Main Line Expo Inc. v. Telugu Association of North America

District Court, E.D. Pennsylvania·Decided July 17, 2026·No. 2:24-cv-01030·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

MAIN LINE EXPO INC., Plaintiff, Civil No. 24-1030

v.

TELUGU ASSOCIATION OF NORTH

AMERICA, Defendant.

MEMORANDUM Costello, J. July 17, 2026 Plaintiff Main Line Expo Inc. is an events contractor. ECF No. 30-1 ¶ 6. Defendant Telugu Association of North America is a not-for-profit organization that aims to identify and address the social, cultural, and educational needs of the North American Telugu community. Id. ¶¶ 1-2. Plaintiff contracted with Defendant to provide event services for Defendant’s biannual convention at the Philadelphia Convention Center. ECF No. 13 ¶ 6. Plaintiff alleges that Defendant knowingly misrepresented the amount of work required for the convention during the planning phase and significantly expanded the scope of work during the convention. Id. ¶ 8. As a result, Plaintiff provided significant additional labor and materials to produce the event. Id. ¶¶ 15, 43. In its Second Amended Complaint, Plaintiff alleged claims for: (1) breach of contract; (2) fraud in the inducement; (3) violation of the Contractor and Subcontractor Payment Act; (4) tortious interference with contractual relations; and (5) in the alternative, equitable relief under quantum meruit and unjust enrichment. Id. ¶¶ 67, 75, 103-108, 112-114, 119-120, 124-128, 132- 134. Defendant moved for summary judgment arguing that Plaintiff failed to produce evidence to support its claims. See generally ECF No. 30. For the reasons that follow, the Court will grant Defendant’s motion. I. FACTUAL & PROCEDURAL BACKGROUND

Under the contract between the parties, Plaintiff agreed to provide event services for Defendant’s biannual convention at the Pennsylvania Convention Center. ECF No. 30-1 ¶¶ 3-4, 13. The convention was held from July 5 to July 10, 2023. Id. ¶ 10. The contract called for Plaintiff to provide materials and labor totaling $129,014.18. Id. ¶ 13; ECF No. 30-4 at 5. However, the contract did not state the total cost of performance. See id. All contractors are required to use the union labor services of Elliot-Lewis Convention Services, LLC (“Elliot- Lewis”), for events at the convention center. ECF No. 32-4 ¶ 32. Accordingly, the contract stated that “[a]ll labor costs are estimated based on current TANA project scope” and “[a]ll labor, scheduled through Elliot Lewis, is billed on a pass-through basis.” ECF No. 30-4 at 4. Defendant paid Plaintiff $159,740.44 for its services. ECF No. 30-1 ¶ 18. Plaintiff

claims that Defendant owes it an additional $315,000 for the labor and materials. ECF No. 32-4 ¶ 55. Plaintiff asserts that Defendant knowingly misrepresented the scope of work required for the convention. Id. ¶ 31. For example, on the first day of the convention, Plaintiff learned for the first time that it would have to provide labor and materials to support the event across an area almost six-fold larger than initially agreed upon. Id. ¶ 37. Defendant allegedly made many other misrepresentations to Plaintiff, including: (1) stating that the work required in one of the areas would be two man-hours when it ended up requiring four hundred plus man-hours; (2) not disclosing the existence of a decorator subcontractor until two days before the event; (3) stating that the decorator’s items could be unloaded by one worker in four hours when the decorator’s items actually contained two tractor trailers and multiple box trucks and required the labor of eight to sixteen men over multiple days; (4) representing that two trailers worth of water would need to be unloaded and distributed on the first day of the convention while in reality, eight tractor trailers worth of water arrived over multiple days; (5) performing outside work that

violated the building code, thus requiring a large crane, three additional carts and two additional forklifts to fix the violations; (6) representing that no electricians would be required to conduct the event then insisting that lighting was necessary such that the electricians’ union was required to provide labor; (7) stating that the convention would end by 11:59 p.m. each night when it did not end until 2:00 a.m. each day; (8) representing that the exhibitors would need two hours to set up when it actually took twelve hours. Id. ¶¶ 38-46. Additionally, Plaintiff claims that Defendant attempted to circumvent the requirement to use Elliot-Lewis union labor by doing work themselves late at night when they thought nobody was watching. Id. ¶ 47. At the end of the convention, Plaintiff alleges that Defendant failed to remove all their items from the Convention Center loading area, and as a result, Plaintiff stored

Defendant’s items in its warehouse. Id. ¶ 53. Ultimately, Plaintiff claims it is owed a greater balance than the amount specified in the contract because of the significant additional labor needed to produce Defendant’s event. See id. ¶ 49. Plaintiff asserts that Defendant approved each of the additional charges for labor from Elliot-Lewis in writing as they were incurred during the convention, including overtime charges. Id. Moving for summary judgment, Defendant contends that it paid what it owed for the convention and that it did not authorize any additional expenses. ECF No. 30-1 ¶ 29. Defendant further argues that Plaintiff has failed to produce any evidence supporting its claims. ECF No. 30-1 at 5. Plaintiff did not conduct any discovery in this case. Id. It has not issued any written discovery requests, produced a single document, or taken a deposition. Id. The record consists of only four documents: an affidavit by Plaintiff’s President; the contract at issue; an invoice to Defendant issued five months after the convention took place; and a planning document that

Defendant used to specify the scope of work to Plaintiff prior to the event. ECF Nos. 32-3, 13-2, 13-3, and 13-4. Plaintiff opposed the motion, arguing that although it has not conducted any discovery, the four documents it has provided are sufficient to establish that genuine issues of material fact exist on each of its claims. ECF No. 32-4 at 5. II. LEGAL STANDARD Summary judgment is appropriate if the movant shows “that there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). “To defeat a motion for summary judgment, there must be a factual dispute that is both material and genuine.” Bennett v. SEPTA, 23cv1271, 2024 WL 404959, at *6 (E.D. Pa. Feb.

2, 2024), aff’d sub nom., Bennett v. Se. Pa. Transp. Auth., 24cv1376, 2025 WL 1248815 (3d Cir. Apr. 30, 2025) (citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986)). “When the movant is the defendant, they have the burden of demonstrating that the plaintiff ‘has failed to establish one or more essential elements of her case.’” Id. (quoting Burton v. Teleflex Inc., 707 F.3d 417, 425 (3d Cir. 2013)). The Court does not weigh evidence or make credibility determinations at the summary judgment stage. Rather, it simply determines “whether there is a genuine issue for trial.” Id. (citing Anderson, 477 U.S. at 249). III. ANALYSIS Plaintiff’s failure to conduct discovery is fatal to its case. At summary judgment, allegations lacking in evidentiary support are insufficient to sustain a claim. See Anderson, 477 U.S. at 248 (“[A] party opposing a properly supported motion for summary judgment may not

Free access — add to your briefcase to read the full text and ask questions with AI

Main Line Expo Inc. v. Telugu Association of North America, (E.D. Pa. 2026).

Main Line Expo Inc. v. Telugu Association of North America (Main Line Expo Inc. v. Telugu Association of North America) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Hershey Foods Corporation v. Ralph Chapek, Inc.
828 F.2d 989 (Third Circuit, 1987)
Mary Burton v. Teleflex Inc
707 F.3d 417 (Third Circuit, 2013)
Eigen v. Textron Lycoming Reciprocating Engine Division
874 A.2d 1179 (Superior Court of Pennsylvania, 2005)
Pennsy Supply, Inc. v. American Ash Recycling Corp.
895 A.2d 595 (Superior Court of Pennsylvania, 2006)
Cosby v. American Media, Inc.
197 F. Supp. 3d 735 (E.D. Pennsylvania, 2016)