Maida v. Kroger Co.

230 F. Supp. 668, 1964 U.S. Dist. LEXIS 9136
CourtDistrict Court, E.D. Texas
DecidedJune 19, 1964
DocketCiv. A. No. 4430
StatusPublished
Cited by1 cases

This text of 230 F. Supp. 668 (Maida v. Kroger Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maida v. Kroger Co., 230 F. Supp. 668, 1964 U.S. Dist. LEXIS 9136 (E.D. Tex. 1964).

Opinion

FISHER, District Judge.

This is a suit by Peter W. Maida, Trustee, against The Kroger Company, doing business under the tradename of Henke & Pillot, a Division of The Kroger Company, for breach of a long term lease of a store building to be constructed by lessor according to certain plans and specifications to be approved by The Kroger Company. The Kroger Company agreed to pay a minimum rental of $343,200.00, payable in installments as provided in the lease contract.

[670]*670The lease contract provided that lessee would furnish lessor certain drawings specifying the tenant’s requirements with reference to heating, air conditioning, duct work, electrical and plumbing requirements, light fixtures, etc. The landlord was to construct the building according to plans and specifications prepared by lessor’s architect which incorporated the lessee’s requirements, but the lessee had the right to approve the plans and specifications.

The plaintiff contended that the defendant deliberately delayed the approval of the plans and specifications and the furnishing of details in order that the building could not be completed by October 1, 1960, as provided in the contract. Plaintiff further contended that defendant repudiated the contract by its action and conduct which had created a delay which made it impossible for the plaintiff to complete the construction within the time required by the contract.

The defendant denied it had refused to approve complete plans and specifications, and denied any deliberate or planned delay to prevent construction within the time prescribed in the lease contract. Defendant • admitted that plaintiff had sought an extension of time, and denied that its agent, Deitz, had agreed to recommend that an extension of time would be granted, and likewise denied that its agent, Deitz, nor the president of Henke & Pillot Division were authorized to grant the extension of time requested. It subsequently developed that the president of the Henke & Pillot Division did have the authority to grant the extension of time, but a decision had been made prior to the date of the conference to cancel the lease contract.

Defendant further contended that on or about June 14, 1962, it had decided to accept a proposal of plaintiff to cancel the lease contract (which offer the court finds did not exist), and this was evidenced by defendant’s letter to plaintiff dated June 22, 1960. Defendant likewise denied any deliberate delays of plaintiff’s construction or that it formed any intention at any time not to accept the leased premises if they were constructed and tendered within the time provided in the lease contract. From time to time, after the lease was signed by The Kroger Company on or about March 3, 1960, the architect for Henke & Pillot Division would furnish to lessor’s architect certain additional requirements and changes in the proposed plans and specifications. Although defendant’s agent admitted the plans were substantially complete except for a few minor details on or about June 24, 1960, the defendant refused to approve the plans and specifications and would not give a partial approval with exceptions. The defendant had made a decision on or prior to June 10 and on June 14, 1960, that the lease would be canceled, and that in any event it would not agree to any extension of time for the construction of the building beyond October 1, 1960, because of its desire to cancel.

Thereafter, on or about June 24, 1960, the plaintiff conferred with the real estate manager and architect for the Henke & Pillot Division, and although the agent of defendant stated that the plans were substantially complete except for a few minor details, he failed and refused to approve the plans and failed to specify the detail on the remaining exceptions and additions which he required. On this occasion, plaintiff requested an extension of time in order that he might complete the construction in accordance with the defendant’s requirements, and the defendant’s agent agreed to submit and recommend the request to its Cincinnati office, representing that the President of the Henke & Pillot Division and the real estate manager did not have authority to grant such extension. Subsequently, The Kroger Company sought to induce plaintiff to accept a cancellation of the lease contract, but plaintiff refused and in good faith requested an extension of time, stating that he wanted to complete the construction within the terms of the lease and within the period as extended.

On July 8, 1960, plaintiff made a second effort to get the defendant to agree [671]*671to extend the time for completion of the construction as there was not sufficient time due to delay in approving the plans and specifications, and due to the misrepresentation that an extension would probably be granted, when, in fact, the defendant’s agent knew that it would not. Thereafter, under date of July 21, 1960, the defendant advised the plaintiff that since it was obvious that he could not complete the building within the time limit set forth in the lease, he was being requested to execute a cancellation agreement. The plaintiff then elected to file suit against the defendant for damages resulting from the anticipatory breach of the contract by the defendant.

Trial of the case was before the Court without a jury, and the Court found that the evidence established a breach of contract for which the plaintiff was entitled to recover damages, which was found by the Court in the amount of $102,572.00. The judgment of the Court is based upon the findings of fact and conclusions of law which are a part of this memorandum opinion.

FINDINGS OF FACT

1.

The plaintiff, Peter W. Maida, Trustee, entered into a written lease contract with The Kroger Company, effective as to landlord December 10, 1959, and as to tenant March 3, 1960, which required the construction of a building and shopping center according to plans and specifications.

2.

I find as a fact that the defendant did not want the contract to come into existence or to be effective, and it employed a “cat and mouse” technique over a period of time from May 11, 1960, until July 6, 1960, in an effort to delay performance by plaintiff.

3.

I find there was no offer open by plaintiff to defendant after May .11, 1960, to rescind or cancel the lease contract. The plaintiff wanted to carry out the contract.

4.

I find there was no acceptance by defendant of a prior offer of plaintiff, if any, to cancel the lease, and the plaintiff was at all times ready, able and willing to proceed with the performance of the contract after May 11, 1960.

5.

I find as a fact that the defendant wanted to be released from the lease contract on or about June 10, 1960.

6.

I find as a fact that plaintiff did nothing to delay final approval of the plans and specifications which were required to be approved by defendant before construction could be begun and completed.

7.

The defendant made an effort to and did delay the final approval of the plans and specifications for the purpose of delaying and finally preventing construction by plaintiff.

8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Target Stores, Inc. v. Twin Plaza Co.
153 N.W.2d 832 (Supreme Court of Minnesota, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
230 F. Supp. 668, 1964 U.S. Dist. LEXIS 9136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maida-v-kroger-co-txed-1964.