Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede

CourtCourt of Appeals of Mississippi
DecidedApril 7, 2026
Docket2024-CA-01310-COA
StatusPublished

This text of Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede (Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede, (Mich. Ct. App. 2026).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI

NO. 2024-CA-01310-COA

MAGDI CORPORATION AND MOHAMED APPELLANTS RAWAID

v.

BERUK CONSTRUCTION, INC. AND FASIL APPELLEES KEBEDE

DATE OF JUDGMENT: 08/06/2024 TRIAL JUDGE: HON. MITCHELL M. LUNDY JR. COURT FROM WHICH APPEALED: DESOTO COUNTY CHANCERY COURT ATTORNEY FOR APPELLANTS: JOHN S. GRANT IV ATTORNEY FOR APPELLEES: MARVIN REID STANFORD NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: REVERSED AND REMANDED - 04/07/2026 MOTION FOR REHEARING FILED:

BEFORE BARNES, C.J., LAWRENCE AND EMFINGER, JJ.

LAWRENCE, J., FOR THE COURT:

¶1. In 2019, Mohamed Rawaid, owner of Magdi Corporation, hired his friend Fasil

Kebede with Beruk Construction Inc. to build an approximately 6,500 square-foot gas station

and shopping center.1 Their friendship and working relationship turned sour, and Magdi sued

Beruk for breach of contract. A bench trial on June 12, 2024, resulted in a dismissal of the

case in favor of Beruk. Rawaid appealed, arguing that the evidence presented at trial proved

that Beruk breached the contract. After review, this Court finds that the chancellor

manifestly erred by granting the dismissal, and we reverse and remand the case for further

1 The record contains an alternative spelling of “Kebede” as “Kabede.” proceedings.

FACTS AND PROCEDURAL HISTORY

¶2. In 2018, Rawaid and Beruk entered into a contract for the construction of a gas station

and shopping center in the City of Olive Branch.2 On July 2, 2018, the parties entered into

an addendum to the contract. There is no dispute between the parties that the addendum and

the contract operated together to dictate the expectations of the project. The addendum

provides that in the event of a conflict between the two documents, the contract controls.

According to the contract, Beruk agreed to complete the construction for a price of $898,000.

Further, Beruk would “achieve Substantial Completion of the entire Work not later than 180

calendar days from the Date of Commencement[.]” The contract further provided that

Rawaid would pay Beruk progress payments based on payment applications that Beruk

would submit to Rawaid.

¶3. Beruk began work on March 28, 2019. Rawaid and Beruk’s working relationship

became increasingly adverse, with multiple alleged instances of Rawaid losing his temper

with Beruk. In December 2019, Beruk asked Rawaid, via email, to not return to Beruk’s

office and to only meet with him on the job site.

¶4. Rawaid made eight progress payments to Beruk from March 2019 to September 2019.

The last application for payment Rawaid paid or partially paid was Beruk’s eighth

2 The contract was not signed and is dated April 3, 2018. There is an attached exhibit to the contract that is signed by Fasil and dated May 14, 2018. Regardless, the parties do not dispute the creation of the contract.

2 application for payment, dated September 10, 2019, which requested payment of $75,988.3

In December 2019, Beruk sent Rawaid a change-order invoice for $5,482.72 and a ninth

application for payment for $29,000. On February 5, 2020, Beruk sent Rawaid a final notice

requesting payment in the amount of $34,482.74 and ceased working on the project. The

February 2020 invoice was not paid, and Rawaid subsequently hired Murphy and Sons Inc.

to finish the work.

¶5. On May 18, 2020, Magdi Corporation and Rawaid filed this suit against Beruk

Construction for breach of contract and damages.4 A bench trial was held on June 12, 2024.

Rawaid and Matthew Murphy, of Murphy and Sons Inc., provided testimony at the hearing.

¶6. Rawaid testified that in May 2018, he hired his friend Fasil Kebede with Beruk

Construction to build a gas station and shopping center with three strip mall bays for

$898,000. Rawaid stated that after the building was framed, he became disappointed in

Fasil’s work. Eventually, Rawaid and Fasil began to argue over Fasil’s work. Rawaid

testified to specific actions that Fasil failed to install or installed improperly—gas lines from

the street into the kitchen, stainless steel vent hood, flooring throughout the store, hand dryers

in the men’s bathroom, and “hot water for each bay.”

¶7. Rawaid testified that Fasil installed a 3-ton air-conditioning unit instead of a 5-ton unit

that was agreed to in the contract. According to Rawaid, Fasil made no attempt to correct

3 Beruk testified at trial that Rawaid only paid $50,000. 4 Included in the complaint was a request to vacate or expunge Beruk’s lien against the property. This issue is not raised on appeal. Additionally, Beruk filed a cross-claim for breach of contract that is not raised on appeal.

3 the issue when Rawaid brought it to his attention. Further, Fasil did not test the unit when

it was installed, and it was later discovered that it was incorrectly wired.

¶8. Rawaid testified to other issues with Fasil’s workmanship. The glass front doors were

incorrectly installed with a gap between the doors. When the HVAC was corrected and

turned on, condensation appeared on the glass windows and doors. Fasil did not install

emergency exits, certain lights did not work, and at least one of the back doors would not

open.

¶9. Rawaid stated that he continued to pay Fasil, despite his concerns, but felt that Fasil

was not truthfully reporting his completion of the projects on his payment applications. For

example, Rawaid testified that in June 2019, he paid $49,600 for a walk-in cooler. Fasil’s

payment applications in September 2019 reported that the walk-in cooler was 100%

completed; however, photographic evidence from September 2019 revealed that the cooler

had not been installed. Rawaid also stated that he paid for part of the HVAC system in June,

but it was not completed when Fasil left the job in September.

¶10. Rawaid testified that he hired Murphy and Sons in April 2020 to finish the project.

Rawaid also hired subcontractors, independent of Murphy and Sons. Hendricks Sheet Metal

had agreed with Fasil to install the vent hood in the kitchen. When Rawaid contacted them

about completing the job, they informed Rawaid that they had never been paid. Rawaid then

directly paid Hendricks to complete the kitchen vent hood. Rawaid paid Airman Air

Conditioning to complete the work on the HVAC system and replace the 3-ton unit. Rawaid

also hired Dees Oil Company Inc. and Baine Brothers to complete the parking lot. Invoices

4 from Dees Oil and Airman were submitted into evidence along with a copy of a check from

Rawaid to Hendricks Sheet Metal. The work was finally completed in July 2020, and the

store opened in August 2020.

¶11. Deposition testimony from Matthew Murphy was introduced at trial.5 Murphy

testified that when Rawaid contacted Murphy and Sons, Murphy went to the project site in

February or March of 2020 to evaluate its status. Murphy stated that the project was

“obviously incomplete” and that his main goal was to “get a substantial completion and have

the City let [Rawaid] sell gas and cigarettes and beer.” Murphy explained many of the issues

he observed with Fasil’s workmanship—incorrect electrical receptacles were installed, power

to the fuel panels was not connected, there was no parking lot, dirt work was incomplete,

there was no erosion control, sinks were not “hooked up[,]” drink fountains were leaking, gas

lines were not connected from the street, the kitchen vent hood was not connected, the walk-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magee v. Magee
661 So. 2d 1117 (Mississippi Supreme Court, 1995)
BEVIS CONSTR. CO., INC. v. Kittrell
139 So. 2d 375 (Mississippi Supreme Court, 1962)
Garner v. Hickman
733 So. 2d 191 (Mississippi Supreme Court, 1999)
Wheat v. Wheat
37 So. 3d 632 (Mississippi Supreme Court, 2010)
Forbes v. General Motors Corp.
935 So. 2d 869 (Mississippi Supreme Court, 2006)
Ladner v. Stone County
938 So. 2d 270 (Court of Appeals of Mississippi, 2006)
Century 21 Deep South Prop., Ltd. v. Corson
612 So. 2d 359 (Mississippi Supreme Court, 1992)
Stewart v. Merchants Nat. Bank
700 So. 2d 255 (Mississippi Supreme Court, 1997)
Gulfport-Biloxi Regional Airport Authority v. Montclair Travel Agency, Inc.
937 So. 2d 1000 (Court of Appeals of Mississippi, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede, Counsel Stack Legal Research, https://law.counselstack.com/opinion/magdi-corporation-and-mohamed-rawaid-v-beruk-construction-inc-and-fasil-missctapp-2026.