Lynn v. Schulte

2015 Ohio 5527
CourtOhio Court of Appeals
DecidedDecember 31, 2015
Docket2015-A-0017 & 2015-A-0026
StatusPublished
Cited by2 cases

This text of 2015 Ohio 5527 (Lynn v. Schulte) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lynn v. Schulte, 2015 Ohio 5527 (Ohio Ct. App. 2015).

Opinion

[Cite as Lynn v. Schulte, 2015-Ohio-5527.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

ASHTABULA COUNTY, OHIO

LARRY LYNN, : OPINION

Plaintiff-Appellant, : CASE NOS. 2015-A-0017 - vs - : 2015-A-0026

DANA SCHULTE, :

Defendant-Appellee. :

Civil Appeal from the Ashtabula County Court of Common Pleas, Case No. 2013 CV 151.

Judgment: Reversed and remanded.

Larry Lynn, pro se, 4243 Harper Street, Perry, OH 44081 (Plaintiff-Appellant).

Christopher M. Newcomb, Christopher M. Newcomb, Esq., LLC, 213 Washington Street, Conneaut, OH 44030 (For Defendant-Appellee).

DIANE V. GRENDELL, J.

{¶1} Plaintiff-appellant, Larry Lynn, appeals the judgment of the Ashtabula

County Court of Common Pleas, finding in favor of defendant-appellee, Dana Schulte,

for breach of contract. The issues before this court are whether a determination that a

party has materially breached a contract is nullified where the non-breaching party

subsequently enters into a purportedly illegal contract with a third party in mitigation of

the breach, and whether a trial court may award, as damages for breach of contract, the

costs of hiring a third-party to complete the contract without considering the original contract price. For the following reasons, we reverse the decision of the lower court

with respect to damages and remand this matter with instructions for the court to award

damages in a manner consistent with this opinion.

{¶2} On February 1, 2013, Lynn filed a Small Claims Complaint against Schulte

in Ashtabula Municipal Court, Small Claims Division, seeking judgment in the amount of

$3,000 for “labor and materials provided at 1636 West 8th Street, Ashtabula.”

{¶3} On February 21, 2013, Schulte filed an Answer and Counterclaims,

seeking judgment in excess of $15,000 for Breach of Contract, Negligence, Slander of

Title, and Fraudulent Inducement.

{¶4} On February 25, 2013, the case was transferred to the Ashtabula County

Court of Common Pleas.

{¶5} On September 18, 2014, the case was tried before a magistrate.

{¶6} On December 4, 2014, a Magistrate’s Decision was issued. The following

findings were made by the magistrate:

Defendant is the owner of residential rental property located at

1636 West 8th Street in Ashtabula, Ohio. On September 13, 2010,

the Ohio Department of Health (“ODH”) conducted a public health

lead risk assessment at Defendant’s property, whereupon hazards

related to lead paint were discovered. Defendant received an order

from the ODH dated October 21, 2010 which detailed the work

necessary to abate the hazard. * * * The order demanded that the

hazard be abated within 90 days, and specified that the work was

to be done by individuals who had been properly trained and/or

2 certified in lead abatement. The parties entered into a one-page

contract * * *, dated September 28, 2011. * * * The contract listed

[six] tasks which Plaintiff was to perform in order to bring the

residence into compliance with the ODH order. * * * The parties

originally agreed that Defendant would provide the new windows

and doors, and agreed on a total contract price of $7,500.00.

However, this term was changed to $10,000.00 when it was agreed

that Plaintiff would provide the new windows and doors. On the

contract signed by the parties, the original contract price of

$7,500.00 is crossed off and the new $10,000.00 price is

handwritten above it. The contract called for three (3) equal

payments, an initial payment of $2,500.00, a second $2,500.00

payment upon completion of items 1-4 [listed in the contract], and a

third $2,500.00 payment when all of Plaintiff’s obligations under the

contract had been performed. Despite the payment plan set forth in

the written contract, which the parties opted not to amend, both

parties testified that Defendant’s initial payment to Plaintiff was

$5,000.00. * * * Plaintiff and his Son, Levi Lynn, testified that at

some point they completed all the work set forth in items 1-4 above.

Both parties testified that when Plaintiff felt he had completed items

1-4, he demanded further payment. * * * Defendant refused to pay

Plaintiff any additional funds because Plaintiff did not complete

items 1-4 prior to demanding further payment. Plaintiff refused to

3 perform any more work under the contract until he received further

payment. Defendant testified that because the work set forth in the

ODH order dated October 21, 2010 * * * was not completed within

the specified 90 days, he received from the ODH a Notice of

Noncompliance and Order to Vacate dated February 10, 2012.

Defendant then contacted the Health Department, advising them of

the situation with Plaintiff. An ODH inspector then came to the

residence, met with general contractor and project manager, Jason

Hamilton, and advised Hamilton as to the work which needed to be

done in order to comply with the October 21, 2010 order. Mr.

Hamilton is not licensed or trained in lead abatement, but

completed the work under the guidance and direction of the ODH

inspector. Mr. Hamilton submitted a bill to Defendant for the work

completed. * * * The ODH conducted a clearance examination,

and Defendant received an ODH Notice of Compliance dated

March 13, 2012 * * * indicating that the hazards set forth in the

initial October 21, 2010 order * * * had been abated. * * * [U]pon

weighing the credibility and weight of the evidence presented, the

Magistrate does not find that Plaintiff completed the work set forth

under items #3 and 4 of the contract prior to demanding additional

payment. * * * The evidence dictates that Defendant is entitled to

compensation from Plaintiff for funds paid to Jason Hamilton for the

4 completion of Plaintiff’s contractual obligations, and for any rent lost

due to Plaintiff’s breach of contract.

{¶7} On December 24, 2014, Lynn filed objections to the Magistrate’s Decision.

{¶8} On January 5, 2015, the trial court dismissed the objections as untimely,

inadvertently citing Civil Rule 53(D)(2)(b), which pertains to magistrate’s orders.

{¶9} On January 23, 2015, Lynn asked the trial court to review the timeliness of

his objections.

{¶10} On January 29, 2015, the trial court overruled Lynn’s request, construed

as a motion for reconsideration.

{¶11} On March 13, 2015, Lynn filed a Notice of Appeal from the January 29,

2015 Judgment Entry and the December 4, 2014 Magistrate’s Decision, assigned Court

of Appeals No. 2015-A-0017.

{¶12} On March 17, 2015, a hearing was held on damages before the trial court.

{¶13} On March 18, 2015, the trial court awarded Schulte “the sum of $3,846.26

for attorney fees; $5,200.00 for monies paid to Jason Hamilton to complete the job that

the Plaintiff was originally supposed to perform; the sum of $4,800.00 for lost rent; and

the sum of $365.00 for the final lead inspection.”

{¶14} On April 17, 2015, Lynn filed a Notice of Appeal from the March 18, 2015

Judgment Entry and the December 4, 2014 Magistrate’s Decision, assigned Court of

Appeals No. 2015-A-0026.

{¶15} On May 5, 2015, this court consolidated the appeals “for purposes of

briefing, oral argument, and disposition.”

{¶16} On appeal, Lynn raises the following assignments of error:

5 {¶17} “[1.] The trial court committed prejudicial error in granting defendant-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bova v. B & J Pools, Inc.
2023 Ohio 1680 (Ohio Court of Appeals, 2023)
Karnofel v. Nye
2016 Ohio 3406 (Ohio Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2015 Ohio 5527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lynn-v-schulte-ohioctapp-2015.