Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede

Court of Appeals of Mississippi·Decided April 7, 2026·No. 2024-CA-01310-COA·Published

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI NO. 2024-CA-01310-COA

MAGDI CORPORATION AND MOHAMED APPELLANTS RAWAID

v.

BERUK CONSTRUCTION, INC. AND FASIL APPELLEES KEBEDE

DATE OF JUDGMENT: 08/06/2024 TRIAL JUDGE: HON. MITCHELL M. LUNDY JR. COURT FROM WHICH APPEALED: DESOTO COUNTY CHANCERY COURT ATTORNEY FOR APPELLANTS: JOHN S. GRANT IV ATTORNEY FOR APPELLEES: MARVIN REID STANFORD NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: REVERSED AND REMANDED - 04/07/2026 MOTION FOR REHEARING FILED:

BEFORE BARNES, C.J., LAWRENCE AND EMFINGER, JJ.

LAWRENCE, J., FOR THE COURT:

¶1. In 2019, Mohamed Rawaid, owner of Magdi Corporation, hired his friend Fasil Kebede with Beruk Construction Inc. to build an approximately 6,500 square-foot gas station and shopping center.1 Their friendship and working relationship turned sour, and Magdi sued Beruk for breach of contract. A bench trial on June 12, 2024, resulted in a dismissal of the case in favor of Beruk. Rawaid appealed, arguing that the evidence presented at trial proved that Beruk breached the contract. After review, this Court finds that the chancellor manifestly erred by granting the dismissal, and we reverse and remand the case for further

1 The record contains an alternative spelling of “Kebede” as “Kabede.”

proceedings.

FACTS AND PROCEDURAL HISTORY

¶2. In 2018, Rawaid and Beruk entered into a contract for the construction of a gas station and shopping center in the City of Olive Branch.2 On July 2, 2018, the parties entered into an addendum to the contract. There is no dispute between the parties that the addendum and the contract operated together to dictate the expectations of the project. The addendum provides that in the event of a conflict between the two documents, the contract controls. According to the contract, Beruk agreed to complete the construction for a price of $898,000. Further, Beruk would “achieve Substantial Completion of the entire Work not later than 180 calendar days from the Date of Commencement[.]” The contract further provided that Rawaid would pay Beruk progress payments based on payment applications that Beruk would submit to Rawaid.

¶3. Beruk began work on March 28, 2019. Rawaid and Beruk’s working relationship became increasingly adverse, with multiple alleged instances of Rawaid losing his temper with Beruk. In December 2019, Beruk asked Rawaid, via email, to not return to Beruk’s office and to only meet with him on the job site.

¶4. Rawaid made eight progress payments to Beruk from March 2019 to September 2019. The last application for payment Rawaid paid or partially paid was Beruk’s eighth

2 The contract was not signed and is dated April 3, 2018. There is an attached exhibit to the contract that is signed by Fasil and dated May 14, 2018. Regardless, the parties do not dispute the creation of the contract.

application for payment, dated September 10, 2019, which requested payment of $75,988.3 In December 2019, Beruk sent Rawaid a change-order invoice for $5,482.72 and a ninth application for payment for $29,000. On February 5, 2020, Beruk sent Rawaid a final notice requesting payment in the amount of $34,482.74 and ceased working on the project. The February 2020 invoice was not paid, and Rawaid subsequently hired Murphy and Sons Inc. to finish the work.

¶5. On May 18, 2020, Magdi Corporation and Rawaid filed this suit against Beruk Construction for breach of contract and damages.4 A bench trial was held on June 12, 2024. Rawaid and Matthew Murphy, of Murphy and Sons Inc., provided testimony at the hearing.

¶6. Rawaid testified that in May 2018, he hired his friend Fasil Kebede with Beruk Construction to build a gas station and shopping center with three strip mall bays for $898,000. Rawaid stated that after the building was framed, he became disappointed in Fasil’s work. Eventually, Rawaid and Fasil began to argue over Fasil’s work. Rawaid testified to specific actions that Fasil failed to install or installed improperly—gas lines from the street into the kitchen, stainless steel vent hood, flooring throughout the store, hand dryers in the men’s bathroom, and “hot water for each bay.”

¶7. Rawaid testified that Fasil installed a 3-ton air-conditioning unit instead of a 5-ton unit that was agreed to in the contract. According to Rawaid, Fasil made no attempt to correct

3 Beruk testified at trial that Rawaid only paid $50,000.

4 Included in the complaint was a request to vacate or expunge Beruk’s lien against the property. This issue is not raised on appeal. Additionally, Beruk filed a cross-claim for breach of contract that is not raised on appeal.

the issue when Rawaid brought it to his attention. Further, Fasil did not test the unit when it was installed, and it was later discovered that it was incorrectly wired.

¶8. Rawaid testified to other issues with Fasil’s workmanship. The glass front doors were incorrectly installed with a gap between the doors. When the HVAC was corrected and turned on, condensation appeared on the glass windows and doors. Fasil did not install emergency exits, certain lights did not work, and at least one of the back doors would not open.

¶9. Rawaid stated that he continued to pay Fasil, despite his concerns, but felt that Fasil was not truthfully reporting his completion of the projects on his payment applications. For example, Rawaid testified that in June 2019, he paid $49,600 for a walk-in cooler. Fasil’s payment applications in September 2019 reported that the walk-in cooler was 100% completed; however, photographic evidence from September 2019 revealed that the cooler had not been installed. Rawaid also stated that he paid for part of the HVAC system in June, but it was not completed when Fasil left the job in September.

¶10. Rawaid testified that he hired Murphy and Sons in April 2020 to finish the project. Rawaid also hired subcontractors, independent of Murphy and Sons. Hendricks Sheet Metal had agreed with Fasil to install the vent hood in the kitchen. When Rawaid contacted them about completing the job, they informed Rawaid that they had never been paid. Rawaid then directly paid Hendricks to complete the kitchen vent hood. Rawaid paid Airman Air Conditioning to complete the work on the HVAC system and replace the 3-ton unit. Rawaid also hired Dees Oil Company Inc. and Baine Brothers to complete the parking lot. Invoices

from Dees Oil and Airman were submitted into evidence along with a copy of a check from Rawaid to Hendricks Sheet Metal. The work was finally completed in July 2020, and the store opened in August 2020.

¶11. Deposition testimony from Matthew Murphy was introduced at trial.5 Murphy testified that when Rawaid contacted Murphy and Sons, Murphy went to the project site in February or March of 2020 to evaluate its status. Murphy stated that the project was “obviously incomplete” and that his main goal was to “get a substantial completion and have the City let [Rawaid] sell gas and cigarettes and beer.” Murphy explained many of the issues he observed with Fasil’s workmanship—incorrect electrical receptacles were installed, power to the fuel panels was not connected, there was no parking lot, dirt work was incomplete, there was no erosion control, sinks were not “hooked up[,]” drink fountains were leaking, gas lines were not connected from the street, the kitchen vent hood was not connected, the walk- in cooler was not connected, wall panels were pealing, the glass doors were “letting air in[,]” glass in the store was “sweating,” emergency exit signs did not meet code requirements, the breaker panel was unlabeled, exhaust fans in the bathroom were not installed, waterlines were not insulated, and the air conditioning was not finished.

Free access — add to your briefcase to read the full text and ask questions with AI

Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede, (Mich. Ct. App. 2026).

Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede (Magdi Corporation and Mohamed Rawaid v. Beruk Construction, Inc. and Fasil Kebede) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Magee v. Magee
661 So. 2d 1117 (Mississippi Supreme Court, 1995)
BEVIS CONSTR. CO., INC. v. Kittrell
139 So. 2d 375 (Mississippi Supreme Court, 1962)
Garner v. Hickman
733 So. 2d 191 (Mississippi Supreme Court, 1999)
Wheat v. Wheat
37 So. 3d 632 (Mississippi Supreme Court, 2010)
Forbes v. General Motors Corp.
935 So. 2d 869 (Mississippi Supreme Court, 2006)
Ladner v. Stone County
938 So. 2d 270 (Court of Appeals of Mississippi, 2006)
Century 21 Deep South Prop., Ltd. v. Corson
612 So. 2d 359 (Mississippi Supreme Court, 1992)
Stewart v. Merchants Nat. Bank
700 So. 2d 255 (Mississippi Supreme Court, 1997)
Gulfport-Biloxi Regional Airport Authority v. Montclair Travel Agency, Inc.
937 So. 2d 1000 (Court of Appeals of Mississippi, 2006)