Maher Terminals, LLC v. Federal Maritime Commission

816 F.3d 888, 421 U.S. App. D.C. 491, 2016 WL 1104774, 2016 U.S. App. LEXIS 5190
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 22, 2016
Docket15-1035
StatusPublished
Cited by3 cases

This text of 816 F.3d 888 (Maher Terminals, LLC v. Federal Maritime Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maher Terminals, LLC v. Federal Maritime Commission, 816 F.3d 888, 421 U.S. App. D.C. 491, 2016 WL 1104774, 2016 U.S. App. LEXIS 5190 (D.C. Cir. 2016).

Opinion

Opinion for the Court filed by Senior Circuit Judge SILBERMAN.

SILBERMAN, Senior Circuit Judge:

Petitioner Maher, a marine terminal operator, challenges a decision of the Federal Maritime Commission authorizing preferential lease terms to a competitor, APM-Maersk. We grant the petition and remand because we think the Commission provided an inadequate explanation.

I.

In the late 1990s, the Port Authority bégan negotiating new leasing terms for maritime terminal operators servicing the Port of New York and New Jersey. This was a part of an overall effort to modern *889 ize the port’s facilities and make it an attractive location for shipping into the future. Among the companies the Port Authority negotiated with were Maher and APM-Maersk. Maher is an independent marine terminal operator, which means that it has no affiliated carrier fleet, and services only third party carriers and shippers through its rented terminal. APM-Maersk, on the other hand, is affiliated with the largest ocean carrier-fleet in the United States, Sea-Land, though it also services third party cargo through its terminals. 1

Lease negotiations between Maher and the Port Authority began in 1995. Maher sought an agreement that would make it competitive with other terminal operators, and tentative terms, including an effective annual rate of $68,750 per acre, were reached in late 1997. Negotiations with Maher were suspended in 1998, however, when the Port Authority began negotiating with APM-Maersk. That larger terminal operator had found the initial terms offered by the Port Authority too expensive, and threatened to go to Baltimore. APM-Maersk’s business was critical to the Port of New York and New Jersey because of the high volume of container business it could bring through its affiliated carriers. Indeed,- Maher’s CEO expressed great concern over the potential departure, writing a letter to the Governor of New Jersey warning of the “grave” risk to the port.

The Port Authority opened negotiations with APM-Maersk in July by offering a 350-acre terminal at a rate of $63,000 per acre,, per year. That was rejected. Later, in September, the offer was reduced to $36,000 per acre, but again rebuffed. APM-Maersk made clear that it would require as much as $120 million in cost reduction in order to make the port as attractive as other options. The Port Authority finally agreed, and submitted terms that included $30 million in capital and structural improvements paid for by the Port-Authority at the terminal, as well as $90 million in basic rent reduction. Those concessions, of $120 million total, reduced APM-Maersk’s effective base rent to $19,000 per acre, per year.

Since the purpose of the concessions was to keep APM-Maersk, because of its affiliated carrier fleet and the promise of additional tonnage of cargo, the Port Authority got a “port guarantee,” requiring APM-Maersk to actually bring cargo from its affiliated carriers through the port. The Port Authority hoped that meant APM-Maersk would not entice third party carriers away from other terminal operators, like Maher. A deal was reached at an effective annual base rent of $19j000 per acre, with certain penalties designed to increase the rent where the port guarantee was not met.

With APM-Maersk secured as a tenant, the Port Authority-turned back to. negotiations with Maher. Maher sought parity with APM-Maersk, but the Port Authority was unwilling to offer the same terms. Lacking the bargaining power- enjoyed by APM-Maersk, Maher ultimately agreed to an initial base rent of $39,750 per acre, with an escalator, such that the average base rent over’the life of the lease would amount to $53,753 per acre. While the exact annual base rent charged to APM-Maersk may be somewhat variable over the period of the 30-year lease (due to the possibility of penalties for failure to meet cargo guarantees), it is undeniable that Maher was forced to pay substantially more than APM-Maersk.

*890 Maher was purchased by Deutsche Bank in 2007. As the global recession hit in 2008, the port's .total container traffic fell for the first time in almost 15 years. Maher lost nearly 15% of its business, while APM-Maersk failed to meet its port guarantees in 2008, 2009, and 2010.

On June 3, 2008, nearly 8 year's after executing its lease, Maher' filed' a complaint against the Port Authority, alleging that the differential terms between its and APM-Maersk’s leases violated the Shipping Act. It alleged that the Port Authority had violated 46 U.S.C. § 41106(2) in offering an “unreasonable preference” to APM-Maersk.

After some dispute regarding the applicable statute of limitations for the claims, 2 the merits came before an ALJ, who issued a decision on April 25, 2014, denying the claims. Maher appealed, and the.Federal Maritime Commission affirmed on December 17, 2014.

The Commission did not deny that the Port Authority had treated Maher and APM-Maersk differently, but the Commission explained the difference was justified, on three counts. First, APM-Maersk had threatened credibly to abandon the port. Maher could make no such threat. Second, APM-Maersk was able to make a port guarantee, relying on its affiliated carrier fleet, that Maher was hot. Finally, Maher’s terminal was of a higher quality than was APM-Maersk’s, thus justifying a higher rent. The Commission similarly dismissed a separate', unreasonable practices claim, explaining that Maher had not met its assigned burden under the applicable regulations.

II.

It is common ground in this case that differences between similar entities contracting with Port Authorities must be based on “transportation factors.” That term goes back to the Interstate Commerce Act and was extended into the earliest Shipping Act. 3 It is not clear whether it was originally articulated as an interpretation of the statutory term “undue or unreasonable preference” 4 or whether it was a policy choice. Perhaps that is why petitioner conflates its challenge as both a-statutory claim and an arbitrary/capricious one. And the dispute is further limited by the Commission’s concession that neither the port guarantee nor. Maersk’s supposed superior terminal quality would justify the lower rent.' The Commission’s decision thus rises or falls on APM-Maersk’s credible threat to leave the Port of New York and New Jersey—which the Commission claims is a “transportation factor,” justifying the distinction in the treatment of APM-Maersk and Maher.

Before considering the issue on which the dueling briefs concentrate—whether a large terminal operator’s-threat to leave can be legitimately regarded as a “transportation factor”—the.more obvious question raised by petitioner is why the same *891 rates were not offered to it, which would avoid the issue of discrimination altogether. In that regard, the Commission’s explanation in its Order is circular. It said, “The Port’s decision not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sun City v. Acc
Court of Appeals of Arizona, 2020
City of Oberlin, Ohio v. FERC
937 F.3d 599 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
816 F.3d 888, 421 U.S. App. D.C. 491, 2016 WL 1104774, 2016 U.S. App. LEXIS 5190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maher-terminals-llc-v-federal-maritime-commission-cadc-2016.