M & D Properties, Inc. v. Bd. of Commissioners of the Twp. of Upper St. Clair

CourtCommonwealth Court of Pennsylvania
DecidedMarch 15, 2024
Docket578 C.D. 2021
StatusUnpublished

This text of M & D Properties, Inc. v. Bd. of Commissioners of the Twp. of Upper St. Clair (M & D Properties, Inc. v. Bd. of Commissioners of the Twp. of Upper St. Clair) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M & D Properties, Inc. v. Bd. of Commissioners of the Twp. of Upper St. Clair, (Pa. Ct. App. 2024).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

M & D Properties, Inc., : Appellant : : v. : No. 578 C.D. 2021 : Argued: February 6, 2024 Board of Commissioners of the : Township of Upper St. Clair :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE CHRISTINE FIZZANO CANNON, Judge HONORABLE MARY HANNAH LEAVITT, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY PRESIDENT JUDGE COHN JUBELIRER FILED: March 15, 2024

M & D Properties, Inc. (M & D) appeals from an Order of the Court of Common Pleas of Allegheny County (common pleas) filed April 29, 2021, which affirmed a decision by the Board of Commissioners (Board) of the Township of Upper St. Clair (Township) denying M & D’s Application for Preliminary and Final Subdivision Approval for a two-lot plan. Contending unique topography, such as wetlands and steep slopes, rendered it economically not feasible to strictly comply with the Township’s Subdivision and Land Development Ordinance (SALDO), M & D sought consolidation of five existing vacant lots and modifications from certain SALDO provisions, which the Board denied, concluding M & D had not demonstrated undue hardship. Without taking additional evidence, common pleas affirmed. On appeal, M & D argues it could support its request for modifications by showing either undue hardship or unreasonableness, which M & D asserts it did through uncontroverted evidence, and it was error or an abuse of discretion to deny the modifications based on what M & D asserts were general, speculative concerns of neighbors of alleged adverse impacts of development.1 Upon review, while we agree that undue hardship or unreasonableness may be a basis to seek modification of a SALDO provision, here, M & D only pursued modification as an undue hardship and, thus, cannot now assert for the first time on appeal that the Board erred2 in failing to consider whether strict compliance with the SALDO was unreasonable. Even if the issue was not waived, we conclude there was no error as M & D’s undue hardship and unreasonableness arguments are both premised on it not being economically feasible to develop the subject property (Property) except as proposed, evidence of which the Board rejected. Because the Board did not credit M & D’s evidence that it was cost prohibitive to develop the Property in compliance with the SALDO, particularly where there was no evidence of the value of the Property, M & D did not meet its burden of showing that the Board erred by denying the modifications. Accordingly, we affirm.

I. BACKGROUND M & D acquired the Property in the Township in 1989 and has previously sought to develop it but no development has occurred and the Property remains vacant. (Reproduced Record (R.R.) at 49a.) In 2005, M & D filed an application

1 We have combined M & D’s arguments for ease of discussion. 2 M & D asserts in its brief that common pleas erred or abused its discretion by not considering unreasonableness. (M & D’s Brief (Br.) at 14.) However, as common pleas did not take additional evidence, we review the governing body’s decision, here the Board’s, for errors of law or abuses of discretion. Miravich v. Township of Exeter, Berks County, 54 A.3d 106, 110 n.4 (Pa. Cmwlth. 2012).

2 with the Board seeking approval of a six-lot plan, but the Board only approved a four-lot plan, which M & D did not pursue, citing costs associated with the Property’s topography. (Id. at 80a-81a.) The Property is described as undeveloped with a stream bisecting it, has wetlands that would need to be mitigated, and is situated on a steep hillside with a 35-degree grade change. (Id. at 46a.) In May 2020, M & D filed an application seeking to consolidate the vacant lots with an adjacent lot it recently purchased, on which a single-family residence is situated. From seven lots, M & D proposed to create two new lots: one with the existing residence (Lot 1), and one approximately 10 acres in size on which a new single-family residence would be constructed (Lot 2). M & D proposed Lot 2 would be what is known as a flag lot, with a long driveway accessing Locust Lane, as depicted on the plan below.

(R.R. at 180a.)

3 M & D maintained accessing Lot 2 via Quigg Drive was not economically feasible due to the topographic conditions. M & D also sought modification of certain provisions of the Township’s SALDO, namely:

• Section 114.41.2 Building lines. The front building line and perimeter setback line as required in the zoning code shall be considered a minimum and shall be adhered to unless variances are granted by the Zoning Hearing Board or modifications by the Board. . . .

• Section 114.41.3. Side lot lines. Side lot lines shall be substantially at right angles or radial to streets. . . .

• Section 114.41.6. Double frontage lots.[3] Double frontage lots shall be avoided except where essential to provide separation of residential development from traffic arteries or to overcome specific disadvantages of topography and orientation.

(UPPER ST. CLAIR SUBDIVISION & LAND DEVELOPMENT CODE (Code), §§ 114.41.2, 114.41.3, 114.41.6 (1991), R.R. at 245a-46a (unnecessary capitalization removed).)4 Upon review, the Township Planning Commission recommended the Board deny the application. A public hearing was scheduled before the Board. At the July 6, 2020 hearing, David Lucci, a registered landscape architect with Victor-Wetzel Associates (Expert), and David Steinbach, a principal of M & D (Principal),

3 A double frontage lot is defined as “a lot having lot lines which extend along two non- intersecting streets.” (UPPER ST. CLAIR SUBDIVISION & LAND DEVELOPMENT CODE (Code) § 114.10.27 (1991).) Excerpts of the Code are found in the Reproduced Record, but the entire Code is available in the original record at Item number 8. 4 M & D originally sought modifications related to the side lot line and double frontage lots, but at the end of the first public hearing, a question was raised as to whether the third modification was required. Because the SALDO required modification requests to be made in writing, the plan was tabled to allow M & D to supplement its request, which it did. (R.R. at 64a- 67a.)

4 testified.5 Expert described the topographical conditions of the Property and what would be required to access Lot 2 via Quigg Drive. Expert testified that 15,000 cubic yards of fill, which is the equivalent of 500 truckloads, and 225 lineal feet of culvert would be needed, along with joint permitting from the Army Corps of Engineers (Army Corps) and Department of Environmental Protection (DEP), sewage pipes would need to be enclosed in concrete, and approximately one-third of an acre of wetlands would need mitigated, at a combined cost of $330,000.6 (R.R. at 46a-48a.) Principal described the efforts M & D made since purchasing the Property in 1989 to develop the Property and that costs prevented it from developing the four lots previously approved. (Id. at 49a-50a.) Principal explained M & D purchased Lot 1 when the owner was selling specifically to provide a driveway to access Lot 2. (Id. at 50a-51a.) At a second public hearing on the plan, held on August 3, 2020, Expert and Principal again testified, and several members of the public also commented on the plan.7 Expert testified his firm did the cost estimate for development of the Property in 2004-05, as well as at least three other times, and advised against developing the Property each time due to costs. (R.R. at 80a-81a.) Expert testified again as to the $330,000 estimate to get access to the site via Quigg Drive and the components of that cost. (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valenti v. Washington Township
737 A.2d 346 (Commonwealth Court of Pennsylvania, 1999)
Ruf v. Buckingham Township
765 A.2d 1166 (Commonwealth Court of Pennsylvania, 2001)
Telvil Construction Corp. v. Zoning Hearing Board of East Pikeland Township
896 A.2d 651 (Commonwealth Court of Pennsylvania, 2006)
Heritage Building Group, Inc. v. Bedminster Township Board of Supervisors
742 A.2d 708 (Commonwealth Court of Pennsylvania, 1999)
Melwood Corp. v. Zoning Board of Adjustment
528 A.2d 668 (Commonwealth Court of Pennsylvania, 1987)
Kassouf v. Township of Scott
883 A.2d 463 (Supreme Court of Pennsylvania, 2005)
Joseph v. North Whitehall Township Board of Supervisors
16 A.3d 1209 (Commonwealth Court of Pennsylvania, 2011)
Miravich v. Township of Exeter
54 A.3d 106 (Commonwealth Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
M & D Properties, Inc. v. Bd. of Commissioners of the Twp. of Upper St. Clair, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-d-properties-inc-v-bd-of-commissioners-of-the-twp-of-upper-st-pacommwct-2024.