversed. See NRG Power Mktg., LLC v. Me. Pub. Utils. Comm’n, — U.S. -, 130 S.Ct. 693, 696-97, — L.Ed.2d -(2010). It identified, however, two questions concerning the Mobile-Sierra provision that had been raised before, but not ruled on by, us, and remanded those issues for our consideration. See id. at 701. Because the Commission failed to address those issues in the challenged orders, we now remand the orders to FERC.

I

This case has characteristics of a chameleon; it has changed its colors — and its shape — at each stage of the proceedings. As we have previously explained, the basic dispute relates to New England’s electrical capacity market, in which an electricity provider purchases an option to buy electricity from a generator rather than purchasing the electricity directly. That market had been beset by problems, including a supply of capacity that was barely sufficient to meet the region’s demand, and FERC, electricity generators, electricity purchasers, and power customers engaged in several attempts to resolve those issues. See Devon Power LLC, 115 FERC ¶ 61,-340, at 62,315 (2006). In response to their attempts, FERC required the New England Independent System Operator, the entity operating the electricity transmission system in New England, to develop a new market mechanism that set prices separately by geographic sub-region. Un *756 der this new mechanism, prices would be highest in the regions with the most severe capacity shortages, encouraging new entries to the max*ket. See Devon Power LLC, 107 FERC ¶ 61,240, at 62,022 (2004). This mechanism proved extremely controversial, and FERC apparently established settlement procedures to allow all affected parties to develop a different market mechanism. After four months of negotiations, a settlement was reached, which FERC approved. See Devon Power LLC, 115 FERC at 62,306.

The key feature of the settlement agreement is the Forward Capacity Market, which entails annual auctions that set the rates for electricity “capacity” (the option of buying a quantum of power). In these auctions, which are held three years in advance of when capacity is needed, electricity providers buy capacity at a standard rate, and must purchase enough capacity to maintain the reliability of the electricity grid. See id. As noted, the settlement agreement provided that challenges to the resulting auction rates— whether brought by a settling party, a non-settling party, or the Commission— would be “adjudicated under the highly-deferential Mobile-Sierra ‘public interest’ standard rather than the usual ‘just and reasonable’ standard” of the Federal Power Act. Me. Pub. Utils. Comm’n, 520 F.3d at 469.

It should be noted that, at the outset of this litigation, it was common ground among all pax-ties that the normal statutory “just and reasonable” standard was a different standard than the “public interest” standard. This belief no doubt was shaped by the eponymous cases of the Mobile-Sierra doctrine, in which the Supreme Court addi’essed the Commission’s authority to modify rates set by contract. In United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956), the Court held that under the Natural Gas Act, a utility could not abrogate a lawful contract with a purchaser merely by filing a new rate. 350 U.S. at 336-37, 76 S.Ct. 373. And in Federal Power Commission v. Sierra Pacific Power Co., 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956), it applied Mobile to the Federal Power Act, and confronted the question of how the Commission evaluates when a contract rate is just and reasonable. 350 U.S. at 352-53, 76 S.Ct. 368. The Court held that a utility that had entered into a contract setting rates could not subsequently seek a greater return by asserting the contract rate was inadequate to meet the just and reasonable standard. See id. at 354-55, 76 S.Ct. 368. It could only escape that rate if the utility could show the “public interest” was jeopardized — which apparently meant the utility faced something close to insolvency, the rate created an excessive burden for consumex's, or the rate was unduly discriminatory. See id. We subsequently extended that hurdle symmetrically to challenges brought by purchasers, in addition to challenges brought by sellers. See Potomac Elec. Power Co. v. FERC, 210 F.3d 403, 404-05 (D.C.Cir.2000).

It appeared to us that application of the Mobile-Sierra doctrine was a form of estoppel, i.e., a contracting party was not at liberty — short of extraordinary circumstances — to avoid its negotiated contract rate. And therefore we framed the Mobile-Sie'iTa issue in our px-evious opinion as whether “the Commission [may] approve a settlement agreement that applies the highly-deferential ‘public interest’ standard to rate challenges brought by non-contracting third parties.” Me. Pub. Utils. Comm’n, 520 F.3d at 477. FERC’s orders had been somewhat ambiguous as to why the Commission decided it could impose the Mobile-Sierra standard on non-settling parties. But we found no need to *757 parse FERC’s various explanations, because we concluded that the Commission could not approve the settlement agreement’s Mobile-Sierra clause that bound non-settling parties.

Then, before the Supreme Court, the ground shifted. Three months after we issued our original opinion in this case, the Supreme Court decided Morgan Stanley Capital Group Inc. v. Public Utility District No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
625 F.3d 754, 393 U.S. App. D.C. 182, 2010 U.S. App. LEXIS 23113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maine-public-utilities-commission-v-federal-energy-regulatory-commission-cadc-2010.