mahoney v. beacon hill builders

CourtVermont Superior Court
DecidedFebruary 29, 2024
StatusPublished

This text of mahoney v. beacon hill builders (mahoney v. beacon hill builders) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
mahoney v. beacon hill builders, (Vt. Ct. App. 2024).

Opinion

Vermont Superior Court Filed 11/16/21 Lamoille Unit

VERMONT SUPERIOR COURT CIVIL DIVISION Lamoille Unit Case No. 196-11-17 Lecv 154 Main Street

Hyde Park VT 05655 802-888-3887 www.vermontjudiciary.org

Mahoney vs. Beacon Hill Builders &

ENTRY REGARDING MOTION

Title: Motion for Summary Judgment (Motion: 25) Filer: Jennifer Lajoie Filed Date: May 21, 2021

The motion is GRANTED IN PART and DENIED IN PART.

Leslie Mahoney (“Plaintiff”) filed a second amended complaint on June 1, 2018, against Beacon Hill Builders & Associates, Inc., (““BHB”), Tucker Fossiano (“Tucker”), and David Fossiano (“David”) (together, “Defendants”). She alleges that in March 2016, she purchased a lot in the Rich- Reed Subdivision located in Wolcott, Vermont and that she retained Defendants to build her a house on that lot. According to the second amended complaint, Plaintiff met with Tucker at the job site in August 2016 to discuss the details of the project, including her available budget. Plaintiff told Tucker she had $250,000 to spend on the project and, according to Plaintiff, Tucker agreed that BHB “could do the project for $250,000.” Plaintiff contends that the parties” agreement is memorialized in the zoning application that Tucker prepared and filed on August 30, 2016,

Construction began in mid-September 2016, and Plaintiff believed BHB would be able to complete “the entire upstairs of the house, the downstairs bathroom, and the downstairs frame and site work for $250,000 which would leave a portion of the basement unfinished, but otherwise, the house would be complete and move-in ready.” Plaintiff asserts that she visited the job site in October 2016 and “discovered for the first time that Defendants had constructed the house in the wrong location by almost 150 feet.” Plaintiff did not ask Defendants to move the house because she “wanted to get the project done.”

Plaintiff alleges she spoke with David in Januaty 2017 about the progress of the project and realized that “Defendants were approaching $250,000 in costs and had not even come close to completing the agreed upon parts of the home.” David told Plaintiff “it would be, at a minimum, over $100,000 more to complete the home.” Plaintiff told Defendants to stop working on the house because she “could not spend more than $250,000.”

Plaintiff asserts that she hired other contractors in March 2017 to continue working on her house. She claims these other contractors discovered “numerous structural defects and deficiencies resulting from Defendants’ poor workmanship.” In addition, Plaintiff alleges that Defendants’ work does not comply with Vermont’s Residential Building Energy Standards (“RBES”), which compliance is required by statute.

Entry Regarding Motion Page 1 of 12 196-11-17 Lecv Mahoney vs. Beacon Hill Builders & Plaintiff asserts ten causes of action against Defendants:

Breach of contract (Count I);

Breach of implied warranty against structural defects (Count II); Breach of implied warranty of good workmanship (Count II); Negligence in construction (Count IV);

Consumer fraud (Count V);

Fraudulent misrepresentation (Count VJ);

Negligent misrepresentation (Count VID);

Fraud-in-inducement (Count VIID;

Unjust entichment (Count IX); and

Noncompliance with Vermont’s RBES (Count X).

Defendants have denied any wrongdoing and filed a motion for partial summary judgment in which they ask the court to dismiss Counts IV-VIII against BHB and to dismiss all ten Counts asserted against the individual defendants, Tucker Fossiano and David Fossiano.

Summary Judgment Standards

A patty is entitled to summary judgment if “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” V.R.C.P. 56(a). A fact is material “4f it might affect the outcome.” In re Estate of Fitzsimmons, 2013 VT 95, 7 13, 195 Vt. 94 (quoting N. Sec. Ins. Co. v. Rossitto, 171 Vt. 580, 581, 762 A.2d 861, 863 (2000) (mem.)). “Where the moving party does not bear the burden of persuasion at trial, it may satisfy its burden of production by showing the coutt that there is an absence of evidence in the record to support the nonmoving party’s case.... The burden then shifts to the nonmoving party to persuade the court that there is a ttiable issue of fact.” Boulton v. CLD Consulting Eng’rs, 175 Vt. 413, 417 (2003) (quoting Ross v. Times Mirror, Inc. 164 Vt. 13, 18 (1995)). ““The nonmoving party may survive the motion if it responds with specific facts raising a triable issue, and it is able to demonstrate sufficient evidence to support a ptima facie case.”” State v. G.S. Blodgett Co., 163 Vt. 175, 180 (1995) (quoting Celotex Corp. v.

Catrett, ATT U.S. 317, 323, 324 (1986)). “If the nonmoving patty fails to establish an essential element of its case on which it has the burden of proof at trial, the moving party is entitled

to summary judgment as a matter of law.” Washington v. Pierce, 2005 VT 125, 917, 179 Vt. 318 (quoting G.S. Blodgett, 163 Vt. at 180). When considering motions for summary judgment, the nonmoving patty is entitled to “all reasonable doubts and inferences.” West v. N. Branch Fire District #7, 2021 VT 44, § 13 (citing In re Miller Subdivision Final Plan. 2008 VT 74, 4 8, 184 Vt. 188):

G.S. Blodgett, 163 Vt. at 180.

Legal Analysis

A. Negligence in Construction (Count IV)

Defendants contend that the economic loss rule precludes Plaintiff from pursuing an action in negligence for the recovety of money damages. “The economic-loss rule ‘maintain[s] a distinction between contract and tort law’ by prohibit[ing] recovery in tort for purely economic losses.”” Walsh », Cluba, 2015 VT 2, J 27, 198 Vt. 453 (quoting Long Trail House Condo. Ass'n v. Eingelberth Constr., Inc., 2012 VT 80, J 10, 192 Vt. 322); see also Wentworth v. Crawford & Co., 174 Vt. 118, 127 (2002) (“{O]ur caselaw prohibits a claimant from seeking damages for contractual losses through tort law.”). As the Walsh Court wrote, “Tort law imposes duties to protect the public from harm, and thus negligence

Entry Regarding Motion Page 2 of 12 196-11-17 Lecv Mahoney vs. Beacon Hill Builders & actions ate generally limited to unanticipated physical injury, while contract law allows patties to protect themselves through bargaining.” Walsh, 2018 VT at J 27 (citing Long Traif, 2012 VT at { 10).

For purposes of the economic loss doctrine, “economic loss” has been described to include:

damages for inadequate value, costs of repait and replacement of the defective product, or consequent loss of profits, as well as the diminution in the value of the product because it is inferior in quality and does not work for the general purposes for which it was sold or manufactured. Redarowicz v. Oblendorf, 441 N.E..2d 324, 327 ill. 1982); Heath v. Palmer, 2006 VT 125, 9 15[, 181 Vt. 545}.

Treetop at Stratton Condo. Ass'n, Inc. v. Treetop Dev. Co., 2011 WL 8472969 (Vt. Super. Feb. 4, 2011). The Treetop at Stratton Condominium court explained that, “to recover in negligence, there must be a showing of harm above and beyond disappointed expectations, since a buyer’s desire to enjoy the benefit of his bargain is not an interest that tort law traditionally protects.” Id. (citing Redarowiex, 441 N.E.2d at 327).

Plaintiff contends that she suffered physical harm to her property as a result of Defendants’ conduct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles E. Wolfe v. United States
798 F.2d 1241 (Ninth Circuit, 1986)
In re Estate of Alden v. Alden v. Alden
2011 VT 64 (Supreme Court of Vermont, 2011)
Follo v. Florindo
2009 VT 11 (Supreme Court of Vermont, 2009)
In Re Miller Subdivision Final Plan
2008 VT 74 (Supreme Court of Vermont, 2008)
Inkel v. Pride Chevrolet-Pontiac, Inc.
2008 VT 6 (Supreme Court of Vermont, 2008)
EBWS, LLC v. Britly Corp.
2007 VT 37 (Supreme Court of Vermont, 2007)
In re Estate of Fitzsimmons
195 Vt. 94 (Supreme Court of Vermont, 2013)
Zeeman v. Black
273 S.E.2d 910 (Court of Appeals of Georgia, 1980)
State v. G.S. Blodgett Co.
656 A.2d 984 (Supreme Court of Vermont, 1995)
Limoge v. People's Trust Co.
719 A.2d 888 (Supreme Court of Vermont, 1998)
Hamill v. Pawtucket Mutual Insurance
2005 VT 133 (Supreme Court of Vermont, 2005)
Winey v. Cutler
678 A.2d 1261 (Supreme Court of Vermont, 1996)
Springfield Hydroelectric Co. v. Copp
779 A.2d 67 (Supreme Court of Vermont, 2001)
Powell v. District of Columbia Housing Authority
818 A.2d 188 (District of Columbia Court of Appeals, 2003)
Jordan v. Nissan North America, Inc.
2004 VT 27 (Supreme Court of Vermont, 2004)
Howard v. Usiak
775 A.2d 909 (Supreme Court of Vermont, 2001)
Washington v. Pierce
2005 VT 125 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
mahoney v. beacon hill builders, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mahoney-v-beacon-hill-builders-vtsuperct-2024.