MacArthur Brothers Co. v. . Kerr

107 N.E. 572, 213 N.Y. 360, 1915 N.Y. LEXIS 1457
CourtNew York Court of Appeals
DecidedJanuary 5, 1915
StatusPublished
Cited by13 cases

This text of 107 N.E. 572 (MacArthur Brothers Co. v. . Kerr) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacArthur Brothers Co. v. . Kerr, 107 N.E. 572, 213 N.Y. 360, 1915 N.Y. LEXIS 1457 (N.Y. 1915).

Opinion

Hiscock, J.

The appellant entered into a contract for railroad construction in the state of Pennsylvania. It made a sub-contract with the firm of Lamorte & McCabe to do part of the work and received from the Fidelity and Deposit Company of Maryland a bond guaranteeing to the extent of $2,000 the faithful performance by said subcontractors of their contract. As a condition of executing this bond said Fidelity and Deposit Company required and received a bond executed by said sub-contractors and the respondent’s testatrix for its indemnity and protection and which amongst other things contained the following material provision:

“ Second. That said Mary Crage (the testatrix) shall and will at all times indemnify, and keep indemnified, and save harmless the said company from and against all loss, damages, costs, charges, counsel fees and expenses whatsoever which said company shall or may for any cause, at any time, sustain or incur by reason or in consequence of said company having executed' or agreed to execute said instrument (its bond to appellant as surety for said sub-contractors); and do further covenant and agree to pay to said company or its representatives all damages for which said company or its representatives shall become responsible upon the said bond or undertaking before said company or its representatives shall be compelled to pay the same, any sum so paid, however, to be applied to the payment of such damages.”

Said sub-contractors failed to fulfill their obligations and complete said contract as provided and guaranteed by *364 the Fidelity and Deposit Company, and subsequently an action was brought by the appellant against said company on said bond to recover the full amount thereof, because of such default. The respondent’s testatrix'with proper references to her obligations on her undertaking before mentioned was duly notified of the commencement and prosecution of this action and requested to defend the same, which, however, she failed to do. The plaintiff in that action recovered a judgment against the Fidelity and Deposit Company for the full amount of its undertaking and later without payment of any money the latter transferred to the former the bond executed to it by respondent’s testatrix and all rights of action thereon and thereunder and in consideration of such transfer the judgment recovered against it as aforesaid was satisfied. On said assignment and transfer appellant brought this action and the question, thus far decided adversely to it, is whether any cause of action had accrued in favor of the Maryland company against the respondent’s testatrix on her undertaking which it could transfer to the appellant. It seems perfectly plain to us that there had.

By the recovery of the judgment against it, after notice to the testatrix of the action and request to defend, the liability of the Fidelity and Deposit Company as surety on its bond was conclusively established as against her, even though the judgment was recovered in a foreign state. (Konitzky v. Meyer, 49 N. Y. 571-576.)

The question which testatrix or her representatives thereafter could litigate was whether the liability thus established against the Maryland company was one against which she had indemnified it under her undertaking.'

It is admitted that the undertaking executed by the testatrix would have bound her to indemnify the Maryland company if the judgment against it had been paid and thereby actual damage incurred. It is, however, insisted that this was the limit of her obligation; that the bond was one of ordinary indemnity and became effective *365 only when the indemnified had suffered actual damages by payment of money or in some equivalent manner.

It may be conceded that this would be the interpretation and effect of a bond of indemnity in the usual form, but of course the parties to the undertaking in question had a perfect right to provide otherwise if they saw fit and this was what they did. In the first sentence of the provision which has been quoted from the bond, the indemnitor obligated herself in the usual manner to indemnify, and keep indemnified, and save harmless the said company from and against all loss, damage, costs, charges, counsel fees and expenses,” and if this were all this appeal would be easily and surely decided in accordance with the contentions of the respondent. But after this obligation was thus expressed said indemnitor did “ further covenant and agree to pay to said company or its representatives all damages for which said company or its representatives shall become responsible upon said bond or undertaking before said company or its representatives shall be compelled to pay the same, any sum so paid, however, to be applied to the payment of such damages.” The parties certainly must have intended something by this additional clause. If they did not design to change the measure of liability stated by the first clause and incident to ordinary bonds of indemnity, it was utterly senseless to add the second clause. Assuming, therefore, as we should, that they meant something by the employment of this additional provision and that it is not to be entirely disregarded, we are simply called on to give to it a reasonable interpretation. This seems to be perfectly plain. It binds the indemnitor to pay to the indemnified all damages for which said company * * * shall become responsible * * * before said company or its representatives shall be compelled to pay the same.” What could be clearer than this language ? It is only by some technical interpretation that we can find anything else than a simple agree *366 ment by the surety to discharge any liability for which the indemnified might become “responsible,” “before,” that is, without waiting for enforcement of this liability by payment and the infliction of damages in the ordinary manner.

It seems to be beside the question to say in opposition to this that this was a bond of indemnity, that the Maryland company did not pay any money to satisfy the judgment against it and that, therefore, no damages have been suffered against which indemnity can be asked. Of course the bond was one of indemnity, and it might have been fitted to this latter theory, but it was not. The thing it indemnified against was not damages actually suffered, but liability for damages.

That situation arose. By a judgment which was conclusive against thé surety the indemnified was adjudged to be liable in the sum of two thousand dollars on account of matters contemplated by her bond and which judgment so far as appears was enforceable at any time. Before and, therefore, without discharging this responsibility by payment, the indemnified was entitled to demand of the surety that she pay the judgment in accordance with the terms of her undertaking. ' This was a perfected right of action which could be assigned and transferred and which may be enforced by the appellant as such assignee.

If authorities are needed to sustain the proposition that parties - if they so desire may enlarge the ordinary scope of a bond of indemnity and create an obligation thereunder to discharge a liability which has accrued without waiting for actual satisfaction thereof by, and damage to, the ■ indemnified in this manner they may be easily found. (Chace v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Ryan
2018 NY Slip Op 3380 (Appellate Division of the Supreme Court of New York, 2018)
Pfizer, Inc. v. Stryker Corp.
348 F. Supp. 2d 131 (S.D. New York, 2004)
Federal Insurance v. Walker
73 A.D.2d 870 (Appellate Division of the Supreme Court of New York, 1980)
Maryland Casualty Co. v. Straubinger
19 A.D.2d 26 (Appellate Division of the Supreme Court of New York, 1963)
American Surety Co. v. Sanitary Sleep Products Corp.
12 A.D.2d 809 (Appellate Division of the Supreme Court of New York, 1961)
Dery v. Wyer
265 F.2d 804 (Second Circuit, 1959)
Debt v. Wyer
265 F.2d 804 (Second Circuit, 1959)
Peerless Casualty Co. v. Sawitz & Simon, Inc.
260 A.D. 448 (Appellate Division of the Supreme Court of New York, 1940)
First National Bank of New York v. Bankers Trust Co.
151 Misc. 233 (New York Supreme Court, 1934)
City of Syracuse v. Standard Accident Insurance
210 A.D. 165 (Appellate Division of the Supreme Court of New York, 1924)
German American State Bank v. Bear
206 P. 902 (Supreme Court of Kansas, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
107 N.E. 572, 213 N.Y. 360, 1915 N.Y. LEXIS 1457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macarthur-brothers-co-v-kerr-ny-1915.