Madregano v. Wisconsin Gas & Electric Co.

195 N.W. 861, 181 Wis. 611, 1923 Wisc. LEXIS 246
CourtWisconsin Supreme Court
DecidedNovember 13, 1923
StatusPublished
Cited by4 cases

This text of 195 N.W. 861 (Madregano v. Wisconsin Gas & Electric Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Madregano v. Wisconsin Gas & Electric Co., 195 N.W. 861, 181 Wis. 611, 1923 Wisc. LEXIS 246 (Wis. 1923).

Opinion

Rosenberry, J.

The plaintiffs alleged that they were engaged in conducting a meat market and grocery store and were users and consumers of electricity in their place of [613]*613business as well as in their residence; that they had paid all bills rendered to them in accordance with the measurements of the meter installed in their premises; that on the 8th day of September, 1922, the defendant removed the meter from the premises of the plaintiffs and ever since that day has refused and still refuses to furnish the plaintiffs with electricity for use in their place of business and residence.

The complaint further alleges that the defendant justified its conduct by the claim that the plaintiffs were guilty of stealing electrical current during the four-year period and refused to re-install the service unless the sum of '$750 should be paid, that being the amount claimed by the defendant company to be due.

The complainants further allege:

“That the said plaintiffs have been, and now are, ready, willing, and able to pay to the defendant for all current or electricity used by them if the meter of said defendant was inaccurate and did not correctly measure the amount of electricity actually used by them, but the said defendant, through its agents and officers, refused to- give any basis for its claim of $750 and subsequently offered to take $375, as a condition of the replacing of such meter and the furnishing of electricity to the plaintiffs.”

There were other formal allegations. Pursuant to an order to show cause the defendant company was required by order dated September 25, 1922, to furnish the plaintiffs service pending a final determination of the action upon the same terms and conditions as it is furnished to other inhabitants of the city of Kenosha, and as a condition of the making of said order the court required the plaintiffs to execute a bond in the sum of $1,000, with sufficient sureties, conditioned that the plaintiffs would pay for all electrical service furnished by the defendant company to the plaintiffs and pay the customary charge for discontinuing and reinstalling the service to the plaintiffs in the event it should be finally adjudged that the defendant did not wrongfully [614]*614discontinue the service. The defendant answered, and we set out the allegations of the answer because upon the allegations of the answer the determination of the trial court rests. After the allegations of formal matters and that it had furnished current to plaintiffs for four years the defendant alleges:

“That the plaintiffs wrongfully, unlawfully, and intentionally so tampered with said meters by inserting foreign substances therein and in various other ways that the meters failed to register the amount of electricity consumed by the plaintiffs. That the defendant company was deceived and misled by the acts of plaintiffs and submitted bills to the plaintiffs computed at the customary rates according to the meter readings, but erroneous in amount because of the wrongful and intentional acts of the plaintiffs in tampering with the meters as above set forth. That the plaintiffs did pay the bills so rendered, but' at the time of such payments well knew that such bills were incorrect because of their own wrongful and unlawful acts in so tampering with said meter.
“That upon investigation, on or about the first of April, 1922, the defendant became suspicious that something was wrong with the mode and method of registering electricity at the premises of the plaintiffs because of the fact that the electric bills seemed small considering the fact that plaintiffs were operating an ice machine run by a two horse-power motor, a meat grinder driven by a one horse-power motor, and also an electric light load aggregating 2,650 watts. That in order to determine definitely whether or not the electricity furnished at the premises of the plaintiffs was being properly measured and paid for according to the schedules of rates filed, the defendant installed a tested check meter on one of their poles outside of the premises and allowed the meter in the premises to continue as it was. That in approximately four months’ operation the check meter showed a consumption of 3,222 kilowatt hours, while the meter in the premises showed a consumption of 651 kilowatt hours, which would make a difference in the bills of the plaintiffs, over and above that already paid by them on the erroneous measurement of electricity above set forth, of not less than $205.68.
[615]*615“That the defendant then demanded of the plaintiffs that they pay for the electric light and power furnished them, and for which they had not paid, on the basis of an estimated bill covering the four-year period, figured according to the electric light and power actually paid for and the electric light and power which would ordinarily and customarily be used on a premises such as that owned by the plaintiffs where such an electric light and power load was installed, and based also on the amount of electricity consumed during the four months the electricity was correctly measured. That the plaintiffs refused to pay the estimated bill, whereupon the service was discontinued and the plaintiffs informed that before the service would be re-installed they must not only pay the estimated bill for service wrongfully consumed and not paid for, but also the cost of disconnecting and reconnecting the service, which would amount in all to about $750.
“That the plaintiffs refused to pay said bill or any part thereof, and have not paid for the electric light and power consumed by them at the schedule of rates on file with the railroad commission of Wisconsin.
“That it is the usual practice and custom of the defendant, in all cases involving disputes with its customers as to the amount due the defendant under the schedule of rates filed with the railroad commission and in cases of theft or other irregularity, to submit said disputes to the railroad commission for investigation and settlement if said disputes cannot be adjusted between the parties. That in all cases of unpaid balances due for service consumed the service has been discontinued and not reconnected until the amount due the company has been paid together with the cost of disconnecting and re-installing and certain other requirements have been met. That the controversy between the plaintiffs and the defendant as set forth in the pleadings herein was handled by the defendant company under its usual custom and practice.
“That the acts of the defendant and its entire conduct in this matter is entirely within the provisions of the public utilities law, and is a matter purely within the jurisdiction of the railroad commission.”

The defendant also alleges that the court was without jurisdiction for the reason that the railroad commission had [616]*616full jurisdiction of the subject matter of the action and denied that any damage had been done to the plaintiffs.

Upon the filing of the answer the plaintiffs moved:

“Upon the pleadings of this action, the complaint of the plaintiffs, and the answer of the defendant, for judgment that the injunctional order heretofore entered be made permanent.”

The defendant objected to the granting of the motion and offered to prove the allegations set forth in its answer. The motion of the plaintiffs was granted ánd thereupon final judgment was entered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

All Electric Service, Inc. v. Matousek
174 N.W.2d 511 (Wisconsin Supreme Court, 1970)
Buckley v. Park Building Corp.
143 N.W.2d 493 (Wisconsin Supreme Court, 1966)
City of Two Rivers v. Town of Wabeno
266 N.W. 178 (Wisconsin Supreme Court, 1936)
Bailey v. Interstate Power Co.
228 N.W. 644 (Supreme Court of Iowa, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
195 N.W. 861, 181 Wis. 611, 1923 Wisc. LEXIS 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/madregano-v-wisconsin-gas-electric-co-wis-1923.