Magnum Air, Inc., Gamma Construction Co., Colonial American Casualty and Surety Company, and Fidelity and Deposit Company of Maryland v. Maven Mechanical, LLC, Ralph Wheeler, and Matthew Janecek

Court of Appeals of Texas·Decided March 17, 2022·No. 09-20-00093-CV·Published

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

NO. 09-20-00093-CV

MAGNUM AIR, INC., GAMMA CONSTRUCTION CO., COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, AND FIDELITY AND DEPOSIT COMPANY OF MARYLAND, Appellants

V.

MAVEN MECHANICAL, LLC, RALPH WHEELER, AND MATTHEW JANECEK, Appellees

On Appeal from the 284th District Court Montgomery County, Texas

Trial Cause No. 16-05-06217-CV

MEMORANDUM OPINION

Following a jury verdict in favor of Maven Mechanical, LLC (“Maven”) and against Magnum Air, Inc. (“Magnum”), the trial court signed its final judgment, titled Final Judgment Nunc Pro Tunc, on the jury’s verdict against Magnum, Gamma Construction Co. (“Gamma”), Colonial American Casualty and Surety Company

(“Colonial”), and Fidelity and Deposit Company of Maryland (“Fidelity”).1 Magnum filed a motion for new trial, which was denied. In four issues, Magnum challenges the trial court’s denial of its Motion for New Trial and contends: (1) the evidence was legally and factually insufficient to support the jury’s findings that Magnum breached the contracts first; and (2) the evidence was legally and factually insufficient to support the jury’s findings that it suffered no damages resulting from Maven’s breach. In its second issue, Magnum argues the trial court abused its discretion by denying its Motion for New Trial based on conflicting and contradictory answers to issues by the jury in the jury charge. In its third and fourth issues, Magnum conditionally contends that if we sustain its first and second issues, then the derivative bond claims and attorney’s fee claims are without legal support. We overrule the first two issues and affirm the judgment of the trial court.

I. Background

A. Parties’ Relationship Pipefitters by trade, Ralph Wheeler and Matthew Janecek decided to start their own company, Maven. They began bidding jobs for Magnum, a commercial HVAC contractor, as Janecek had worked with William Fincher, Magnum’s Vice President, on other projects when they were employed for different contractors. Magnum

1 Defendants/Counter-Plaintiffs nonsuited their counterclaims against Wheeler and Janecek individually along with their conversion claim against Maven.

primarily did school construction jobs, because the “money is pretty much guaranteed.”2 In 2014 and 2015, Maven and Magnum executed contracts on four individual projects at issue in this litigation. These projects included three schools: Creekside Park Junior High in Tomball, Katy Elementary 38, and Katy Elementary 39. The fourth project was St. Luke’s United Methodist Church. A Master Subcontract Agreement (“MSA”) executed in 2014 governed the parties’ work.3 Additionally, separate “[W]ork [A]uthorizations” containing identical terms, except for the scope of work and contractual amount to be paid, covered each individual project. Each work authorization included a provision requiring Magnum to provide Maven with a job schedule. A “pay when paid” provision requiring Magnum to pay Maven once it received payment from the general contractor also applied to all the projects.

As the projects progressed, Maven fell further behind on its scheduled completion date, with each party attributing the delays to different reasons. In January, Magnum began requiring Maven to add significant manpower to the jobs to overcome the delays. Magnum paid Maven at the end of each week for these additional labor charges but deducted those amounts from the overall payment

2 See generally Tex. Gov’t Code Ann. § 2253.001 (defining various terms pertaining to public work performance and payment bonds).

3 During trial, the parties also referred to this as the “Master Services Agreement.”

installments owed to Maven under their contract. Maven began experiencing difficulty paying its vendors, and Magnum began withholding Maven’s payments under the auspices of auditing their accounts, as was contractually permitted.

Because of increased tensions on the jobs, Maven requested a meeting with Magnum, which took place on April 20, 2016. At the time of the meeting, Maven had not received payments from Magnum for work performed in February and March, although Magnum had been paid by the general contractor for each of these months. Additionally, Magnum put Maven’s January payment for Creekside on hold to audit the account. At the meeting, Magnum had several checks ready for Maven; however, Maven advised Magnum they would be unable to continue the jobs given the payment situation. The parties disagreed on whether Maven refused to accept the checks or whether Magnum refused to hand over the checks. After the April 20 meeting, Magnum took over each of the jobs for Maven and hired Maven’s workers as their own to complete the projects. Magnum also agreed to hire Janecek and Wheeler to help finish the jobs.

Following the conclusion of these projects, both parties filed multiple lawsuits in various jurisdictions against each other. The lawsuits were ultimately consolidated into one suit in Montgomery County, Texas, with Maven designated as the Plaintiff and Counter-Defendant and Magnum designated as the Defendant and Counter-

Plaintiff. Although the parties pleaded multiple causes of action, the primary dispute dealt with competing breach of contract claims. B. Evidence at Trial 1. Matthew Janecek’s Testimony Janecek, one of Maven’s owners, testified that Maven and Magnum executed an MSA dated April 15, 2014. Janecek testified the MSA covers any job Maven does for Magnum, which has terms that apply for every project. Work authorizations are executed for each individual project awarded Maven under the MSA.

Janecek testified adverse weather caused significant delays on the two Katy projects and the Tomball Creekside project. Janecek said with the school projects, there is a firm start date and finish date, so even if the project starts late or experiences delays, the finish date does not change. If a delay occurs, contractors must then hire additional people to complete the job timely, which increases the contractor’s costs and reduces any profit. Janecek testified that happened in this case, and Maven had to man the jobs with more people than they originally calculated when they made their bid for the project.

a. Katy 38 and 39

Janecek discussed the Katy 38 Elementary Work Authorization. Janecek testified that Maven’s total contract price for Katy 38 was $540,000. Janecek testified that Item 13 on “Exhibit A” of the Katy 38 Work Authorization stated,

“Magnum Air shall provide you with a construction schedule. We expect you to ship and receive the equipment as to not delay the progress of the job.” Janecek testified that Magnum Air never provided them with a construction schedule for the Katy 38 job. Janecek testified Gamma, the general contractor, held weekly meetings with foremen from the different trades, and “generally [had] a weekly schedule change as the job flows along. It’s pretty much a living document. It changes from week to week.”

Janecek said between the start of the Katy 38 project in June 2015 to April 2016, Maven “[r]eceived equipment, installed piping, ran mains, piped equipment, . . . and then purchased material as well.” Janecek said Maven actually began their work in October 2015 and confirmed he submitted payment requests for October, November, and December, which Magnum paid. For Katy 38, Maven also received a January payment in the ordinary course of business. Janecek explained that it typically took forty-five to fifty days for Magnum to pay Maven’s payment application.

Free access — add to your briefcase to read the full text and ask questions with AI

Magnum Air, Inc., Gamma Construction Co., Colonial American Casualty and Surety Company, and Fidelity and Deposit Company of Maryland v. Maven Mechanical, LLC, Ralph Wheeler, and Matthew Janecek, (Tex. Ct. App. 2022).

Magnum Air, Inc., Gamma Construction Co., Colonial American Casualty and Surety Company, and Fidelity and Deposit Company of Maryland v. Maven Mechanical, LLC, Ralph Wheeler, and Matthew Janecek (Magnum Air, Inc., Gamma Construction Co., Colonial American Casualty and Surety Company, and Fidelity and Deposit Company of Maryland v. Maven Mechanical, LLC, Ralph Wheeler, and Matthew Janecek) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Del Lago Partners, Inc. v. Smith
307 S.W.3d 762 (Texas Supreme Court, 2010)
Exxon Corp. v. Emerald Oil & Gas Co., LC
348 S.W.3d 194 (Texas Supreme Court, 2011)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Bradford v. Vento
48 S.W.3d 749 (Texas Supreme Court, 2001)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Jawed Manjlai v. Nabila Hamid Manjlai
447 S.W.3d 376 (Court of Appeals of Texas, 2014)
STR Constructors Ltd. and Arch Insurance Company v. Newman Tile, Inc.
395 S.W.3d 383 (Court of Appeals of Texas, 2013)
Usaa Texas Lloyds Company v. Gail Menchaca
545 S.W.3d 479 (Texas Supreme Court, 2018)