M2J2S, LLC v. United Telephone Company of PA

CourtSuperior Court of Pennsylvania
DecidedJuly 9, 2019
Docket1185 MDA 2018
StatusUnpublished

This text of M2J2S, LLC v. United Telephone Company of PA (M2J2S, LLC v. United Telephone Company of PA) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M2J2S, LLC v. United Telephone Company of PA, (Pa. Ct. App. 2019).

Opinion

J-A11028-19

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

M2J2S, LLC D/B/A SERVICEMASTER : IN THE SUPERIOR COURT OF RESTORATION SERVICES, MICKEY : PENNSYLVANIA RAPP AND JESSIE BOCK : : : v. : : : UNITED TELEPHONE COMPANY OF : No. 1185 MDA 2018 PENNSYLVANIA, LLC D/B/A : CENTURYLINK : : Appellant :

Appeal from the Order Dated June 21, 2018 In the Court of Common Pleas of Cumberland County Civil Division at No(s): 2018-04421

BEFORE: BOWES, J., OLSON, J., and STABILE, J.

MEMORANDUM BY OLSON, J.: FILED JULY 09, 2019

Appellant, United Telephone Company of Pennsylvania, LLC, d/b/a

CenturyLink (CenturyLink) appeals from the order entered on June 21, 2018

denying CenturyLink’s preliminary objections to a complaint filed by M2J2S,

LLC, d/b/a ServiceMaster Restoration Services (ServiceMaster).1 Upon

review, we reverse and remand for further proceedings consistent with this

memorandum.

This case arises from a contract between CenturyLink and ServiceMaster

for the remediation of extensive water damage and mold contamination of

____________________________________________

1 Mickey Rapp and Jessie Bock originally asserted claims against CenturyLink. Those claims were dismissed by the trial court. Rapp and Bock are not parties to the current appeal. J-A11028-19

property leased by CenturyLink. ServiceMaster and CenturyLink entered into

a contract on June 11, 2015. The parties also signed a “statement of

authorization for mold,” which included the following arbitration clause:

Any dispute between Owner [(CenturyLink)] and ServiceMaster (including the interpretation of this Agreement), except for non- payment of invoices for ServiceMaster’s work, shall be submitted to binding arbitration. … The arbitration shall be binding on all parties and judgment may be entered in any court having jurisdiction.

Statement of Authorization for Mold, 6/11/2015, ¶ 7 (original emphasis

omitted).

At the time of the agreement, CenturyLink indicated there was no

asbestos in the building. According to ServiceMaster, once it began work,

CenturyLink interfered in numerous ways, the most serious of which was a

site visit by a CenturyLink contractor who, without wearing protective

equipment, removed materials from the property for asbestos testing. After

this incident, ServiceMaster and CenturyLink quarreled over the presence of

asbestos on the property.

On July 23, 2015, CenturyLink sent ServiceMaster a notice of claims,

“which claimed … breaches of contract, claims of contractual undertakings,

and violation of asbestos removal and disposal regulations.” Complaint, ¶

127. ServiceMaster responded to these allegations; CenturyLink did not reply

except to inform ServiceMaster that it received its response.

On August 12, 2015, ServiceMaster filed a writ of summons in the trial

court. On September 10, 2015, according to ServiceMaster, CenturyLink

-2- J-A11028-19

notified ServiceMaster that there was a “serious asbestos issue” for which

“CenturyLink was claiming approximately $164,000.00 in offset claims in

relation to the work.” Id. at ¶ 145. The next day, counsel for ServiceMaster

responded to those claims and sent an acceptance of service form with a copy

of the writ of summons, asking CenturyLink’s counsel to accept service on

behalf of CenturyLink as previously promised. According to ServiceMaster, on

September 16, 2015, CenturyLink’s counsel sent another “false and fraudulent

demand for immediate payment by ServiceMaster to CenturyLink of

$164,000.00.” Id. at 151.

On October 19, 2015, CenturyLink filed preliminary objections to

ServiceMaster’s complaint, which included a preliminary objection based on

lack of subject matter jurisdiction. CenturyLink asserted that the arbitration

clause in the contract required the parties to arbitrate this matter. According

to CenturyLink,

[t]he dispute at issue … [was] ServiceMaster’s breach of contract, including advising CenturyLink that there was no asbestos present in the area where the mold abatement work was to be completed and performing unlicensed demolition of asbestos-containing materials, which subsequently required CenturyLink to spend significant sums investigating and completing clean-up and incur costs for lost use of lease space and obtaining alternate facilities.

Preliminary Objections, 10/19/2015, ¶ 16. CenturyLink asserted that

“because the dispute at issue is ServiceMaster’s breach of contract, this matter

must be arbitrated and the [trial court is] without subject matter jurisdiction.”

Id. at ¶ 18.

-3- J-A11028-19

ServiceMaster did not file a written response to the preliminary

objections, but instead requested argument. After argument, on August 15,

2016, the trial court overruled CenturyLink’s preliminary objection based on

lack of subject matter jurisdiction, concluding that the arbitration clause

excepted claims involving non-payment of ServiceMaster’s invoices and,

because ServiceMaster alleged non-payment of invoices, ServiceMaster

properly filed suit in the trial court. On September 15, 2016, CenturyLink

timely appealed to this Court.

In an unpublished memorandum filed on September 5, 2017, a prior

panel of this Court reversed the trial court order overruling CenturyLink’s

preliminary objections and remanded the case for further proceedings. Our

prior panel recognized that the parties did not dispute the validity of the

arbitration clause and, thus, the proper inquiry was whether the alleged

dispute fell within the scope of that clause.2 After citing general contract law

principles, the prior panel noted:

In its opinion, the trial court concluded that the term “except for nonpayment of invoices for ServiceMaster's work” (“except clause”) “clear[ly] state[d] that arbitration was expressly limited to disputes related to quality of contracted services and excluded contract balance claims.” In re: Opinion Pursuant to Pa.R.A.P. 1925(a), 11/14/16, at 3. The court therefore found that “the claims of the [c]omplaint are outside the arbitration clause” and overruled CenturyLink's preliminary objection. Id. The trial court's ____________________________________________

2 As we shall explain below, whether to enforce an arbitration agreement clause involves a two-part inquiry. First, the trial court must determine if a valid arbitration agreement exists. Second, if there is a valid agreement, there must be a determination as to whether the dispute involved is within the scope of the arbitration provision. See infra at 9.

-4- J-A11028-19

ruling is premised on an implicit conclusion that the except clause is unambiguous. We disagree.

The except clause is reasonably susceptible to two constructions. The first construction, which would render the arbitration clause narrow and favor ServiceMaster, would exclude from binding arbitration any issue that involves, either directly or indirectly, the non-payment of invoices. The second construction of the except clause, which would render the arbitration clause broad and favor CenturyLink, would require binding arbitration for all issues except those that involve only the non-payment of invoices. The parties have not offered, nor have we found, any case law that interprets the language contained in this particular clause.

Based on the language of the except clause, and the lack of case law interpreting similar language, we conclude that the except clause is subject to more than one reasonable interpretation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Theodore C. Wills Co. v. School District of Boyertown Area
837 A.2d 1186 (Superior Court of Pennsylvania, 2003)
Trizechahn Gateway LLC v. Titus
976 A.2d 474 (Supreme Court of Pennsylvania, 2009)
Saltzman v. Thomas Jefferson University Hospitals, Inc.
166 A.3d 465 (Superior Court of Pennsylvania, 2017)
Callan v. Oxford Land Development, Inc.
858 A.2d 1229 (Superior Court of Pennsylvania, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
M2J2S, LLC v. United Telephone Company of PA, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m2j2s-llc-v-united-telephone-company-of-pa-pasuperct-2019.