STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
11-1537
LYNTON O. HESTER, IV
VERSUS
BURNS BUILDERS, ET AL.
**********
APPEAL FROM THE NINTH JUDICIAL DISTRICT COURT PARISH OF RAPIDES, NO. 230,061 HONORABLE DONALD T. JOHNSON, DISTRICT JUDGE
PHYLLIS M. KEATY JUDGE
Court composed of Sylvia R. Cooks, Marc T. Amy, Billy Howard Ezell, J. David Painter, and Phyllis M. Keaty, Judges.
Amy, J., dissents and assigns written reasons.
REVERSED AND REMANDED.
Lauren Gay Coleman Attorney at Law 910 Foisy Avenue Alexandria, Louisiana 71301 (318) 449-9857 Counsel for Plaintiff/Appellant: Lynton O. Hester, IV
Wade T. Visconte All American Law Firm of Louisiana, LLC 1500 North Market Street, Suite C-106 Shreveport, Louisiana 71107 (318) 918-1245 Counsel for Defendant/Appellee: Malcolm Burns d/b/a Burns Builders Karl H. Schmid Sidney W. Degan, III Degan, Blanchard & Nash 400 Poydras Street, Suite 2600 New Orleans, Louisiana 70130 (504) 529-3333 Counsel for Defendant/Appellee: Gemini Insurance Company
David Moragas Richard E. King Galloway, Johnson, Tompkins, Burr & Smith 701 Poydras Street, Suite 4040 New Orleans, Louisiana 70139 (504) 525-6802 COUNSEL FOR DEFENDANT/APPELLEE: Zurich North America KEATY, Judge.
The parties entered into a contract for the construction of a new home.
Contending that the quality of the defendant’s work was sub-par, the plaintiff
refused to issue a scheduled progress payment. The defendant allegedly did not fix
the defective construction. The plaintiff filed suit after the parties failed to resolve
their dispute, seeking damages for the alleged shoddy construction among other
remedies. The defendant filed a reconventional demand, seeking payment of sums
he alleged were due under the contract and subsequently filed a motion for
summary judgment, seeking dismissal of the plaintiff’s claims and judgment in his
favor on the reconventional demand. The trial court granted the defendant’s
motion for summary judgment, and the plaintiff now appeals. For the following
reasons, we reverse the trial court’s grant of summary judgment and remand the
matter for further proceedings consistent with this opinion.
Factual and Procedural Background
According to the record, in December of 2005, the plaintiff, Lynton O.
Hester, IV (Hester), entered into a contract with the defendant, Malcolm L. Burns
d/b/a Burns Builders (Burns), for the construction of a new home in Rapides
Parish. The contract price was initially $303,287.00. However, an addendum
signed in January of 2006 increased the contract price to $322,287.00. The
financing of the home was closed in March 2006, and construction began shortly
thereafter. The contract between the parties called for progress payments (or
draws) to be made when the construction reached various stages of completion and
conditioned payment upon “substantial completion” of those phases. On March 16,
2006, the first payment was made by Hester in the amount of $18,447.46. The
second payment in the amount of $96,686.10 was made on April 20, 2006, and the
third payment in the amount of $88,000.00 was made on June 22, 2006. Thereafter, issues arose between Hester and Burns concerning the workmanship of the trim
portion of the construction. Burns contends that when the trim stage was
completed, Hester refused to tender the progress payment for that stage of
construction. Hester contends that because there were issues with the
workmanship, he hired an expert, Philip Beard (Beard), to conduct an inspection of
the residence and, based on Beard’s report, refused to authorize further payment to
Burns. Burns refused to do any further work. According to the briefs, the parties
were unable to reach any agreement concerning correction of the alleged defects.
Hester then filed the instant suit alleging breach of contract, defects in
construction, and general damages for cost and injuries that resulted from delay in
completion of the home. Burns filed an answer and reconventional demand,
seeking sums that he alleged were due under the terms of the contract. Hester filed
an answer to the reconventional demand, denying that additional sums were due.
Burns filed a motion for summary judgment, alleging he was entitled to judgment
dismissing Hester’s claims and granting Burns’ relief as a matter of law because
there was no genuine issue of material fact. After a hearing, the trial court granted
judgment in favor of Burns on his reconventional demand in the amount of
$96,686.10 with eighteen percent judicial interest, pursuant to the terms of the
contract. It dismissed Hester’s claims against Burns. Hester appeals, asserting
that:
1. The trial court erred in granting Summary Judgment in favor of Burns Builders and dismissing the claims of the Appellant for breach of contract.
2. The trial court erred in granting Judgment in favor of Burns Builders and awarding him $96,686.10 representing sums it determined to be due under the contract.
2 Discussion
In Wright v. Louisiana Power & Light, 06-1181, p. 16 (La. 3/9/07), 951
So.2d 1058, 1069 (quoting Babin v. Winn-Dixie Louisiana, Inc., 00-78 (La.
6/30/00), 764 So.3d 37), the supreme court discussed the standard for granting a
motion for summary judgment, stating:
A motion for summary judgment will be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to material fact, and that mover is entitled to judgment as a matter of law.” La.C.C.P. art. 966(B).
Appellate courts review summary judgments de novo. Supreme Servs. &
Specialty Co., Inc. v. Sonny Greer, Inc., 06-1827 (La. 5/22/07), 958 So.2d 634. In
that review, we must determine whether “the pleadings, depositions, answers to
interrogatories, and admissions on file, together with the affidavits, if any, show
that there is no genuine issue as to material fact, and that mover is entitled to
judgment as a matter of law.” La.Code Civ.P. art. 966(B).
Hester’s assignments of error address the trial court’s grant of summary
judgment. Hester contends that his expert’s report on construction defects creates
genuine issues of material fact remaining that would defeat Burns’ motion for
summary judgment. We agree.
The parties entered into a written contract to build before construction
began. Generally, a contract has the effect of law between the parties. Paddison
Builders, Inc. v. Turncliff, 95-1753 (La.App. 1 Cir. 4/4/96), 672 So.2d 1133, writ
denied, 96-1675 (La. 10/4/96), 679 So.2d 1386. When a contract is clear,
unambiguous, and does not lead to absurd consequences, the court should not infer
beyond the written agreement to gather the parties’ true intentions. Lyons v.
Coleman, 31,866 (La.App. 2 Cir. 5/5/99), 743 So.2d 213. In the contract to build
between Hester and Burns, paragraph five allows the plaintiff to withhold funds if 3 the work performed by the builder is defective and not remedied. Paragraph ten
requires the builder to fix any and all defects. Hester’s expert signed an affidavit
outlining numerous construction defects. Burns did not submit evidence showing
that he fixed the defects. Pursuant to the contract, only when the alleged defects
are fixed does plaintiff have a duty to pay the builder.
Burns filed a reconventional demand asserting that payment was owed
pursuant to the contract.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
11-1537
LYNTON O. HESTER, IV
VERSUS
BURNS BUILDERS, ET AL.
**********
APPEAL FROM THE NINTH JUDICIAL DISTRICT COURT PARISH OF RAPIDES, NO. 230,061 HONORABLE DONALD T. JOHNSON, DISTRICT JUDGE
PHYLLIS M. KEATY JUDGE
Court composed of Sylvia R. Cooks, Marc T. Amy, Billy Howard Ezell, J. David Painter, and Phyllis M. Keaty, Judges.
Amy, J., dissents and assigns written reasons.
REVERSED AND REMANDED.
Lauren Gay Coleman Attorney at Law 910 Foisy Avenue Alexandria, Louisiana 71301 (318) 449-9857 Counsel for Plaintiff/Appellant: Lynton O. Hester, IV
Wade T. Visconte All American Law Firm of Louisiana, LLC 1500 North Market Street, Suite C-106 Shreveport, Louisiana 71107 (318) 918-1245 Counsel for Defendant/Appellee: Malcolm Burns d/b/a Burns Builders Karl H. Schmid Sidney W. Degan, III Degan, Blanchard & Nash 400 Poydras Street, Suite 2600 New Orleans, Louisiana 70130 (504) 529-3333 Counsel for Defendant/Appellee: Gemini Insurance Company
David Moragas Richard E. King Galloway, Johnson, Tompkins, Burr & Smith 701 Poydras Street, Suite 4040 New Orleans, Louisiana 70139 (504) 525-6802 COUNSEL FOR DEFENDANT/APPELLEE: Zurich North America KEATY, Judge.
The parties entered into a contract for the construction of a new home.
Contending that the quality of the defendant’s work was sub-par, the plaintiff
refused to issue a scheduled progress payment. The defendant allegedly did not fix
the defective construction. The plaintiff filed suit after the parties failed to resolve
their dispute, seeking damages for the alleged shoddy construction among other
remedies. The defendant filed a reconventional demand, seeking payment of sums
he alleged were due under the contract and subsequently filed a motion for
summary judgment, seeking dismissal of the plaintiff’s claims and judgment in his
favor on the reconventional demand. The trial court granted the defendant’s
motion for summary judgment, and the plaintiff now appeals. For the following
reasons, we reverse the trial court’s grant of summary judgment and remand the
matter for further proceedings consistent with this opinion.
Factual and Procedural Background
According to the record, in December of 2005, the plaintiff, Lynton O.
Hester, IV (Hester), entered into a contract with the defendant, Malcolm L. Burns
d/b/a Burns Builders (Burns), for the construction of a new home in Rapides
Parish. The contract price was initially $303,287.00. However, an addendum
signed in January of 2006 increased the contract price to $322,287.00. The
financing of the home was closed in March 2006, and construction began shortly
thereafter. The contract between the parties called for progress payments (or
draws) to be made when the construction reached various stages of completion and
conditioned payment upon “substantial completion” of those phases. On March 16,
2006, the first payment was made by Hester in the amount of $18,447.46. The
second payment in the amount of $96,686.10 was made on April 20, 2006, and the
third payment in the amount of $88,000.00 was made on June 22, 2006. Thereafter, issues arose between Hester and Burns concerning the workmanship of the trim
portion of the construction. Burns contends that when the trim stage was
completed, Hester refused to tender the progress payment for that stage of
construction. Hester contends that because there were issues with the
workmanship, he hired an expert, Philip Beard (Beard), to conduct an inspection of
the residence and, based on Beard’s report, refused to authorize further payment to
Burns. Burns refused to do any further work. According to the briefs, the parties
were unable to reach any agreement concerning correction of the alleged defects.
Hester then filed the instant suit alleging breach of contract, defects in
construction, and general damages for cost and injuries that resulted from delay in
completion of the home. Burns filed an answer and reconventional demand,
seeking sums that he alleged were due under the terms of the contract. Hester filed
an answer to the reconventional demand, denying that additional sums were due.
Burns filed a motion for summary judgment, alleging he was entitled to judgment
dismissing Hester’s claims and granting Burns’ relief as a matter of law because
there was no genuine issue of material fact. After a hearing, the trial court granted
judgment in favor of Burns on his reconventional demand in the amount of
$96,686.10 with eighteen percent judicial interest, pursuant to the terms of the
contract. It dismissed Hester’s claims against Burns. Hester appeals, asserting
that:
1. The trial court erred in granting Summary Judgment in favor of Burns Builders and dismissing the claims of the Appellant for breach of contract.
2. The trial court erred in granting Judgment in favor of Burns Builders and awarding him $96,686.10 representing sums it determined to be due under the contract.
2 Discussion
In Wright v. Louisiana Power & Light, 06-1181, p. 16 (La. 3/9/07), 951
So.2d 1058, 1069 (quoting Babin v. Winn-Dixie Louisiana, Inc., 00-78 (La.
6/30/00), 764 So.3d 37), the supreme court discussed the standard for granting a
motion for summary judgment, stating:
A motion for summary judgment will be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to material fact, and that mover is entitled to judgment as a matter of law.” La.C.C.P. art. 966(B).
Appellate courts review summary judgments de novo. Supreme Servs. &
Specialty Co., Inc. v. Sonny Greer, Inc., 06-1827 (La. 5/22/07), 958 So.2d 634. In
that review, we must determine whether “the pleadings, depositions, answers to
interrogatories, and admissions on file, together with the affidavits, if any, show
that there is no genuine issue as to material fact, and that mover is entitled to
judgment as a matter of law.” La.Code Civ.P. art. 966(B).
Hester’s assignments of error address the trial court’s grant of summary
judgment. Hester contends that his expert’s report on construction defects creates
genuine issues of material fact remaining that would defeat Burns’ motion for
summary judgment. We agree.
The parties entered into a written contract to build before construction
began. Generally, a contract has the effect of law between the parties. Paddison
Builders, Inc. v. Turncliff, 95-1753 (La.App. 1 Cir. 4/4/96), 672 So.2d 1133, writ
denied, 96-1675 (La. 10/4/96), 679 So.2d 1386. When a contract is clear,
unambiguous, and does not lead to absurd consequences, the court should not infer
beyond the written agreement to gather the parties’ true intentions. Lyons v.
Coleman, 31,866 (La.App. 2 Cir. 5/5/99), 743 So.2d 213. In the contract to build
between Hester and Burns, paragraph five allows the plaintiff to withhold funds if 3 the work performed by the builder is defective and not remedied. Paragraph ten
requires the builder to fix any and all defects. Hester’s expert signed an affidavit
outlining numerous construction defects. Burns did not submit evidence showing
that he fixed the defects. Pursuant to the contract, only when the alleged defects
are fixed does plaintiff have a duty to pay the builder.
Burns filed a reconventional demand asserting that payment was owed
pursuant to the contract. In order for Burns to succeed on his claim, he would have
to prove that payment was owed. Under paragraphs five and ten, Hester had the
right to withhold payment if he believed the construction was defective. Whether
there were defects is a question of fact for the trial court to determine. The scope
of damages is another determination for the fact finder. If there were no defects,
Burns would be entitled to payment. Hester’s assertion that there were damages
presents a question of material fact that should have been addressed by the trial
court. Accordingly, summary judgment was inappropriate.
DECREE
For the foregoing reasons, the judgment of the trial court is reversed, and the
matter is remanded for further proceedings consistent with this opinion. Costs of
this appeal are assessed to defendant/appellee, Malcolm Burns d/b/a Burns
Builders.
4 NUMBER 11-1537
COURT OF APPEAL, THIRD CIRCUIT
STATE OF LOUISIANA
AMY, J., dissenting.
I respectfully dissent from the majority’s opinion in this case, as I would
affirm the trial court’s grant of summary judgment.
Louisiana Code of Civil Procedure Article 966(C)(2) addresses the burden
of proof in a motion for summary judgment. Per Article 966(C)(2), “[t]he burden
of proof remains with the movant.” However, if the movant is not the party who
will bear the burden of proof at trial, the movant must only “point out to the court
that there is an absence of factual support for one or more elements essential to the
adverse party’s claim . . . . Thereafter, if the adverse party fails to produce factual
support sufficient to establish that he will be able to satisfy his evidentiary burden
of proof at trial, there is no genuine issue of material fact.” Id. See Wright v. La.
Power & Light, 06-1181 (La. 3/9/07), 951 So.2d 1058.
Hester’s suit alleged both breach of contract and defective workmanship
claims. In order to succeed on these claims, Hester had to prove his damages. See,
e.g., Maxwell v. Cayse, 10-680, p. 3 (La.App. 3 Cir. 12/8/10), 54 So.3d 118, 121
(Stating, in a breach of contract case, “[t]o establish a contractor’s liability for
damages due to defective workmanship, the owner must prove: (1) the existence
and nature of the defects; (2) that the defects are due to faulty materials or
workmanship; and (3) the cost of repairing the defects.”).
The record indicates that Hester submitted evidence that creates a genuine
issue of material fact with regard to the existence of construction defects. Specifically, Hester submitted an expert’s report that indicates that are several
architectural and structural defects, including garage settlement, problems with
several windows and a handrail, and walls that are not straight. Burns did not
submit any evidence that would contradict the expert’s conclusions that
architectural and structural defects existed. Further, the record indicates that Burns
replaced some of the drywall that Hester considered defective, indicating that
Burns attempted to remedy at least some of the alleged defects.
However, the record reveals that Hester did not submit any evidence
establishing the cost of completion or correction of the alleged defects. After
Burns pointed out the lack of factual support for that element, the burden of proof
then shifted to Hester to show that he would be able to meet his burden at trial. In
my view, the record indicates that he failed to do so. Of particular note, Hester
admitted that he had not contacted any other contractors about repairing the alleged
construction defects and/or completing the project, nor had he obtained any bids or
estimates concerning the cost of repair or completion. Further, in addition to
damages, Hester requested specific performance. However, the record indicates
that the property was sold at foreclosure, thus, at a minimum, abrogating the
possibility of specific performance in this case.
Further, I find no error with regard to the trial court’s grant of summary
judgment on Burns’ reconventional demand for the payments due under the
contract. In my view, Hester failed to rebut Burns’ evidence showing that the
“trim” stage of construction was complete and that, therefore, Burns was entitled to
the third draw payment. My review of the record reveals that Burns submitted
evidence indicating that the “trim” stage of construction was complete, including
documents and a deposition from Hester’s bank to that effect.
Hester contends that Burns had been slightly overpaid, and that, therefore,
Burns was not entitled to any additional payments. In support of that contention,
2 Hester submitted evidence indicating that construction was 72% complete and that
Burns had been paid slightly more than 72% of the contract price. However, the
contract specifies that “[p]rogress payments will be made in the following amounts
on the following Completions schedule.” The “Completions schedule” lists four
“completed tasks,” including “Completion of Trim,” and an “Amount to be Paid”
upon completion of the associated stage. Thus, pursuant to the contract, Burns’
payments are not pegged to the percentage of construction completed, but are tied
to the completion of discrete stages under the contract.
Accordingly, in my view, Burns demonstrated his entitlement to summary
judgment dismissing Hester’s claims and awarding him the third draw payment
due under the contract. See Wright, 951 So.2d 1058.
For these reasons, I dissent.