M & W DEVELOPMENT, INC. v. El Paso Water Co.

634 P.2d 166, 6 Kan. App. 2d 735, 1981 Kan. App. LEXIS 347
CourtCourt of Appeals of Kansas
DecidedOctober 2, 1981
Docket52,333
StatusPublished
Cited by7 cases

This text of 634 P.2d 166 (M & W DEVELOPMENT, INC. v. El Paso Water Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M & W DEVELOPMENT, INC. v. El Paso Water Co., 634 P.2d 166, 6 Kan. App. 2d 735, 1981 Kan. App. LEXIS 347 (kanctapp 1981).

Opinion

Abbott, J.:

The defendant, El Paso Water Company, Inc., (El Paso) áppeals from a judgment against it for $151,826.07, contending the maximum judgment should be $19,707.89. The case involves the due date and manner in which the plaintiff, M & W Development, Inc. (M & W), may recover funds it advanced to El Paso to finance the extension of water lines in the city of Derby, Kansas. The total amount owing M & W is not in dispute.

*736 M & W is a real estate developer active in the Derby, Kansas, area. El Paso is a privately owned water utility serving the City of Derby under a franchise granted by Derby. In order to finance the extension of water service to new developments within the franchised area, El Paso has for a number of years executed standard form contracts with the various real estate developers whereby a developer would advance funds to cover the costs of extending El Paso’s distribution system into the area being developed. The contracts provided for repayment of the advancements pursuant to a formula that was based on whether the addition was developed in units or in its entirety, and on whether a certain percentage of connections had been completed in the unit. If the developer chose to develop the addition in its entirety, the money advanced by the developer would “mature for repayment” when 90 percent of the lots were occupied by water customers of El Paso. If the developer chose to develop the addition by units, the money advanced would mature for repayment at the rate of one-third when 40 percent of the total lots were developed and occupied by water customers; an additional one-third when 75 percent of the lots were so developed and occupied; and the remaining one-third when 90 percent of the lots were so developed and occupied.

Upon the occurrence of the particular event triggering the repayment obligation, two methods of repayment of the advances are provided for in the contract. The provision that applies when the obligation to repay the advancement matures is the subject of this appeal and states:

“(a) First Party [El Paso] will make, execute and deliver to Second Party [M & W] its promissory note or notes in amount or amounts equal to the sum of sums so advanced to First Party, bearing interest from the date of execution and delivery at the rate of 5% per annum, the principal and interest thereof becoming due and payable on a twenty-year amortized schedule with the first installment of interest and principal becoming due and payable sixty (60) days after the date thereof, and with semi-annual payments thereafter; or
“(b) If First Party has funds from, or shall thereafter receive funds from, the issuance of any series of its first mortgage bonds to any mortgagee, it will then repay to Second Party the sum or sums advanced under and pursuant to the terms of this contract, and from time to time qualified for re-payment as in this Paragraph 4 provided, so long as funds from such source or sources remain available.”

*737 El Paso has used some version of the above clause in its contracts with developers since 1955; and prior to 1975, it had paid the advancements in full as they matured.

The trial court held that El Paso’s failure to issue notes as provided for in that part of the contract set forth above constituted breach of contract; and, having failed to issue the notes, El Paso is not entitled to rely upon that provision of the contract pertaining to matured but unpaid advancements. The trial judge found that $112,279 had matured for repayment prior to commencement of the action. The attorneys agreed that additional amounts had matured prior to judgment and that the newly matured advancements should be included in the judgment; judgment was entered for M & W in the amount of $151,826.07. The trial judge also found that if he were in error concerning El Paso’s right to issue notes for the outstanding balance, the sum due on the notes as of December 31, 1979, would be $19,707.85 without interest on past due payments.

El Paso contends that it did not breach its contracts with M & W; that its conduct did not constitute a material breach of its contracts with M & W; that any damages awarded in excess of $19,707.89 amounts to rewriting the contract between the parties and are excessive; and that the trial court erred in failing to find that M & W did not mitigate any of the damages that it might have sustained by reason of El Paso’s conduct. M & W cross-appeals, arguing that the contracts are unconscionable, and therefore null and void; that its forbearance to exercise its right of repayment was consideration for El Paso’s alleged agreement to pay cash plus a higher rate of interest; that El Paso waived its right to issue 20-year bonds in lieu of paying cash; and that it is entitled to punitive damages.

The record contains substantial competent evidence to support the trial judge’s finding that El Paso breached the contract by not issuing notes to M & W. We cannot say, however, that a “material breach” justifying rescission of the contract has occurred, as was concluded by the trial judge. What justifies rescission of a contract was considered in In re Estate of Johnson, 202 Kan. 684, 691-92, 452 P.2d 286 (1969), wherein the Supreme Court commented:

“[T]he right to rescind a contract is extreme and does not necessarily arise from every breach. To warrant rescission, the breach must be material and the failure to *738 perform so substantial as to defeat the object of the parties in making the agreement. A breach which goes to only a part of the consideration, which is incidental and subordinate to the main purpose of a contract, does not warrant a rescission. (Baron v. Lyman, 136 Kan. 842, 18 P.2d 137; 17 Am. Jur. 2d, Contracts § 504; 17A C.J.S., Contracts § 422 [1]; Corbin on Contracts § 1104.)” (Emphasis supplied.)

Accord, Whiteley v. O’Dell, 219 Kan. 314, 548 P.2d 798 (1976).

Our Supreme Court has also held that failure of consideration, unless so great that it amounts to fraud, is not grounds for rescission of a contract; neither is the mere failure of a party to comply with terms of the contract. Kohn v. Babb, 204 Kan. 245, 250-51, 461 P.2d 775 (1969). Generally, upon rescission of contract the parties must be placed in substantially the same condition as they were in when the contract was executed. E.g., Whiteley v. O’Dell, 219 Kan. at 319. That obviously cannot be done in this case.

Except for payment by El Paso, the contract had been fully complied with. M & W advanced the money to El Paso to extend its water lines to the land being developed, and El Paso extended its lines and provided water service. The developed area became occupied and the only provision in the contract left to be performed was the repayment of the matured advancements to M & W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Hiawatha v. Rural Water Dist. No. 2
Court of Appeals of Kansas, 2015
Smith v. Stephens
940 P.2d 68 (Court of Appeals of Kansas, 1997)
Jetz Service Co. v. Salina Properties
865 P.2d 1051 (Court of Appeals of Kansas, 1993)
Federal Land Bank of Wichita v. Krug
856 P.2d 111 (Supreme Court of Kansas, 1993)
State v. Bullock
849 P.2d 137 (Court of Appeals of Kansas, 1993)
Tongish v. Thomas
840 P.2d 471 (Supreme Court of Kansas, 1992)
Tongish v. Thomas
829 P.2d 916 (Court of Appeals of Kansas, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
634 P.2d 166, 6 Kan. App. 2d 735, 1981 Kan. App. LEXIS 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-w-development-inc-v-el-paso-water-co-kanctapp-1981.