This text of 3 Wis. 287 (Madison, Watertown, & Milwaukee Plank Road Co. v. Reynolds) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Madison, Watertown, & Milwaukee Plank Road Co. v. Reynolds, 3 Wis. 287 (Wis. 1854).

Opinion

By the Court,

Whit on, C. J.

It appears that by an act of the legislature of the territory of Wisconsin, passed on the second day of February,. A. D. 1846, a company was incorporated by the [290]*290name of the “ Lisbon and Milwaukee Plank Road Company.” This company had the power to construct a plank road from a point where the north Madison territorial road crossed the range line divi-fpng rangeg nineteen and twenty, to f.a point within one mile of the Milwaukee river, in the direction of the westward of [Milwaukee village. The company also had the power to “ extend said plank road from said range line nineteen and twenty to the village of Watertown, in Jefferson county, or any part of the way to said village.”

The company had power, whenever ten consecutive miles ofthe road should be completed, to cause a tollgate to be erected, or when five miles should be completed, a half toll-gate, at which gates the company was entitled to receive from travellers on the road certain tolls. Section 18 of this act is as follows : “ The corporation hereby created, shall exist and be continued twenty years, and the future State of Wis cousin, through its legislature, may at any time alter or repeal this act.”

The next act of the legislature bearing upon the question before ns, was passed by the legislature of the territory of Wisconsin, on the first day of March, 1848, and is entitled “an act to provide for the continuation of the Lisbon Plank Road, from Watertown to Madison.” By it, the company had the right to “locate and construct a plank road from Watertown to Madison, in continuation of the road wh* m -s fid company is authorized to make from Milwau.. ■ "mi Lisbon to Watertown.”

This act contained a provision changing the name of the company to the “Madison, Watertown and Milwaukee Plank Road Company.” It also contained [291]*291a section fixing the tolls which the company authorized to take, and in this respect it was an exact copy of the act of February 2d, 1846 ; fixing the tolls at the same rate. It also contained a section as follows : “ This act may be amended by any future legislature of the territory or State of Wisconsin.’’ The last act passed by the legislature in relation to the subject, was passed on the 2nd day of April, 1850, and is entitled “ an act to amend the charter of the Madison, Watertown and Milwaukee Plank Koad Company.”

By this act it is provided, that “whenever said company shall have completed their road, or any five consecutive miles thereof, the said company may erect one or more toll-gates upon said road, but not within three miles of each other, and may demand and receive tolls not exceeding the following rates : for every vehicle drawn by one animal, one cent per mile ; for every vehicle drawn by two animals two cents per mile ; and if drawn by more than two animals half a cent per mile for every additional animal. For every horse and rider or led animal, a half cent per mile. For one .score of sheep or swine one cent per mile, and for every score of neat cattle three cents per mile.”

It is claimed that the company is authorized to demand and receive under this section, at each gate through which a traveller passes, a sum equal to the amount which he would be required to pay if he travelled the whole distance between the gates, whether he actually travelled the distance or not, and that as the toll taken by the agent of the company did not exceed the sum which the company was an-[292]*292thorized to receive by tins construction of the statute, no penaly was incurred by receiving it.

Ia support of this position we are referred to the case of Mallory vs. Austin, 7 Barb. R. 626, and caseg p[iere referred to. These cases appear to establish the doctrine in the State of New York, that under statutes which authorize companies to receive tolls for each mile travelled upon their roads, a gross amount may be demanded at each gate equal to the toll as fixed by law for the whole distance between the gates, although the whole distance may not have been travelled. But our statutes seem to require that a different construction should be given to these provisions. Section three of chapter four hundred and. seventy-eight of the session laws of 1852, imposes a penalty of ten dollars upon every traveller who shall report untruly, or refuse to report when requested by any toll-gatherer or other person employed on the road, the distance he has travelled, or desires to travel. Section two of the same chapter provides that the company shall erect and maintain suitable mile-posts on the road. These provisions were evidently intended to facilitate the collecting of tolls for the distance actually travelled, and are repugnant to the idea that the company can take toll of a traveller who passes a toll-gate, for the whole distance between the gates, although the whole distance has not been travelled. We therefore think that the tolls established by the act of 1853, are different from those established by the laws of 1846 and 1848, above referred to.

As the action in this case is brought against the company for the act of its agent, who demanded of [293]*293Reynolds the sum fixed by these acts, and as that is more than the amount which the company is authorized to receive, if Reynolds can only be required to pay for the distance he actually travelled, we are driven to the necessity of deciding whether the act of the legislature which restricts the company to this rate of toll is obligatory. The counsel for the company contends that it is not, for the reason that it impairs the obligation [of the contract entered into by the legislature of the territory and the company, by the act of incorporation, and is thus repugnant to the Constitution of this State, (Art. 1, § 12,) and also to the Constitution of the United States, (Art. 1, § io.)

We are not disposed to controvert the proposition, that an act of the legislature which creates a corporation and confers privileges upon it, in consideration of certain things to be done by the corporation, is a contract within the meaning of the prohibition contained in the Constitution of Wisconsin and of the United States. We are therefore forced to the consideration of the question whether the alteration made by the legislature in the charter of the company, was authorized. As this corporation was created by the legislature of the territory of Wisconsin, we lay out of view the provision contained in Art. 11, 5, 1, of our State Constitution, which provides “ that all general laws or special acts granted under the provisions of this section, may be altered, or repealed by the legislature at any time after their passage.

The section of which the words above quoted formed a part, authorizes the legislature to create corporations by general laws, and by special acts in certain cases. The provision which is quoted may [294]*294obviate the necessity of the consideration of questions like the one before ns in all cases where the corporation is created by the State.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Superior Water, Light & Power Co. v. City of Superior
181 N.W. 113 (Wisconsin Supreme Court, 1921)
Milwaukee Electric Railway & Light Co. v. Railroad Commission
142 N.W. 491 (Wisconsin Supreme Court, 1913)
City of Superior v. Douglas County Telephone Co.
122 N.W. 1023 (Wisconsin Supreme Court, 1910)
Wisconsin River Improvement Co. v. Pier
118 N.W. 857 (Wisconsin Supreme Court, 1908)
Russell v. Ayer
120 N.C. 180 (Supreme Court of North Carolina, 1897)
Palms v. Shawano County
21 N.W. 77 (Wisconsin Supreme Court, 1884)
Vary v. Norton
6 F. 808 (U.S. Circuit Court for the District of Western Michigan, 1881)
Sellers v. Union Lumbering Co.
39 Wis. 525 (Wisconsin Supreme Court, 1876)
Attorney General v. Chicago & Northwestern Railway Co.
35 Wis. 425 (Wisconsin Supreme Court, 1874)

Cite This Page — Counsel Stack

Bluebook (online)
3 Wis. 287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/madison-watertown-milwaukee-plank-road-co-v-reynolds-wis-1854.