M. J. Kelly Co. v. Haendiges

397 N.E.2d 416, 60 Ohio App. 2d 318, 14 Ohio Op. 3d 284, 1978 Ohio App. LEXIS 7640
CourtOhio Court of Appeals
DecidedJuly 6, 1978
Docket38117
StatusPublished
Cited by3 cases

This text of 397 N.E.2d 416 (M. J. Kelly Co. v. Haendiges) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. J. Kelly Co. v. Haendiges, 397 N.E.2d 416, 60 Ohio App. 2d 318, 14 Ohio Op. 3d 284, 1978 Ohio App. LEXIS 7640 (Ohio Ct. App. 1978).

Opinion

Corrigan, C. J.

This suit was originally brought by M. J. Kelly Co. against numerous defendants. The instant appeal involves only the cross claim of defendant-appellee, Shaker Mechanical Corp., against defendant-appellant, Roger M. Haendiges. All other parties and claims were disposed of by the trial court; the sole issue before this Court is the validity of appellee’s mechanic’s lien against appellant’s property.

*319 The facts relevant to this appeal are as follows. Appellant owns property upon which the Calvon Corporation contracted as general contractor to build a supermarket. Appellee subcontracted with Calvon to install a heating and air conditioning system in the building. The contract price was $26,900. Appellee billed Calvon for work completed at several stages of the construction; the last 'bill was termed “Billing in full, final billing,” and dated May 25, 1974.

There was conflicting testimony regarding when the contract was completed. Mr. Macsay, vice president of appellee, testified that the company never billed for work unless it had been completed. Under this reasoning, the contract would have been completed on or before May 25, 1974, the date of the invoice stating “final billing.” However, Mr. Macsay also stated that the job “wasn’t final” until June 6,1974, the date that the air conditioning was tested, and that the final date of work on the contract was May 30, 1974.

Other conflicting testimony consisted of appellant’s assertion that work was completed some time before June 1, 1974, when the tenant (“Allied”) took possession of the premises:

“Q And on June 1,1974, was there any more work to be done upon the premises?
“A No.
“Q Would you have permitted Allied to move into the premises had work been required to have been done?
“A It would have been impossible for them to move in and risk the security of losing some of their equipment if there was any work to be done on the property.”

However, a letter from Allied to appellant, dated June 10,1974, inferred that work may not have been completed as of June 1:

“Please be advised that we have accepted possession of the leased premises effective June 1, 1974, subject only to whatever defects or omissions remain outstandinq on said date.”

Of the total $26,900 billed by appellee to Calvon, Calvon paid appellee $10,000 leaving a balance still owing of $16,800. On July 31, 1974, appellee filed an Affidavit to Obtain A Mechanic’s Lien with the Cuyahoga County Recorder. Appellant was served with a copy of the affidavit on August 17, *320 1974. Appellee also served an affidavit of subcontractor on both appellant and Calvon Corporation on October 14,1974. Neither of these affidavits was signed.

The trial court found that the appellee had a valid mechanic’s lien upon appellant’s property. Appellant filed a surety bond pursuant to R. C. 1311.11, and the Court, discharged the mechanic’s lien.

Appellant assigns three errors:

I. The trial court erred in determining that the mechanic’s lien of the defendant appellee, Shaker Mechanical Corp., was a valid and subsisting lien upon the appellant’s real property.

II. The trial court erred in determining that the appellee’s affidavit to obtain a mechanic’s lien was filed within the time prescribed by law.

III. The-judgment of the trial court was clearly against and unsupported by the manifest weight of the evidence.

I.

The first assignment of error raises the question of whether a subcontractor is required to file the affidavit of subcontractor referred to in R. C. 1311.04 with either the general contractor or the property owner as a prerequisite to obtaining a mechanic’s lien. The question includes the interpretation of both R. C. 1311.04 and of several conflicting cases decided under that statute.

R. C. 1311.04 is a complex and often confusing 1 provision of the mechanic’s lien law. It must be complied with before a contractor, subcontractor, materialman or laborer can sue or obtain a lien for money due him. While the entire statute is far too lengthy to quote, the portions relevant to the instant case state:

“Whenever any payment of money becomes due from the owner* **or whenever the original contractor desires to draw any money from the owner, *** such contractor shall make out and give to the owner* * *a statement under oath, showing***the name and address of every subcontractor in his employ***.
*321 “The original contractor shall also deliver to such owner* **similar sworn statements from each subcontractor***.
“Until the statements are made and furnished in the manner and form provided for in this section***the subcontractor has no right of action or lien against the owner***and any payments made by the owner***before such statements are made***are illegal.***”

The gravamen of appellant’s first assignment of error is his contention that this section prohibits a subcontractor from obtaining a mechanic’s lien until he has furnished the general contractor with the affidavit which it describes.

Several Ohio cases have addressed this question. In Williamson Heater Co. v. Radich (1934), 128 Ohio St. 124, a subcontractor filed an action to foreclose a mechanic’s lien. The subcontractor had served the affidavit of subcontractor required by R. C. 1311.04 (then G. C. 8312) upon the general contractor 2 but not with the property owner. The general contractor did not supply the owner with this statement. The Court held that, while the general contractor was under a clear duty to furnish the owner with both his own affidavit and the affidavits of his subcontractors, the subcontractors owed the owner no such duty. The Court reasoned:

“What then is the significance of the words, ‘such statements’ to be furnished by the subcontractor? Thus far the only ‘statements’ mentioned in the statute in connection with the subcontractor are those to be furnished by him to the contractor. How then can it logically be urged that this reference is to statements to be furnished by the subcontractor to the owner? Not until the last sentence in the whole statute is anything said about a statement to be furnished by the subcontractor directly to the owner.” 128 Ohio St. at 127.

The Court concluded its analysis by holding that the only time the subcontractor is under a duty to furnish the owner with the affidavit is when he receives such a demand from the owner. Id. Thus, absent a demand from the owner, a subcontractor who furnishes a general contractor with an R. C. *322 1311.04 affidavit is under no duty to do more and is not prohibited by that section from obtaining a mechanic’s lien.

The converse to the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
397 N.E.2d 416, 60 Ohio App. 2d 318, 14 Ohio Op. 3d 284, 1978 Ohio App. LEXIS 7640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-j-kelly-co-v-haendiges-ohioctapp-1978.