Madrigal v. City of Huntington Beach

55 Cal. Rptr. 3d 209, 147 Cal. App. 4th 1375, 7 Cal. Daily Op. Serv. 2104, 2007 Daily Journal DAR 2655, 2007 Cal. App. LEXIS 263
CourtCalifornia Court of Appeal
DecidedJanuary 31, 2007
DocketG036991
StatusPublished
Cited by5 cases

This text of 55 Cal. Rptr. 3d 209 (Madrigal v. City of Huntington Beach) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Madrigal v. City of Huntington Beach, 55 Cal. Rptr. 3d 209, 147 Cal. App. 4th 1375, 7 Cal. Daily Op. Serv. 2104, 2007 Daily Journal DAR 2655, 2007 Cal. App. LEXIS 263 (Cal. Ct. App. 2007).

Opinion

*1378 Opinion

FYBEL, J.

Introduction

We consider whether the trial court abused its discretion in determining the City of Huntington Beach (the City) properly issued a grading permit without conducting an environmental review of the permit’s impact, pursuant to the California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.). “The fundamental purpose of CEQA is to ensure ‘that environmental considerations play a significant role in governmental decision-making’ [citation].” (Fullerton Joint Union High School Dist. v. State Bd. of Education (1982) 32 Cal.3d 779, 797 [187 Cal.Rptr. 398, 654 P.2d 168].) “CEQA must be interpreted to afford the fullest possible protection to the environment within the reasonable scope of statutory language. [Citation.]” (Day v. City of Glendale (1975) 51 Cal.App.3d 817, 823 [124 Cal.Rptr. 569].)

The City found the entire project was exempt from compliance with CEQA because it involved a minor alteration to land, and issued a notice of exemption at the same time it issued a conditional use permit (CUP) for the project. (Cal. Code Regs., tit. 14, § 15304, subd. (a).) (All further references to title 14 are to title 14 of the California Code of Regulations.) The exemption finding was never challenged. Merrilee Madrigal, the Santa Ana River Watershed Coalition, and the HB River Park Foundation (collectively Madrigal) challenged the later issuance of a grading permit, on the grounds (1) the permit was inconsistent with the CUP and (2) the issuance of the permit was not exempt from CEQA compliance and required environmental review. Madrigal petitioned the trial court for a writ of mandate; the trial court entered judgment denying the petition, finding the City did not abuse its discretion in issuing the grading permit without conducting an environmental review.

We affirm. The grading permit was consistent with the CUP. The CUP contemplated the use of fill as part of the grading process, although no specific amount of fill was mentioned at that time. The fact two different grading plans, prepared six years apart, estimate two different amounts of fill does not mean either of the grading plans was inconsistent with the CUP. The grading permits issued in connection with those grading plans were also consistent with the CUP.

Additionally, Madrigal did not meet the burden on appeal of proving that the issuance of the grading permit was discretionary, rather than ministerial, or that it was not otherwise exempt from CEQA.

*1379 Statement of Facts

The property in question is located in Huntington Beach, north of Atlantic Avenue, between the Santa Ana River and a residential tract. Southern California Edison (SCE) owns the property and SCE’s power lines cross above it. In June 1996, the predecessor in interest of Landscape by Hiro, Inc., entered into a license agreement with SCE to use the property for horticultural and agricultural purposes.

On June 20, 1996, Hiro Kawachi applied to the City for a CUP to operate a wholesale nursery on the property. On June 24, Kawachi submitted a proposed land use plan for the nursery. In response to a request for more information, Kawachi advised the City he planned to “eliminate the areas of flooding [on the property] by adding or scraping away soil.” Kawachi also explained the area would be graded and a drainage system installed, over the course of several years, in stages of 500 feet per stage.

The City conducted public hearings on Kawachi’s CUP application. At a public hearing on September 4, 1996, Kawachi explained, “[t]he project will be implemented over the next five (5) years in 500 foot sections,” and he would “use a 10 wheel truck to bring in the dirt for grading.”

At a September 18, 1996 hearing, the City’s staff circulated a detailed written summary of the project, which contained the following relevant language: “Project Implementation: Applicant proposes to prepare the site incrementally, approximately 500 linear feet each year over a four to five year period. Initially, some other site preparation will be required . ... [ft] Step 1: Along westerly edge, flatten grade for entire length of project site for location of drainage pipe. There will be no export or import of soil for this step. This will eliminate ponding condition for 80 percent of the site. Approximate duration: Two months, [ft] Step 2: Prepare area where office and storage trailers and parking will be located at Atlanta end of site. Applicant expects approximately 50 truck trips to/from site for import/export of soil. (All trips planned using a 10 wheel truck.) Approximate duration: One month. Note this work will overlap slightly with Step 1. [ft] Step 3-7: Prepare 500 linear feet of area for plant material. Applicant expects approximately 100-150 truck trips for each of these steps. Approximate duration for each step: Nine to 12 months. Project to be completed in four to five years.”

At the conclusion of the hearing, the City approved CUP No. 96-45, which specified that the proposed land use plan submitted by Kawachi “shall be the conceptually approved layout” with certain modifications not relevant to the present dispute. The CUP was issued with conditions, including a requirement that a grading plan be submitted for approval. The City also issued a notice of *1380 action, which included a finding that the “proposed use will improve ponding and flooding conditions which now occur on the site and impact the adjacent residential properties by grading the site and installing a drainage pipe to accommodate runoff.”

At the same time it issued the CUP, the City found the project exempt from CEQA because it involved only minor grading without the construction of any permanent structures. (Tit. 14, § 15304, subd. (a).) The City filed a notice of exemption on September 30, 1996. The filing of the notice of exemption triggered the 35-day statute of limitations to institute an action challenging the finding that the project was exempt from CEQA (Pub. Resources Code, § 21167, subd. (d)); no challenge was filed.

On July 31, 1998, Kawachi submitted the grading plan required by the CUP (the 1998 grading plan). On August 14, 1998, the City approved Kawachi’s grading plan and issued a grading permit (the 1998 grading permit). By April 1999, Kawachi had completed the first two steps identified in the project summary. The City advised Kawachi he could complete the remaining steps “at [his] leisure.”

In 2003, Kawachi resumed grading for the nursery. In May 2003, the City issued a stop-work notice to evaluate the grading, in response to complaints from Merrilee Madrigal. The City compared the as-built survey with the 1998 grading plan, and determined the completed work was not in compliance with the 1998 grading plan. The City instructed Kawachi to obtain a new grading permit to bring the site into compliance. In May 2004, Kawachi prepared a new grading and drainage plan (the 2004 grading plan). The City approved the 2004 grading plan, which referenced 4,046 cubic yards of earth fill to be imported to the site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Health First v. March Joint Powers Authority
174 Cal. App. 4th 1135 (California Court of Appeal, 2009)
Yamagiwa v. City of Half Moon Bay
523 F. Supp. 2d 1036 (N.D. California, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
55 Cal. Rptr. 3d 209, 147 Cal. App. 4th 1375, 7 Cal. Daily Op. Serv. 2104, 2007 Daily Journal DAR 2655, 2007 Cal. App. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/madrigal-v-city-of-huntington-beach-calctapp-2007.