Magliaro v. Modern Homes, Inc.

178 A. 733, 115 N.J.L. 151, 1935 N.J. LEXIS 276
CourtSupreme Court of New Jersey
DecidedMay 17, 1935
StatusPublished
Cited by17 cases

This text of 178 A. 733 (Magliaro v. Modern Homes, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Magliaro v. Modern Homes, Inc., 178 A. 733, 115 N.J.L. 151, 1935 N.J. LEXIS 276 (N.J. 1935).

Opinion

The opinion of the court was delivered by

Campbell, Chancellor.

The plaintiff-respondent entered into a parol contract with the defendant-appellant to exea *152 yate, lay sewers and construct an extension of Caldwell road, Lincoln Park, in Maplewood, according to plans and specifications of E. R. Halsey, engineer. The consideration was based upon unit prices for which plaintiff then was performing or had executed a like work on adjoining property of one Sirlyn. Payments were to be made monthly upon the certificate of Halsey, the engineer, to eighty per cent, of the amount of such certificates.

The agreement was entered into April 1st, 1926. A monthly certificate of the engineer was issued May 26th, 1926; payment thereof was not made; plaintiff discontinued work and brought suit for the amount of the unpaid certificate on May 21st, 1929.

The complaint consists of three counts but we are only concerned with the first because at the trial the second and third were either abandoned or stricken out.

The first count averred:

"1. On or about April 1st, 1926, * * * plaintiff agreed to excavate, lay sewers, fill and construct Caldwell road * * * according to the plans and specifications of E. R. Halsey, engineer, upon defendant’s promise to pay to' plaintiff eighty per cent, of the work completed each month upon presentation to defendant of the engineer’s statement certifying the amount of work completed.
“2. Plaintiff had in all things performed said agreement during the first month of operation and did present the engineer’s certificate to1 defendant, &c., * * *.
“3. There is now due and owing plaintiff $2,059.92 which defendant has refused, neglected and failed to' pay in whole or in part, although requested to do so.
“4. Plaintiff demands as damages $2,059.92 with interest and costs.”

The defendant answered by admitting all the allegations contained in paragraph 1 of the first count denying all other allegations of the complaint and pleading four separate defenses and a counter-claim.

The separate defenses are:

1. That plaintiff failed to perform and carry out the terms *153 of his contract resulting in defendant being obliged to complete the work at a cost exceeding the contract price.

2. That the work performed was not done and completed to defendant’s satisfaction nor according to the specifications and drawings.

3. That, under the contract, time was of the essence and the work was not performed within the time provided by the contract by reason of which defendant was put to a loss of $25,000.

4. That the work was performed in an improper and unworkmanlike manner so that the defendant was required to do over a part thereof as well as complete the work at the sum of $3,000.

The counter-claim is:

As a result of plaintiff’s failure to perform his contract and his abandonment thereof defendant was obliged to complete the work at a cost of $3,000. Defendant “demands an affirmative judgment against the plaintiff in the sum of $28,000 on counter-claim.”

The plaintiff replied denying every allegation of the answer and counter-claim.

It appears from the proofs that the defendant refused payment to the plaintiff because it disputed the rock removal and the quantity of the earth excavation certified by the engineer. This dispute seems to have continued from May, 1926, until some time about April, 1928, when defendant proceeded to complete the work which was accomplished in May of that year.

At the trial the proofs on the part of the plaintiff were not only that his contract was as alleged in paragraph one of the first count of his complaint, admitted by the first paragraph of the defendant’s answer, but further that if any monthly estimate was not paid plaintiff’s obligation to continue with the work would cease. This seems not to have been seriously objected to; at least, no exception was taken to any ruling thereon.

The ground of appeal now before us was not raised until the close of the entire case when a motion for direction of *154 verdict, in favor of the defendant, was made and urged upon two grounds:

1. “That there is a substantial and fatal variance between the complaint and the proof.
2. “That the only contract is the so-called Sirlyn contract which is repudiated.”

The latter, whatever it may have been intended to urge, do'es not seem to have been pressed below and is not urged here.

The motion was denied and the plaintiff was permitted to amend paragraph 1 of the first count of his complaint (the second and third counts being stricken) by restating it as theretofore and adding that the payment of the monthly estimates was a condition precedent to his proceeding with the work.

This was objected to upon the ground of surprise and that it presented a new cause of action after the running of the statute of limitations against the original cause.

The question of surprise does not appear to have been pressed below or pursued here. Below it was stated but not shown to exist in fact.

The only grounds of appeal are:

1. The trial court was in error in granting leave to plaintiff to amend his complaint, to avoid variances, the effect of which was to state a new, and substantially different, cause of action after the statute of limitations had run.

2. That the trial court was in error in refusing to direct a verdict in favor of the defendant on the pleadings and proofs as the same stood prior to granting leave to plaintiff to amend his complaint.

The court and counsel for both parties appear to have acted upon the theory that if plaintiff refused to proceed with the work under his contract simply and solely because the defendant failed or refused to make payment of the installment in question he could not have a recovery. So, in fact, the trial court charged and such instruction appears to have been accepted because neither party lodged any exception to it.

*155 The point is not before us and a conclusion as to its soundness is of value only in determining whether or not the plaintiff, to the extent that he had pleaded, had a maintainable cause of action.

We find he did. His contract, as the court below held, was entire, in that it called for labor and materials for a single complete piece of work. The consideration was payable in monthly installments of eighty per cent, of the work certified based upon unit prices for the several classes of work. Having a certificate of the engineer, as required by his contract, he was entitled to’ the payment and upon nonpayment could sue and recover. Potts v. Point Pleasant Land Co., 49 N. J. L. 411; Vine v. Kennedy, 2 N. J. Mis. R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County of Morris v. Fauver
707 A.2d 958 (Supreme Court of New Jersey, 1998)
Zulla Steel, Inc. v. a & M GREGOS, INC.
415 A.2d 1183 (New Jersey Superior Court App Division, 1980)
A & B AUTO STORES v. City of Newark
248 A.2d 258 (New Jersey Superior Court App Division, 1968)
Scott v. Garber
198 A.2d 103 (New Jersey Superior Court App Division, 1964)
City of Trenton v. Fowler-Thorne Co.
154 A.2d 369 (New Jersey Superior Court App Division, 1959)
Ross v. Realty Abstract Co.
141 A.2d 319 (New Jersey Superior Court App Division, 1958)
McGraw v. Johnson
126 A.2d 203 (New Jersey Superior Court App Division, 1956)
Cafone v. Nesto Const. Co.
115 A.2d 148 (New Jersey Superior Court App Division, 1955)
MIDDLESEX CONCRETE, ETC. v. Borough of Carteret
113 A.2d 821 (New Jersey Superior Court App Division, 1955)
Kennedy v. Westinghouse Elec. Corp.
101 A.2d 592 (New Jersey Superior Court App Division, 1953)
United States v. Schefrin
14 F.R.D. 462 (D. New Jersey, 1953)
Rothman Realty Corp. v. MacLain
91 A.2d 101 (New Jersey Superior Court App Division, 1952)
Granahan v. Celanese Corp. of America, Plastics Div.
69 A.2d 572 (Supreme Court of New Jersey, 1949)
Integrity Flooring, Inc. v. Zandon Corp., Inc.
32 A.2d 507 (Supreme Court of New Jersey, 1943)
Maty v. Grasselli Chemical Co.
303 U.S. 197 (Supreme Court, 1938)
Campbell v. City of Hackensack
179 A. 687 (Bergen County Circuit Court, N.J., 1935)

Cite This Page — Counsel Stack

Bluebook (online)
178 A. 733, 115 N.J.L. 151, 1935 N.J. LEXIS 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/magliaro-v-modern-homes-inc-nj-1935.