Mabry v. Priester

333 S.W.2d 684, 1960 Tex. App. LEXIS 2093
CourtCourt of Appeals of Texas
DecidedMarch 17, 1960
DocketNo. 13340
StatusPublished
Cited by3 cases

This text of 333 S.W.2d 684 (Mabry v. Priester) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mabry v. Priester, 333 S.W.2d 684, 1960 Tex. App. LEXIS 2093 (Tex. Ct. App. 1960).

Opinion

BELL, Chief Justice.

This suit originated in a petition filed by appellee, seeking to cancel a mechanic’s lien filed in the Mechanic’s Lien Records of Harris County filed by appellant, and seeking to remove such as a cloud on title. The theory of the suit was that while appellant may have been employed by oral contract to draw plans and specifications for a building to be used for a supper club or restaurant, he did not perform his agreement because he never completed plans and specifications that could be used in constructing a building, but they were so incomplete that no contractor could take them and make a bid without in many ways qualifying the bid or estimate so as to cover the deficiencies in the plans and specifications, and even with this there would be different ways to meet these deficiencies so that the contractors would not be bidding on the same thing. Too, the agreement was, so appellee alleged, that the plans and specifications must be for a building that could be built for from $60,000 to $70,000, certainly for not more than $70,000, and, because of the incompleteness of the plans and specifications, only two contractors made a bid or estimate, one being for some $171,000 and one for some $175,000, and even then the estimates were qualified to care for phases of construction not covered by the plans and specifications, one bidder having made 19 qualifications.

The appellant answered asserting compliance with the agreement and filed a cross-action to recover a 5% fee on the cost of building the building. He claimed a fee of $12,500, but gave credit of $1,500, so his cross-action was for recovery of an architect’s fee of $11,000, and foreclosure of his lien on certain described land belonging to appellee. He contended his plans and specifications were complete and that while it was originally planned by ap-pellee to build a place costing $60,000 to $70,000, the plan was changed so that a larger and more elaborate place was to be built and the limitation of cost was removed.

The alleged agreement was made in 1954 and the work on the plans and specifications from November, 1954 through August, 1955.

Trial was before a jury in 1958. At the conclusion of all testimony and after both sides had rested, appellee filed a motion for instructed verdict, which was granted by the court, and judgment was rendered [686]*686that appellant take nothing and that appel-lee recover judgment cancelling the lien and removing it as a cloud on title.

We should note that appellee also asked that she recover the $1,500 she had paid appellant, but she expressly and in open court agreed in connection with the proceeding on the motion for instructed verdict that the court should find against her on this claim.

The grounds of the motion for instructed verdict, without detailing them, were that there was no pleading or evidence that appellant was at the time of his agreement, or when he performed such work as he did perform, a duly licensed architect in good .standing; that recovery could not be had on quantum meruit because the evidence showed an express contract; and that the undisputed evidence showed the plans and specifications that were prepared were so substantially incomplete that they could not be used to build the building contemplated, and certainly not for $70,000.

After this motion was made, and prior to action on it by the court, appellant asked leave of the court to file a trial amendment alleging he was a duly licensed architect and was at all times mentioned (meaning apparently at all times mentioned in his pleadings) in good standing. Appellee asserted surprise and that since the records were kept in Austin she would have to be given time to investigate and delay would be caused. The court refused leave to file.. Appellant did not ask to be allowed to withdraw his announcement of ready, nor did he ask to be allowed to reopen the case so he could make proof.

The appellant, as grounds for reversal, contends that the trial court erred in not allowing the trial amendment to be filed; that the burden was on appellee under Rule 94, Texas Rules of Civil Procedure, to plead that appellant was not a duly licensed architect in good standing, such being an affirmative defense; that the issue was tried by consent and the evidence showed appellant was a duly licensed architect in good standing; that the judgment on the cross-action was contrary to the law and evidence; and the court erred in cancel-ling the lien because a fact issue as to its validity was raised.

The question first presented is-whether it is incumbent upon a person, seeking to recover an architect’s fee to-allege and prove that he, at the time the employment agreement was entered into’ and while the work was being performed, was a duly registered architect in good standing. We have concluded that it is.

All cases decided in Texas involving an architect suing for a fee have held; that recovery may not be had unless the-architect has registered, because it is unlawful for him to practice without registering, as provided by Article 249a, Vernon’s-Ann.Texas St. It is probably more accurate to say the cases at least by dictum-have so stated, or all parties assumed this-to be true, and the cases actually turned on a matter of waiver of pleading or proof by failure to raise the issue in the trial1 court. See the following cases: Guffey v. Collier, Tex.Civ.App., 203 S.W.2d 812, no writ hist.; Shotwell v. Phillips, Tex.Civ.App., 180 S.W.2d 223, writ dism. In the case of Clark v. Eads, Tex.Civ.App., 165 S.W.2d 1019, ref., w. m., the court, among other things, held the architect who had not complied with Article 249a could not recover his fee. The statutes regulating the practice of architecture are for the purpose of protecting the public, just as are statutes regulating engineers and dealers in securities. In those cases it is also held’that the contract of a person not complying with its provision by qualifying is not enforceable. M. M. M., Inc. v. Mitchell, 153 Tex. 227, 265 S.W.2d 584; Kadane v. Clark, 135 Tex. 496, 143 S.W.2d 197; Gray v. Blau, Tex.Civ.App., 223 S.W.2d 53, n. r. e.

As to whether appellant must have alleged and proved his compliance or whether it is an affirmative defense, there is only one case involving an architect in which [687]*687the matter has been specifically passed on. The case of Clark v. Eads, supra, held, among other things, that it was not an affirmative defense that must be pled by the defendant under Rule 94, but it must be alleged and proven by the architect seeking to recover his fee. Again, the cases first above cited seem to say this is true, but under the facts of those cases the courts held there was a waiver by failure to raise the issue in the trial court.

In this case there was no waiver under Rule 90, because the matter was specifically called to the attention of the trial court in a motion for instructed verdict.

Appellant, however, urges that it was error for the trial court not to have allowed him to file the trial amendment offered as above stated.

Rule 66, T.R.C.P., provides for trial amendments and enjoins liberality in allowing them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Opinion No.
Texas Attorney General Reports, 1984
Farha v. Elam
385 S.W.2d 692 (Court of Appeals of Texas, 1964)
Mabry v. Priester
338 S.W.2d 704 (Texas Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
333 S.W.2d 684, 1960 Tex. App. LEXIS 2093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mabry-v-priester-texapp-1960.