MacK Manufacturing Co. v. Massachusetts Bonding & Insurance

103 S.E. 499, 114 S.C. 207, 1920 S.C. LEXIS 100
CourtSupreme Court of South Carolina
DecidedMarch 29, 1920
Docket10388
StatusPublished
Cited by6 cases

This text of 103 S.E. 499 (MacK Manufacturing Co. v. Massachusetts Bonding & Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacK Manufacturing Co. v. Massachusetts Bonding & Insurance, 103 S.E. 499, 114 S.C. 207, 1920 S.C. LEXIS 100 (S.C. 1920).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 209 March 29, 1920. The opinion of the Court was delivered by Action by the Mack Manufacturing Company on a bond executed by Bowe Page and the Massachusetts Bonding Insurance Company to the city of Greenville.

The object of the action is to recover some $12,000 for brick supplied by the Mack Company to Bowe Page to pave the streets of the city of Greenville.

Pursuing the terminology adopted in 108 S.C. 164,93 S.E. 713, we shall refer to the Mack Manufacturing Company, the materialman, as the Mack Company; to the Massachusetts Bonding Insurance Company as the bond company; to the Carolina National Bank as the bank; to the city of Greenville as the city; and we shall refer to Bowe Page as the contractors; and to the Greenville Traction Company as the traction company.

We held on a former appeal that the complaint states a cause of action in the Mack Company against the bond company,103 S.C. 55, 87 S.E. 439.

Thereafter, a party hitherto not in the cause, the bank, was brought into it on motion of the bond company, 108 S.C. 164,93 S.E. 713.

The present appeal is from the opinion of the Circuit Court which tried the cause on the merits; for a trial by jury was waived, the master took the testimony, and the Court tried the cause.

The judgment of the Court went practically to sustain all the contentions of the bond company, and the Mack Company and the bank have appealed. *Page 225

But before so much shall be considered it is meet to here dispose of the first of two exceptions made by the bond company.

The first exception of the bond company goes to the point that the city and the bond company never intended, by the paper writing which they signed called the bond and extensively set out in 103 S.C. 55, 87 S.E. 439, to protect the materialmen; and if they expressed any such intention it was a mistaken expression.

There is no testimony of any weight which would warrant us to conclude that the parties did not intend to say that which we have before concluded they did say.

The bond being intact, the bond company seeks to defeat the instant recovery upon it on these grounds, to wit:

1. That the contract of August 29, 1910, between the contractors and the Mack Company, which the bond operated to secure, was abrogated by three other written agreements which the contractors entered into, to wit:

(a) One dated October 24, 1910, between the contractors and the traction company touching the pavement of the car trackway.

(b) One dated May 16, 1911, between the contractors and the Mack Company about the method of payment, etc.

(c) One dated August 17, 1911, between the city, the contractors, and the Mack Company about a transference of attachment lien from brick to money, etc.

2. That the same contract of August 29, 1910, was abrogated by the following several acts of the contractors and the Mack Company, to wit:

(a) By the receipt of $10,000 by the contractors from the city on January 5, 1911, when only $7,263.62 was due to be paid to the contractors. *Page 226

(b) By the assignment by the contractors to the bank of their several monthly installments of payment from the city, when the same had been hitherto assigned by the contractors to the bond company.

(c) By the stoppage in transit by the Mack Company of eleven cars of brick bound for the contractors and the subsequent release of the same to the city.

(d) By the Mack Company's attachment of brick and other property of the contractors, and then releasing the attachment.

3. That the Mack Company, as creditor of the contractors, is estopped to set up its present claim by the record in the bank against the city to the extent of the recovery by the city in that case.

4. That the Mack Company's present right to set up its claim has been lost by the city's culpable negligence at the completion of the work by it, in paying to the bank the balance it then had on hand, instead of applying the same to the materialmen's claim.

5. The bond company lastly contends that if these defenses shall fail and the bond be yet intact, yet the bank is liable ahead of the bond company to pay the plaintiff's claim.

Before any of these defenses shall be examined, there ought to be stated so general a rule of law as is possible and which will ordinarily operate to discharge such a surety as the bond company. To that end the bond company has cited for reliance our own case of Greenville v. Ormand,51 S.C. 121, 28 S.E. 147. The sureties in that case were personal; the sureties in the instant case are "bondmen and insurers" for a compensation.

It is true the bond company's liability is not absolute; those for whom they undertake may do acts which are substantially hurtful to the bond company and in real contravention to the terms of the bond contract, and in such a case the *Page 227 bond company will be discharged. But the liability which the bond company assumed was not confined in time and place to the performance of a single act by the contractors, as is commonly the case with strict sureties. The contract, evidenced by the bond, the application, and the specifications, contemplated many and complicated transactions by many parties in many periods; and the relationship of the bond company thereto was not simply one of passivity. The bond company was constituted a possible actor in the whole transaction from start to finish. Its attitude was to be at attention. See 21 R.C.L. 1060; Greenville v. Guaranty,83 S.C. 90, 64 S.E. 518, 964; Mack v. Mass., 103 S.C. 55,87 S.E. 439; Atlanta v. Laurinburg, 163 Fed. 690, 90 C.C.A. 279; Guaranty v. Pressed Brick, 191 U.S. 416,24 Sup. Ct. 142, 48 L.Ed. 242; Hill v. American, 200 U.S. 202,26 Sup. Ct. 168, 50 L.Ed. 437; Phil. v. Fidelity,231 Pa. 208, 80 A. 62, Ann. Cas. 1912b, 1085.

So the real inquiry is: Have the supplementary agreements of the contractors before referred to, and the acts or omissions of the contractors, or of the city or the Mack Company before recited, operated to do a real hurt to the bond company by an attempted material alteration of its bond contract, or by the loss of a right not now available to it?

Reverting. now, to the aforespecified defenses in their order, that one is plainly untenable which refers to the effect of the contract between the contractors and the traction company touching the paving of the trackway.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E & S INVESTMENT CORP. v. Richland Bowl, Inc.
216 S.E.2d 522 (Supreme Court of South Carolina, 1975)
Birnbaum v. Hall
101 F. Supp. 605 (E.D. South Carolina, 1951)
Cantey v. Newell Contracting Co.
178 S.E. 342 (Supreme Court of South Carolina, 1935)
American Hardware & Equipment Co. v. Detroit Fidelity & Surety Co.
156 S.E. 770 (Supreme Court of South Carolina, 1931)
Standard Oil Co. v. Powell Paving & Contracting Co.
138 S.E. 184 (Supreme Court of South Carolina, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
103 S.E. 499, 114 S.C. 207, 1920 S.C. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mack-manufacturing-co-v-massachusetts-bonding-insurance-sc-1920.