Mahler v. Bellis

435 N.W.2d 661, 231 Neb. 161, 1989 Neb. LEXIS 58
CourtNebraska Supreme Court
DecidedFebruary 17, 1989
Docket86-950
StatusPublished
Cited by7 cases

This text of 435 N.W.2d 661 (Mahler v. Bellis) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mahler v. Bellis, 435 N.W.2d 661, 231 Neb. 161, 1989 Neb. LEXIS 58 (Neb. 1989).

Opinion

Buckley, D.J.

Plaintiff-appellant, John Mahler, hired defendant-appellee, Lyle Beilis, a construction contractor, to do some remodeling to plaintiff’s house. The written contract involved the conversion of an existing garage into a room enlarged by a 12- by 20-foot addition.

During the construction, numerous problems arose, and this suit followed. Plaintiff alleged that the defendant did not perform in a workmanlike manner and did not follow the terms of the written contract, causing plaintiff to sustain damages to repair and replace defendant’s faulty work.

Defendant denied plaintiff’s allegations and by way of affirmative defense alleged that an accord and satisfaction was reached as to all of the disputes between the parties.

The case was tried to the court without a jury, resulting in a judgment for the defendant and a dismissal of plaintiff’s petition. The trial court specifically found that “there was an accord and satisfaction as to all items of damage claimed by plaintiff other that [sic] the footings, the cracks in the drywall and the shingles.” The court further found that as to those items, the plaintiff failed to establish either that the work was done improperly or in breach of the contract or that any damages resulted therefrom.

In a law action tried to the court, the findings of the trial court have the effect of a jury verdict and will not be disturbed on appeal unless clearly wrong. In a nonjury law action, the evidence must be considered in the light most favorable to the successful party, with conflicts resolved in favor of the *163 successful party, who is entitled to the benefit of every inference which can be reasonably deduced from the evidence. Nebraska State Bank v. Rasmussen, 225 Neb. 81, 402 N.W.2d 688 (1987).

The contract was executed in July 1984, requiring payment totaling $15,036. Plaintiff paid $7,500 when the contract was executed; the balance was to be paid upon completion.

Plaintiff testified that after construction began, the first problem that arose concerned the footings for the addition. Defendant told him that as they were digging the footings they struck something in the ground, which concerned the plaintiff because it was in the area where he knew there was some type of sewage disposal system. Plaintiff said defendant told him there was no problem because what they encountered was solid and had not moved. Defendant then proceeded to pour the footings before they were inspected by the building inspectors. The room included a loft, and while it was being constructed, plaintiff noticed the roof sagging, whereupon construction was halted and plaintiff retained a structural engineer, who redesigned the loft support system. Construction then continued, and the balcony and supports were built according to the engineer’s design.

About mid-August 1984, defendant said the project was finished and requested payment of the balance due under the contract. Plaintiff told him that several things had not been done at all or were not done properly. These included failure to form up some concrete put in next to the patio area, installation of a screen with holes, installation of a fireplace pipe with a color that did not match the color of existing pipe sections, failure to pay the costs for retaining the engineer to redesign the loft support system, failure to clean up tar and glue from the concrete floor, and failure to clean up the windows and woodwork. Plaintiff had also discussed with defendant his concern over the way that the new roof was tied into the existing structure; that it was just a piece of tin pounded down over the top of the shingles, which appeared very rough and unsightly. Defendant told him that it was the normal way to do that type of a tie-in and that he would not change it without waiving his guarantees.

Plaintiff testified that on August 31,1984, the parties met to *164 discuss plaintiff’s concerns just described, which plaintiff says were the only problems he was aware of at that time. They went over each item and the monetary impact on the contract. Some of the items plaintiff did not push further. The parties agreed that the contract price would be adjusted for the chimney pipe that plaintiff obtained and installed himself, for engineering costs, and for cleaning the concrete floor. The total adjustment was $600. Plaintiff paid defendant $1,500 at that meeting and paid the balance of the contract 2 to 3 weeks later.

Plaintiff contends that after the negotiated settlement, he encountered further problems not known to him or discussed on August 31, 1984, resulting from defendant’s failure to complete work required by the contract or to complete it properly. The defendant’s position is that all disputes were settled at the August 31 meeting, constituting a complete accord and satisfaction, but that if any items were not settled then, defendant’s evidence more than supports the trial court’s findings that no damages were sustained through any fault of defendant.

To constitute an accord and satisfaction there must be (1) a bona fide dispute between parties, (2) substitute performance tendered in full satisfaction of the claim, and (3) acceptance of the tendered performance. Meyers v. Frohm Holdings, Inc., 211 Neb. 329, 318 N.W.2d 716 (1982).

The key element of accord and satisfaction is the intent of the parties, which, although as a general rule presents a question of fact, becomes a question of law when the evidence creates no conflict as to intent. Rosenberg v. Lincoln Fed. Sav. & Loan Assn., 219 Neb. 689, 365 N.W.2d 809 (1985).

Defendant testified that the August 31 meeting resulted in a settlement of all of the plaintiff’s complaints and that final payment by the plaintiff finalized the settlement and the matter was over. Plaintiff does not seek damages for any item he was aware of at the settlement meeting, but only those items he discovered afterward. Defendant admitted on cross-examination that none of these items were discussed. The evidence will not permit a finding that the parties intended that the August 31 meeting settled any items of damage other than those known by the plaintiff and considered by the parties at *165 that meeting. Therefore, there was no accord and satisfaction as to any of the items of damage claimed by the plaintiff in this suit. However, there is evidence that supports a finding for the defendant as to each element of damage. We take them up separately.

UNEVENNESS OF THE FLOOR

The contract called for a water drain in the floor of the old garage to be closed and the floor area leveled. After the “settlement” meeting and while plaintiff was painting the room, he spilled some water which collected at the drain area. He offered no other evidence that the area had not been leveled as required by the contract and no evidence of the cost to do the work that defendant presumably failed to do. This item fails for lack of any evidence of damages.

INSTALLATION OF DRYWALL

Plaintiff testified that the drywall was uneven.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

English Estates v. Champion Kearney
Nebraska Court of Appeals, 2022
Zornes v. Zornes
292 Neb. 271 (Nebraska Supreme Court, 2015)
Lone Cedar Ranches, Inc. v. Jandebeur
523 N.W.2d 364 (Nebraska Supreme Court, 1994)
MacKiewicz v. JJ & ASSOCIATES
514 N.W.2d 613 (Nebraska Supreme Court, 1994)
Peterson v. Kellner
513 N.W.2d 517 (Nebraska Supreme Court, 1994)
Stiles v. Skylark Meats, Inc.
438 N.W.2d 494 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
435 N.W.2d 661, 231 Neb. 161, 1989 Neb. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mahler-v-bellis-neb-1989.