Mabey v. Dixie Elec Mbrship

CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 7, 2007
Docket06-30774
StatusUnpublished

This text of Mabey v. Dixie Elec Mbrship (Mabey v. Dixie Elec Mbrship) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mabey v. Dixie Elec Mbrship, (5th Cir. 2007).

Opinion

No. 06-30774

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit

FILED August 7, 2007 No. 06-30774 Charles R. Fulbruge III Clerk Ralph R. Mabey Appellee v.

Dixie Electric Membership Corp.

Appellant

Appeal from the United States for the Middle District of Louisiana, Baton Rouge Division USDC No. 3:06-CV-11

Before DENNIS, CLEMENT, and PRADO, Circuit Judges. PER CURIAM:* Plaintiff Mabey, as bankruptcy trustee for Cajun Electric Power Cooperative (“Cajun”), sued to recover $2,754,760.04 for 39 months of electricity received by defendant Dixie Electric Membership Corporation (“DEMCO”) but unmetered (and therefore not billed) by Cajun until a calibration error in a transformer at a power substation was discovered. The bankruptcy court granted Cajun’s motion for summary judgment and denied DEMCO’s motion; the district court affirmed without oral argument. After review of the record and the parties' arguments, we agree. The judgment of the district court is therefore AFFIRMED. I. Cajun is a nonprofit corporation that generates and transmits electricity to members of the cooperative as well as non-members. The cooperative's members, including DEMCO, are also

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. No. 06-30774

non-profit electric distribution cooperatives, who sell and distribute power to the end consumer. DEMCO was required by a contract known as the 1976 Wholesale Power Supply Agreement (“WPSA”) to purchase from Cajun at wholesale all of its electric power requirements. The WPSA contains, inter alia, the following provisions: 1. GENERAL. The Seller [Cajun] shall sell and deliver to the Member [DEMCO] and the Member shall purchase and receive from the Seller all electric power and energy which the Member shall require for the operation of the Member's system to the extent that the Seller shall have such power and energy and facilities available; provided, however, that the Member shall have the right to continue to purchase electric power and energy under any existing contract or contracts with a supplier other than the Seller during the remainder of the term thereof. If the Member continues to purchase electric power and energy under a contract or contracts with a supplier or suppliers other than the Seller, then the power and energy purchased under such contract or contracts shall be paid for by Seller for the account of the Member, and the Member shall be billed by Seller for such power and energy in accordance with the terms and conditions of [Article] 4 hereof.

3. DELIVERY FACILITIES. The Seller shall be responsible for the facilities to deliver power and energy to the Point or Points of Connection [e.g., a power substation]. The Member shall be responsible for providing the facilities necessary to take and use the power and energy from the Point or Points of Connection. The parties shall provide and maintain, or cause to be provided and maintained, switching and protective equipment which may be reasonably necessary to protect the system of the other. Meters and metering equipment shall be furnished, maintained, and read, or caused to be furnished, maintained, and read, by the Seller. 4. RATE. .... The Member shall pay the Seller for all electric power and energy furnished hereunder at the rates and on the terms and conditions set forth in Rate Schedule A....

6. METER TESTING AND BILLING ADJUSTMENT. The Seller shall test and calibrate or cause to be tested and calibrated meters by comparison with accurate standards at intervals of twelve (12) months. The Seller shall also make or cause to be made special meter tests at any time at the Member's request. . . . The readings of any meter which shall have been disclosed by test to be inaccurate shall be corrected for the ninety (90) days previous to such test in accordance with the percentage of inaccuracy found by such test. If any meter shall fail to register for any period the Member and the Seller shall agree as to the amount of energy furnished during such period and the Seller shall render a bill therefor.

In the 1990s, DEMCO built the Vignes power substation; although constructed by DEMCO alone, the facility was jointly owned by DEMCO and Cajun. Entergy, per a contractual arrangement with Cajun, provided electricity through the substation to DEMCO for further distribution. The station had two meters: one, a "high side" meter, belonged to Cajun and measured electricity coming No. 06-30774

into the station from Entergy's lines; the other, a "low side" meter, belonged to DEMCO and measured the electricity DEMCO received for distribution. The station became operational in September 1996. At that time, it is undisputed that Cajun's meter was incorrectly calibrated, such that it registered only half of the electricity entering the substation. Cajun's resulting bill to DEMCO therefore covered only half of the electricity provided. DEMCO, however, had a properly calibrated meter and was charging its customers for the full amount of electricity provided. The problem continued for 39 months until, in December 1999, an Entergy employee discovered the problem. The meter itself was corrected the same day. Entergy and Cajun executed a plan under which Cajun reimbursed Entergy for Entergy's share of the unmetered electricity delivered to DEMCO. In January 2000, Cajun made written demand on DEMCO for the unmetered electricity received but not billed, a total value of $2,754,760.04. The following month, DEMCO tendered a check for $179,483.82, citing to a provision under the WPSA known as the "reach back" provision that, DEMCO claimed, limited its liability for excess electricity to the excess received during the 90 days prior to discovery of the error. Cajun refused tender; the company subsequently underwent a bankruptcy reorganization. On February 17, 2003, the bankruptcy trustee sued DEMCO as a part of an adversary proceeding related to Cajun's declaration of bankruptcy under Chapter 11. The trustee sought to recover the entirety of the $2,754,760.04, asserting three different bases for recovery: (1) breach of contract; (2) indemnity (for the payments Cajun made to Entergy for the power sold to DEMCO); and (3) unjust enrichment. The trustee moved for summary judgment on the issue of liability in January 2005; DEMCO responded with a motion to dismiss for failure to state a claim or, in the alternative, for summary judgment. In September 2005, the bankruptcy court granted summary judgment for Cajun. DEMCO appealed both the grant of Cajun's motion and the denial of its own; at the same time, it also asserted that an order of the Louisiana Public Service Commission barred Cajun from seeking reimbursement for billing errors over six months old. In June 2006, the district court, without oral argument, affirmed the judgment of the bankruptcy court. DEMCO timely appeals. II. We review the bankruptcy court's grant of a motion for summary judgment de novo. In re: Ark-La-Tex Timber Co., 482 F.3d 319, 328 (5th Cir. 2007). Summary judgment is appropriate where the record shows “that there is no genuine issue as to any material fact and that the moving party is No. 06-30774

entitled to a judgment as a matter of law.” FED. R. CIV. P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). Facts and inferences reasonably drawn from those facts should be taken in the light most favorable to the non-moving party. Ark-La-Tex, 482 F.3d at 329 (citing Duckett v. City of Cedar Park,

Related

Allen v. Rapides Parish School Board
204 F.3d 619 (Fifth Circuit, 2000)
STATE FARM MUT. AUTO. INS. v. Berthelot
732 So. 2d 1230 (Supreme Court of Louisiana, 1999)
Parker v. Harris Pine Mills, Inc.
291 P.2d 709 (Oregon Supreme Court, 1955)
Unverzagt v. Young Builders, Inc.
215 So. 2d 823 (Supreme Court of Louisiana, 1968)
Cleco Evangeline v. Louisiana Tax Com'n
813 So. 2d 351 (Supreme Court of Louisiana, 2002)
Duckett v. City of Cedar Park
950 F.2d 272 (Fifth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Mabey v. Dixie Elec Mbrship, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mabey-v-dixie-elec-mbrship-ca5-2007.