Lynch v. Snead Architectural Iron Works

116 S.W. 693, 132 Ky. 241, 1909 Ky. LEXIS 110
CourtCourt of Appeals of Kentucky
DecidedFebruary 26, 1909
StatusPublished
Cited by31 cases

This text of 116 S.W. 693 (Lynch v. Snead Architectural Iron Works) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lynch v. Snead Architectural Iron Works, 116 S.W. 693, 132 Ky. 241, 1909 Ky. LEXIS 110 (Ky. Ct. App. 1909).

Opinion

Opinion of the Court by

Judge Lassing

Reversing.

The Board of Education of the Methodist Church owns an office building in Louisville known as the “Kenyon Building.” It was six stories in height, and. the board desired to have it raised and made eight stories in height. Looking to this end, it employed architects to prepare plans and specifications for the desired work. Having secured the plans and specifications, it received bids from various contractors on the work in accordance with the plans and specifications. The bids received were for the entire work. Among the bidders who bid upon the work was E. P. Lynch, and he was the successful bidder. When he was making his estimate preparatory to bidding, he took from different contractors in particular lines of work bids for the parts of the work falling within their respective lines. Among those from whom he took bids was the Snead Architectural Iron Works, which bid for the structural steel work embraced in the contemplated improvement. After the contract had been awarded to Lynch, a dispute arose between the Snead Architectural Iron Works and Lynch as to whether or not the bid submitted by the Snead Architectural Iron Works had been accepted by Lynch. This dispute finally culminated in the institution of a suit for damages on the part of the Snead Architectural Iron Works against Lynch and the Board of Education of the Methodist Church, in which the plaintiff sought to recover of the defendants damages which it alleged it had sustained by [245]*245reason of its having been deprived of an opportunity to carry out its contract and supply the necessary structural steel for the building. The trial court held that no case was made out as to the Board of Education of the Methodist Church, and a peremptory instruction was given the jury to -find in its favor, which was done, and no appeal has been prosecuted from that judgment. The defendant Lynch in his answer joined issue with the plaintiff upon every material allegation of the petition, so that the question which was tried out in the lower court was whether or not the plaintiff had entered into a contract with the defendant, by the terms of which it was to supply the necessary structural steel at a designated price. Plaintiff contended that it had entered into an oral contract with the defendant, by the terms of which it was to supply all of the structural steel called for in the plans and specifications for the alteration of the Kenyon Building for the sum of $9,969; whereas the defendant contended that, while it was agreed and understood between him and the plaintiff that the plaintiff was to furnish the necessary structural steel for the price named, it was further agreed that their contract was to he reduced to writing, and the plaintiff was to execute a good and sufficient bond to guarantee the performance of its contract according to terms; that, although he frequently requested plaintiff to sign the contract, as per their agreement, and execute the required bond, it steadfastly failed and refused to do so, and that, after he had thus endeavored to procure the execution of the contract and bond ■according to their understanding for about two-months, he was compelled to and did make other arrangements, and notified plaintiff that he had done so. On the issue of contract or no contract the case [246]*246was tried before a jury, which returned a verdict in favor of plaintiff for $2,000, and the defendant appeals.

Two grounds are relied upon for reversal, first, that the court did not properly instruct the jury; and, second, that the verdict is against the law as given by the court. Upon the trial the court gave the following instructions:

“ (1) If you believe from the evidence that after the Snead Architectural Iron Works made its bid to the defendant, E. P. Lynch, to- do certain work in connection with the improvements at the Kenyon Building for a certain specified price, and that there was an acceptance of that offer by the defendant Lynch, then the law of this case is for the plaintiff, and you should so find, unless- the acceptance was made with the understanding between the parties that the work was to be done in a certain stipulated time, or that after that acceptance a contract between them should be put in writing and signed by the parties, or a bond should be executed by the Iron Works to Lynch. Now, if you believe any of those1 stipulaiions or terms were understood and agreed to between the parties, and the plaintiff, the Snead Architectural Iron Works, failed to do those things or any one of them, if it had agreed to it, then the law" of this case is for the defendant, and you- should so find.
“ (2) I further instruct you, gentlemen, that if you believe from the evidence that there was an agreement between these parties that the work should be done, and there was no stipulation as to the time within which it was to be done, then the Snead Architectural Iron Works had a reasonable time within which to do the work; but if there was- a stipulation as to- the time, and they failed to- do- the work within [247]*247that time or to proceed diligently to' do the work within that time, then they cannot recover.
“(3) I further instruct you, gentlemen, that although you may believe from the evidence there was an agreement, and although you may believe from the |- evidence that there was a stipulation as to the time; within which the work was to be done, yet if you further believe from the evidence that, before Lynch proceeded to have the work done by others than the plaintiff, the plaintiff notified Lynch that it desired that he should procure the materials and work from other sources, and notified him or stated to him that they did not regard that they had a contract with him to do the work then they cannot recover for his proceeding to do the work through others and not through them.
“(4) I further instruct you, gentlemen, although you may believe from the evidence that the Snead Architectural Works did agree that the work should be done within a certain stipulated time, and although you may believe from the evidence that they failed to do the work or to complete the work within that time, yet if you further believe from the evidence that they ceased in their preparation or progress of doing the work by reason of a notification from Lynch, the defendant, that he would not take their work or would not permit them to proceed with the work, then the delay on their part or failure on their part to comply with the contract as to the time, as to the three months, would not relieve Lynch of liability.
“ (5) I further instruct you that, if you find for the plaintiff, you will award the plaintiff such sum in damages as you believe from the evidence will reasonably and fairly compensate them for such loss or [248]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daniels v. Central Truckaway System, Inc.
253 S.W.2d 1 (Court of Appeals of Kentucky, 1952)
Wright v. Traders & General Insurance
123 S.W.2d 314 (Texas Supreme Court, 1939)
Maynard v. Kentucky & West Virginia Power Co.
98 S.W.2d 460 (Court of Appeals of Kentucky (pre-1976), 1936)
Refiners Oil Corp. v. Bell
92 S.W.2d 88 (Court of Appeals of Kentucky (pre-1976), 1936)
Louisville Water Co. v. Bowers
64 S.W.2d 444 (Court of Appeals of Kentucky (pre-1976), 1933)
Franklin County v. Bailey
63 S.W.2d 622 (Court of Appeals of Kentucky (pre-1976), 1933)
Malone's Ex'x v. Chesapeake & O. Ry. Co.
61 S.W.2d 876 (Court of Appeals of Kentucky (pre-1976), 1933)
Kentucky Utilities Co. v. Sapp's Adm'r
60 S.W.2d 976 (Court of Appeals of Kentucky (pre-1976), 1933)
C. L. & L. Motor Express v. Lyons
53 S.W.2d 978 (Court of Appeals of Kentucky (pre-1976), 1932)
Iseman v. Hayes
46 S.W.2d 110 (Court of Appeals of Kentucky (pre-1976), 1932)
Cooper v. Girdler
39 S.W.2d 1009 (Court of Appeals of Kentucky (pre-1976), 1931)
City of Madisonville v. Nisbit
39 S.W.2d 690 (Court of Appeals of Kentucky (pre-1976), 1931)
Louisville Railway Company v. Jackey
35 S.W.2d 28 (Court of Appeals of Kentucky (pre-1976), 1930)
Louisville & Nashville Railroad v. Muncey
17 S.W.2d 422 (Court of Appeals of Kentucky (pre-1976), 1928)
Axelson v. Jardine
223 N.W. 32 (North Dakota Supreme Court, 1928)
Ball v. Commonwealth
7 S.W.2d 237 (Court of Appeals of Kentucky (pre-1976), 1928)
Kentucky Independent Oil v. Schnitzler, Administrator
271 S.W. 570 (Court of Appeals of Kentucky (pre-1976), 1925)
Farmers Bank & Trust Co. v. Harding
272 S.W. 3 (Court of Appeals of Kentucky (pre-1976), 1925)
Myers v. Cassity
272 S.W. 718 (Court of Appeals of Kentucky (pre-1976), 1925)
Kahler Co. v. W. P. Brown & Sons Lumber Co.
254 S.W. 922 (Court of Appeals of Kentucky, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
116 S.W. 693, 132 Ky. 241, 1909 Ky. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lynch-v-snead-architectural-iron-works-kyctapp-1909.