M. A. Long Co. v. Keystone Portland Cement Co.

153 A. 429, 302 Pa. 308, 1931 Pa. LEXIS 659
CourtSupreme Court of Pennsylvania
DecidedDecember 2, 1930
DocketAppeal, 9
StatusPublished
Cited by13 cases

This text of 153 A. 429 (M. A. Long Co. v. Keystone Portland Cement Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M. A. Long Co. v. Keystone Portland Cement Co., 153 A. 429, 302 Pa. 308, 1931 Pa. LEXIS 659 (Pa. 1930).

Opinion

Opinion by

Mr. Justice Simpson,

Plaintiff filed a mechanic’s lien against defendant’s properties, and caused a writ of scire facias to be issued upon it. Defendant’s affidavit of defense was held in *311 sufficient, and judgment entered for $155,098.37. From it the present appeal was taken.

Before the case was reached for argument in this court, appellant presented to us a petition praying that the record be returned to the lower court, in order that an application might be made therein “to open the judgment and for leave to file a supplemental or amended affidavit of defense.” A rule to show cause was granted, plaintiff filed an answer, and we made the rule absolute.

On the return of the record to the lower court, defendant presented a petition of the character referred to, and attached thereto a copy of the proposed supplemental affidavit of defense. A rule to show cause was granted, plaintiff filed an answer, and the petition was dismissed because it had not been presented within the term of the court below at which the judgment for want of a sufficient affidavit of defense had been entered. Surely it would have been reasonable to infer we knew that particular term had expired, when we remitted the record, since, at that time, more than three months had passed after the entry of the judgment; or that, if we were in doubt on the subject, we could readily have inquired of court or counsel, and not taken the roundabout method of remitting the record, etc., in order to ascertain this simple fact. Perhaps, also, it would not have been difficult to conclude that we believed the same-term rule had no application to the case, as was indeed the fact, since we had recently so decided. In Kantor v. Herd, 276 Pa. 519, 524, which, like the present, was a mechanic’s lien case in which it was sought to open a judgment by default entered at a prior term, we said, “we see no reason, — in the case of a statutory rather than a common law proceeding, if due diligence appears, —why appropriate action should not be taken though the term had expired.” Appellee seeks to distinguish that case from the present one by the fact that the affidavit of defense there filed was in effect only an affidavit raising preliminary questions of law. There is *312 such a distinction, but it was not the basis of the decision, which is specifically stated to be because that was “a statutory rather than a common law proceeding,” just as it is here.

To clarify the situation for the future, we now definitely say that in statutory proceedings the rule should not be applied, in the absence of a legislative requirement, but the question should always be, as it was stated to be in that case, whether the defendant exercised “due diligence” in seeking relief. ■ The rule itself is a survival of a time when the judgment roll was finally closed at the end of the term, and all things appertaining to it were supposed to be closed with it; hence there appeared then to be some excuse for the existence of the rule. Now, however, no such reason exists. In several of our recent cases it seemed clear that the rule was invoked by a litigant who had purposely delayed taking summary judgment until the last day of the term; and it has appeared to the writer, and to at least some of his colleagues, that the rule could be wisely supplanted by one fixing a definite period, after the entry of the judgment, within which time a rule to open it must be sought, if at all; or by one applying to each case the principles involved when the doctrine of laches is invoked. For the reason'already stated, however, it is not necessary to consider the matter further at the present time.

Returning to the questions now before us, we are admonished, by the constitutional requirement that “justice shall be administered without......delay,” not to send the case back for an opinion on the merits, as would ordinarily be done, but to dispose of it finally, without the aid we were entitled to have from the judges of the court below. Since appellant claims not only that the judgment should have been opened when the record was returned, but also that there was error in entering it in the first instance, we shall consider these questions in their chronological order.

*313 In the original affidavit, defendant does not deny that plaintiff duly performed the work contracted for, and there is no challenge regarding the manner in which it was done, nor as to the character, quality or quantity of the materials used. Defendant does not question the fact that, for so much of the work as gives rise to the present controversy, the contract simply provided that plaintiff was to be paid therefor at “the unit prices charged by [it] in the construction of the original plant [of defendant], of which [plaintiff] was also the principal contractor,” and that it was so charged. Apparently its contention was, and this was its only objection to the claim, that in the building of the original plant, when bids were submitted by plaintiff for the concrete form construction, they were specified to be at 25c per square foot, and that figure was inserted in a preliminary agreement covering part of the work, which agreement stated, however, that it was to be followed by a formal agreement including all of it; that in the latter, when it was executed, the price was stated to be 50c per square foot, and that, when the work was done and paid for, it was at the latter figure. It was urged, however, that the change was wrongfully made, a fact which defendant said was unknown to it at the time the additional plant, the subject of this lien, was contracted for, and hence the provision in the present contract that “the unit prices charged by [plaintiff] in the construction of the original plant” should apply to the new work, would be legally construed to mean only the unit prices as they should have been, and not as they actually were charged in that construction.

The lower court correctly determined that if, in the original affidavit of defense, fraud was intended to be charged, the language used was inadequate for the purpose, under the principle which requires certainty and clearness in that kind of an averment. It was expressly admitted by defendant that, for several years, payments had been regularly made under the original contract, *314 at the rate of 50c per square foot for concrete form construction, exactly as specified therein; but it was alleged they were made before the overcharge was discovered by defendant. It is averred that the original bid was for 25c per square foot, but that Franks, who was defendant’s vice-president and general manager, afterwards “went to the office of the claimant in the City of Baltimore, Maryland, for the purpose of going further into the matter of awarding the contract for said construction work,” and that, when he returned, “the bid of the claimant had been raised......to 50c per square foot for form work”; that “the said increase......was made without any reason, justification or excuse and created a disadvantageous contract upon the part of the defendant company”; that the change “was unauthorized, illegal and prejudicial to the rights of the defendant company and its stockholders and was the means by which a fraud was perpetrated upon” them; and that the payment and acceptance of the excess price was also a fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Better Living, Inc. v. Filosa
184 A.2d 314 (Superior Court of Pennsylvania, 1962)
ROSE v. Cohen
165 A.2d 264 (Superior Court of Pennsylvania, 1960)
Kuntz v. Lanbar Hotel Co., Inc.
110 A.2d 249 (Supreme Court of Pennsylvania, 1955)
Vallish v. Rapoport
70 A.2d 616 (Supreme Court of Pennsylvania, 1950)
Shaffer v. Rose
61 Pa. D. & C. 655 (Bedford County Court of Common Pleas, 1948)
Pytle v. Zyvith
52 Pa. D. & C. 44 (Westmoreland County Court of Common Pleas, 1944)
Curran v. James Regulator Co.
36 A.2d 187 (Superior Court of Pennsylvania, 1943)
Wuestner v. Manning
46 Pa. D. & C. 602 (Philadelphia County Court of Common Pleas, 1943)
McCune v. Cramer
40 Pa. D. & C. 623 (Cumberland County Court of Common Pleas, 1941)
Horning v. David
8 A.2d 729 (Superior Court of Pennsylvania, 1939)
Com. Ex Rel. Paige v. Smith, Warden
198 A. 812 (Superior Court of Pennsylvania, 1938)
Shallcross v. Quaker City Building & Loan Ass'n
22 Pa. D. & C. 315 (Philadelphia County Court of Common Pleas, 1935)
Malis v. Homer Building & Loan Ass'n
171 A. 570 (Supreme Court of Pennsylvania, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
153 A. 429, 302 Pa. 308, 1931 Pa. LEXIS 659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/m-a-long-co-v-keystone-portland-cement-co-pa-1930.