M & I Marshall & Ilsley Bank v. Pump

276 N.W.2d 295, 88 Wis. 2d 323, 1979 Wisc. LEXIS 1927
CourtWisconsin Supreme Court
DecidedMarch 27, 1979
Docket76-536
StatusPublished
Cited by6 cases

This text of 276 N.W.2d 295 (M & I Marshall & Ilsley Bank v. Pump) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M & I Marshall & Ilsley Bank v. Pump, 276 N.W.2d 295, 88 Wis. 2d 323, 1979 Wisc. LEXIS 1927 (Wis. 1979).

Opinion

CONNOR T. HANSEN, J.

The third party action is based upon long-term financing commitments the appellants obtained from Crown Life Insurance Company (hereinafter Crown) for a 92-unit, four building apartment project to be constructed by the appellant at Menasha, Wisconsin. Construction financing for the project was provided by Richter-Schroeder Company (hereinafter Richter), a mortgage banking firm and a loan correspondent of Crown. Richter was acquired by M & I Marshall & Ilsley Bank (hereinafter Bank) while the construction was in progress.

In two financing commitments dated January 21 and 22, 1974, Crown agreed to lend appellants $1.16 million secured by two first mortgages for $440,000 and $720,000. These commitments provided that they would be null and void if the transaction was not completed within 253 days, unless extended in writing, at Crown’s option. The commitments required, among other things, as conditions precedent, a title insurance policy without exceptions, payment of outstanding taxes and completion *326 in strict compliance with the plans and specifications, including landscaping.

The appellants were unable to complete the project by the time the commitments expired in October, 1974, and requested an extension. At the request of the appellants, Crown- ultimately agreed to four successive extensions of the commitments, first to December 15, 1974, then to April 15, 1975, then to July 15, 1975, and finally to a one-month extension to August 15, 1975.

During the period of the extensions, the appellants needed funds in addition to the original construction financing for the project. As a result, in June, 1975, the Bank agreed to advance appellants an additional $100,-000, secured by a $250,000 second mortgage. This mortgage also covered a $116,000 rental holdback.

Appellants and Richter began preparations for closing in August, 1975, even though work continued on the project. The architect’s certificate of completion was signed August 7th, but the project engineer indicated that this referred to the building itself and not to “odds and ends,” such as hardware, carpeting, appliances or cleanup. He further indicated that some of the incomplete items, landscaping among them, were not included in the building plans. He admitted that building code violations existed the day he signed the completion certificate.

The closing did not occur because a title policy had not been obtained and the project was not completed. An inspection of the project on August 13th by Tom Richter showed that although the buildings were structurally finished the following work remained to be done:

1. Installation of appliances, including 28 refrigerators, three stoves and two dishwasher front panels;

2. installation of carpet padding in 35 apartments, and carpeting in 53 apartments;

3. installation of numerous electric fixtures, including those in 31 bathrooms and 21 hallways;

*327 4. installation of numerous doors and door hardware;

5. removal of construction materials from underground garages and installation of garage doors and electric door openers;

6. fifty percent of the exterior painting and installation of some roof flashing;

7. the landscaping; and

8. correction of a number of building code violations, including the addition of fire-resistant materials and doors to the furnace rooms and on the basement stairs in each of the four buildings and the installation of a new ventilating system in the underground parking area in each building.

The building had 20 tenants on August 15th and approximately five more were due to move in.

A title insurance policy was not obtained because construction lien claims had been filed and potential unfiled claims existed. The appellants were also delinquent in real estate taxes.

The first two construction loans had been completely disbursed by June 15, 1975. Advances and draw requests being processed on August 15, 1975, depleted the $100,000 loan from the Bank. Crown’s last extension of the commitments expired August 15, 1975. Richter attempted to get a further extension from Crown. However, on September 4, 1975, Crown advised Richter that the commitments would not be reinstated. The Bank then brought this foreclosure action in which the appellants counterclaimed against Crown seeking specific performance of the long-term financing commitments.

In an attempt to show that the commitments’ terms could be met the appellants presented evidence at trial that the title company had agreed to provide a policy insuring that Crown’s mortgages would have priority status over the filed construction liens if those liens were bonded. A bonding company representative testified *328 that they agreed to bond the liens but were never given a list of filed liens. However, the testimony of the title company representative, Alan Dolenshek, was contradictory as to whether a policy could be issued which both insured over the bonded filed liens and eliminated the standard unfiled claim exception. Dolenshek did indicate that the liens could have been bonded for 125 to 150 percent of the amount already filed plus 125 percent of the undetermined amount of the unfiled claims. He admitted he didn’t know if such a policy would be acceptable to Crown, but said Crown did require a waiver of the unfiled lien exception. A. John Richter testified that generally investors would not accept a title insurance policy with an exception for unfiled liens. There was no evidence that appellants could, in fact, provide such a bond or pay the liens.

The appellants also attempted to show that they understood Crown was extending the commitments on a day-to-day basis after August 15th. A. John Richter actually testified that any mention of short-term or day-to-day extensions referred to the time period prior to August 15th. He said that after August 15th there was no formal agreement or extension, only an informal understanding that if the project w9,s completed within a few days that Crown would close. The project was not so completed. Richter indicated that an escrow of $25,000 to complete the carpeting after August 15th would be acceptable, but that they could not consider adding the remaining unfinished items to that escrow. No such escrow was tendered or proof offered that appellants were able to provide an escrow.

Goldman, one of the appellants, testified that they had several lines of credit on which to draw to pay the liens as. soon as disputes regarding their amounts were settled. He said that according to their estimates on September 4th approximately $96,000 was needed to pay off the outstanding liens and install the carpeting. Pump *329 testified that he calculated that they would need about $172,000 to close, including the $116,000 rental hold-back, $8,400 for taxes and $48,000 to be escrowed to cover unfinished items. He said he thought they had $165,000 remaining on the $250,000 second mortgage and the $11,600 standby fee due from Crown at closing. On cross-examination he admitted the second mortgage balance was reduced after August 15th by draw requests.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & L Properties New Pinery, LLC v. Todd W. Bennett
Court of Appeals of Wisconsin, 2024
Manpower, Inc. v. Mason
405 F. Supp. 2d 959 (E.D. Wisconsin, 2005)
Fehring v. Republic Insurance
347 N.W.2d 595 (Wisconsin Supreme Court, 1984)
Davis v. Allstate Insurance
303 N.W.2d 596 (Wisconsin Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
276 N.W.2d 295, 88 Wis. 2d 323, 1979 Wisc. LEXIS 1927, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-i-marshall-ilsley-bank-v-pump-wis-1979.