Lynn v. Schulte

2015 Ohio 5527
Ohio Court of Appeals·Decided December 31, 2015·No. 2015-A-0017 & 2015-A-0026·Published·Cited by 2 cases

Opinion

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT ASHTABULA COUNTY, OHIO

LARRY LYNN, : OPINION

Plaintiff-Appellant, :

CASE NOS. 2015-A-0017

- vs - : 2015-A-0026

DANA SCHULTE, :

Defendant-Appellee. :

Civil Appeal from the Ashtabula County Court of Common Pleas, Case No. 2013 CV 151.

Judgment: Reversed and remanded.

Larry Lynn, pro se, 4243 Harper Street, Perry, OH 44081 (Plaintiff-Appellant).

Christopher M. Newcomb, Christopher M. Newcomb, Esq., LLC, 213 Washington Street, Conneaut, OH 44030 (For Defendant-Appellee).

DIANE V. GRENDELL, J.

{¶1} Plaintiff-appellant, Larry Lynn, appeals the judgment of the Ashtabula County Court of Common Pleas, finding in favor of defendant-appellee, Dana Schulte, for breach of contract. The issues before this court are whether a determination that a party has materially breached a contract is nullified where the non-breaching party subsequently enters into a purportedly illegal contract with a third party in mitigation of the breach, and whether a trial court may award, as damages for breach of contract, the costs of hiring a third-party to complete the contract without considering the original

contract price. For the following reasons, we reverse the decision of the lower court with respect to damages and remand this matter with instructions for the court to award damages in a manner consistent with this opinion.

{¶2} On February 1, 2013, Lynn filed a Small Claims Complaint against Schulte in Ashtabula Municipal Court, Small Claims Division, seeking judgment in the amount of $3,000 for “labor and materials provided at 1636 West 8th Street, Ashtabula.”

{¶3} On February 21, 2013, Schulte filed an Answer and Counterclaims, seeking judgment in excess of $15,000 for Breach of Contract, Negligence, Slander of Title, and Fraudulent Inducement.

{¶4} On February 25, 2013, the case was transferred to the Ashtabula County Court of Common Pleas.

{¶5} On September 18, 2014, the case was tried before a magistrate.

{¶6} On December 4, 2014, a Magistrate’s Decision was issued. The following findings were made by the magistrate:

Defendant is the owner of residential rental property located at 1636 West 8th Street in Ashtabula, Ohio. On September 13, 2010, the Ohio Department of Health (“ODH”) conducted a public health lead risk assessment at Defendant’s property, whereupon hazards related to lead paint were discovered. Defendant received an order from the ODH dated October 21, 2010 which detailed the work necessary to abate the hazard. * * * The order demanded that the hazard be abated within 90 days, and specified that the work was to be done by individuals who had been properly trained and/or

certified in lead abatement. The parties entered into a one-page contract * * *, dated September 28, 2011. * * * The contract listed [six] tasks which Plaintiff was to perform in order to bring the residence into compliance with the ODH order. * * * The parties originally agreed that Defendant would provide the new windows and doors, and agreed on a total contract price of $7,500.00. However, this term was changed to $10,000.00 when it was agreed that Plaintiff would provide the new windows and doors. On the contract signed by the parties, the original contract price of $7,500.00 is crossed off and the new $10,000.00 price is handwritten above it. The contract called for three (3) equal payments, an initial payment of $2,500.00, a second $2,500.00 payment upon completion of items 1-4 [listed in the contract], and a third $2,500.00 payment when all of Plaintiff’s obligations under the contract had been performed. Despite the payment plan set forth in the written contract, which the parties opted not to amend, both parties testified that Defendant’s initial payment to Plaintiff was $5,000.00. * * * Plaintiff and his Son, Levi Lynn, testified that at some point they completed all the work set forth in items 1-4 above. Both parties testified that when Plaintiff felt he had completed items 1-4, he demanded further payment. * * * Defendant refused to pay Plaintiff any additional funds because Plaintiff did not complete items 1-4 prior to demanding further payment. Plaintiff refused to

perform any more work under the contract until he received further payment. Defendant testified that because the work set forth in the ODH order dated October 21, 2010 * * * was not completed within the specified 90 days, he received from the ODH a Notice of Noncompliance and Order to Vacate dated February 10, 2012. Defendant then contacted the Health Department, advising them of the situation with Plaintiff. An ODH inspector then came to the residence, met with general contractor and project manager, Jason Hamilton, and advised Hamilton as to the work which needed to be done in order to comply with the October 21, 2010 order. Mr. Hamilton is not licensed or trained in lead abatement, but completed the work under the guidance and direction of the ODH inspector. Mr. Hamilton submitted a bill to Defendant for the work completed. * * * The ODH conducted a clearance examination, and Defendant received an ODH Notice of Compliance dated March 13, 2012 * * * indicating that the hazards set forth in the initial October 21, 2010 order * * * had been abated. * * * [U]pon weighing the credibility and weight of the evidence presented, the Magistrate does not find that Plaintiff completed the work set forth under items #3 and 4 of the contract prior to demanding additional payment. * * * The evidence dictates that Defendant is entitled to compensation from Plaintiff for funds paid to Jason Hamilton for the

completion of Plaintiff’s contractual obligations, and for any rent lost due to Plaintiff’s breach of contract.

{¶7} On December 24, 2014, Lynn filed objections to the Magistrate’s Decision.

{¶8} On January 5, 2015, the trial court dismissed the objections as untimely, inadvertently citing Civil Rule 53(D)(2)(b), which pertains to magistrate’s orders.

{¶9} On January 23, 2015, Lynn asked the trial court to review the timeliness of his objections.

{¶10} On January 29, 2015, the trial court overruled Lynn’s request, construed as a motion for reconsideration.

{¶11} On March 13, 2015, Lynn filed a Notice of Appeal from the January 29, 2015 Judgment Entry and the December 4, 2014 Magistrate’s Decision, assigned Court of Appeals No. 2015-A-0017.

{¶12} On March 17, 2015, a hearing was held on damages before the trial court.

{¶13} On March 18, 2015, the trial court awarded Schulte “the sum of $3,846.26 for attorney fees; $5,200.00 for monies paid to Jason Hamilton to complete the job that the Plaintiff was originally supposed to perform; the sum of $4,800.00 for lost rent; and the sum of $365.00 for the final lead inspection.”

{¶14} On April 17, 2015, Lynn filed a Notice of Appeal from the March 18, 2015 Judgment Entry and the December 4, 2014 Magistrate’s Decision, assigned Court of Appeals No. 2015-A-0026.

{¶15} On May 5, 2015, this court consolidated the appeals “for purposes of briefing, oral argument, and disposition.”

{¶16} On appeal, Lynn raises the following assignments of error:

{¶17} “[1.] The trial court committed prejudicial error in granting defendant-

appellees’ DANA SCHULTE favorable judgment based on the conclusion that his handyman, JASON HAMILTON, could somehow go around the laws of the STATE OF OHIO DEPARTMENT OF HEALTH (otherwise known as ODH) and perform [the] work of a Licensed Lead Abatement Contractor without having the proper Lead Abatement License nor the proper training to do so.”

{¶18} “[2.] The trial court committed prejudicial error in granting defendants-

appellees’ request for reimbursement of loss of rent (8 months x 600.00 per month or 4800.00) and for claimed wages paid to the handyman (in the amount of 5200.00) for work that had nothing at all in common with the contract between plaintiff and defendant.”

Free access — add to your briefcase to read the full text and ask questions with AI

Lynn v. Schulte, 2015 Ohio 5527 (Ohio Ct. App. 2015).

2015 Ohio 5527 (Lynn v. Schulte) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bova v. B & J Pools, Inc.
2023 Ohio 1680 (Ohio Court of Appeals, 2023)
Karnofel v. Nye
2016 Ohio 3406 (Ohio Court of Appeals, 2016)