Lyda Swinerton Builders, Inc. v. Pools by Blue Haven, Inc.

CourtCourt of Appeals of Texas
DecidedMarch 2, 2011
Docket04-10-00631-CV
StatusPublished

This text of Lyda Swinerton Builders, Inc. v. Pools by Blue Haven, Inc. (Lyda Swinerton Builders, Inc. v. Pools by Blue Haven, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyda Swinerton Builders, Inc. v. Pools by Blue Haven, Inc., (Tex. Ct. App. 2011).

Opinion

MEMORANDUM OPINION No. 04-10-00631-CV

LYDA SWINERTON BUILDERS, INC., Appellant

v.

POOLS BY BLUE HAVEN, INC., Appellee

From the 288th Judicial District Court, Bexar County, Texas Trial Court No. 2009-CI-20145 Honorable Solomon Casseb, III, Judge Presiding

Opinion by: Karen Angelini, Justice

Sitting: Karen Angelini, Justice Phylis J. Speedlin, Justice Steven C. Hilbig, Justice

Delivered and Filed: March 2, 2011

REVERSED AND REMANDED

The present appeal arises from the trial court’s denial of a motion to compel arbitration

filed by Lyda Swinerton Builders, Inc. (“Lyda”). We reverse the trial court’s orders denying

Lyda’s motion to compel arbitration and remand the case to the trial court for further

proceedings. 04-10-00631-CV

BACKGROUND

The facts pertinent to Lyda’s appeal are largely undisputed. On July 14, 2006, Lyda

entered into a construction contract with Riverwalk CY Hotel Partners, Ltd. (“Riverwalk”) to

construct a hotel known as the Marriott Courtyard at the San Antonio Riverwalk (the “Hotel”).

The construction agreement between Lyda and Riverwalk contained provisions for the mediation

of disputes. The agreement further provided that if formal mediation could not resolve a dispute,

binding arbitration under the Construction Industry Rules of the American Arbitration

Association was required.

Lyda subsequently entered into a subcontract (the “Subcontract”) with Pools by Blue

Haven, Inc. (“Blue Haven”) on March 8, 2007, concerning the design/construction of a

swimming pool and spa at the Hotel. The Subcontract contained various dispute resolution

clauses, including:

15. CLAIMS RESOLUTION PROCEDURE

(a) In the event of any dispute or claim between Contractor and Owner which directly or indirectly involves Subcontractor’s Work, or in the event of any dispute or claim between Contractor and Subcontractor which directly or indirectly involves Subcontractor’s Work, or in the event of any dispute or claim between Contractor and Subcontractor which directly or indirectly involves a claim against Owner for either additional compensation or an extension of time under the Contract Documents, Subcontractor agrees to be bound to Contractor and Contractor agrees to be bound to Subcontractor by all decisions, findings or determinations made by the person so authorized in the Contract Documents, by an administrative agency, court of competent jurisdiction, or arbitration panel, whether or not Subcontractor is a party to the proceedings before said person, agency, court or panel. If any dispute or claim involving Subcontractor is prosecuted or defended by Contractor, Subcontractor agrees to cooperate fully with Contractor and to furnish all documents, statements, witnesses and other information required by Contractor for such purpose and shall pay or reimburse Contractor for all expenses and costs, including reasonable attorney’s fees, incurred in connection therewith to the extent of Subcontractor’s interest in such claim or dispute. It is expressly understood and agreed in connection with the determination of such claims or disputes that, as to any and all work done and agreed to be done by Subcontractor, and as to any and all damages, if any,

-2- 04-10-00631-CV

incurred by Subcontractor in connection with the Project, Contractor shall never be liable to Subcontractor to any greater extent than Owner is liable to Contractor. If a dispute between Contractor and Subcontractor is not subject to the dispute resolution procedure set forth in the Contract Documents, then the dispute resolution procedure set forth in paragraphs (b) and (c) below shall apply.

(b) MEDIATION. Subcontractor agrees, upon the request of Contractor, to submit any claim or dispute to a neutral mediator and to negotiate in good faith to reach an agreement with respect to the dispute. Any such mediation proceeding shall be under the auspices of and governed by the rules of the Construction Industry Mediation Rules of the American Arbitration Association; or as may be agreed by the parties. In such event, neither party shall proceed with arbitration or litigation until the completion of mediation proceedings. The costs of the mediator shall be shared equally by the parties. Venue for the mediation shall be at the most practical location convenient to the parties and/or the location of the project.

(c) ELECTION OF ARBITRATION OR LITIGATION. In the event of a dispute between Contractor and Subcontractor, Contractor may elect to arbitrate such dispute in the manner provided below, or to litigate the dispute in a forum with jurisdiction to decide the dispute. Any arbitration proceeding shall be conducted in accordance with the Construction Industry Rules of the American Arbitration Association, provided, however, that only one arbitrator shall hear the dispute. The award rendered by the arbitrator shall be final and judgment may be entered upon in accordance with applicable law in any court having jurisdiction.

****

(e) FEDERAL ARBITRATION ACT. The arbitration rights set forth herein shall be specifically enforceable under the Federal Arbitration Act, 9 U.S.C. 1, et seq., the parties agreeing that the transactions contemplated hereunder will have an effect on interstate commerce.

During the course of the construction of the Hotel, Lyda encountered various delays to

the dissatisfaction of Riverwalk. In accordance with their contractual agreement, Lyda and

Riverwalk proceeded to mediation in October and November 2008 to resolve their issues. The

mediation between Lyda and Riverwalk was unsuccessful.

On January 9, 2009, Blue Haven submitted its initial pool/spa design for the Hotel for

approval by the project architect. The project architect rejected Blue Haven’s initial submittal

and requested Blue Haven to resubmit its plans. Despite the project architect’s rejection of Blue

-3- 04-10-00631-CV

Haven’s initial pool/spa design, Blue Haven moved forward with the construction of the pool

and spa without resubmitting its design for approval. Blue Haven completed construction of the

pool and spa and proceeded to submit pay applications to Lyda on May 21, 2009 and June 25,

2009.

After completing the construction of the pool and spa, Blue Haven resubmitted its plans

to the project architect for his approval on June 18, 2009 and, again, on August 5, 2009. The

project architect rejected both sets of plans submitted by Blue Haven and refused to certify Blue

Haven’s pay applications.

In the meantime, Riverwalk filed a demand for arbitration against Lyda on July 9, 2009.

Riverwalk’s “demand for arbitration included an exhibit which listed three hundred and eighty-

four (384) items of allegedly non-conforming work which included items relating to Blue

Haven’s work on the Project.” Riverwalk and Lyda selected arbitrators and agreed on a

scheduling order for the arbitration proceeding.

On October 8, 2009, Blue Haven sent a demand letter to Lyda requesting payment of

$59,600 for the construction of the pool and spa at the Hotel. Blue Haven’s letter sought

payment of the entire amount past due and warned Lyda that it would “have no choice but to file

suit against [Lyda] for breach of contract, among other causes of action” if Lyda failed to comply

with its request for payment. Lyda refused to remit payment to Blue Haven and Blue Haven

filed suit against Lyda on December 18, 2009 for breach of contract, quantum meruit, violations

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perry Homes v. Cull
258 S.W.3d 580 (Texas Supreme Court, 2008)
In Re Citigroup Global Markets, Inc.
258 S.W.3d 623 (Texas Supreme Court, 2008)
Pennzoil Company v. Arnold Oil Company
30 S.W.3d 494 (Court of Appeals of Texas, 2000)
EZ Pawn Corp. v. Mancias
934 S.W.2d 87 (Texas Supreme Court, 1996)
Dallas Cardiology Associates, P.A. v. Mallick
978 S.W.2d 209 (Court of Appeals of Texas, 1998)
PER Group, L.P. v. Dava Oncology, L.P.
294 S.W.3d 378 (Court of Appeals of Texas, 2009)
In Re Bruce Terminix Co.
988 S.W.2d 702 (Texas Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Lyda Swinerton Builders, Inc. v. Pools by Blue Haven, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyda-swinerton-builders-inc-v-pools-by-blue-haven-inc-texapp-2011.