Lyda Constructors, Inc. v. Butler Manufacturing Co.

103 S.W.3d 632, 50 U.C.C. Rep. Serv. 2d (West) 100, 2003 Tex. App. LEXIS 2112, 2003 WL 1090581
CourtCourt of Appeals of Texas
DecidedMarch 12, 2003
Docket04-01-00284-CV
StatusPublished
Cited by12 cases

This text of 103 S.W.3d 632 (Lyda Constructors, Inc. v. Butler Manufacturing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyda Constructors, Inc. v. Butler Manufacturing Co., 103 S.W.3d 632, 50 U.C.C. Rep. Serv. 2d (West) 100, 2003 Tex. App. LEXIS 2112, 2003 WL 1090581 (Tex. Ct. App. 2003).

Opinion

ON MOTION FOR REHEARING

Opinion by

PAUL W. GREEN, Justice.

We grant Butler Manufacturing Company’s motion for rehearing. The opinion and judgment issued June 26, 2002 are withdrawn and the following is substituted.

This is a dispute between a general contractor, Lyda Constructors, Inc., and a supplier, Butler Manufacturing Company, over project delay damages allegedly caused by Butler. We affirm the judgment of the trial court in part, and reverse and remand in part.

BACKGROUND

In 1996, Lyda contracted with the Northside Independent School District to build Sandra Day O’Connor High School in Helotes, Texas. In December 1996, Lyda entered a subcontract with SAC Building Corporation to construct metal buildings for the project. This subcontract held SAC “liable for any damage in connection with its work.” SAC eventually contracted with Butler to supply the necessary materials.

On January 22, 1997, representatives from Lyda, SAC, and Butler met to establish a time line and estimate supply delivery dates. From this meeting, a chart (“the matrix”) was drafted reflecting the *635 dates discussed. Butler and SAC entered a supply contract, providing Butler’s liability was limited to repair and replacement of products. The contract also absolved Butler of liability for any consequential delay damages. In March 1997, SAC was dissolved due to financial difficulties, and SAC’s owners formed a new entity, ASC Metal Building Systems. ASC asked Butler to transfer the supply contract to it and asked Lyda to permit ASC to assume SAC’s subcontract on the project.

Meanwhile, in April 1997, Lyda prepared a project schedule. Lyda claims the project schedule was based on the dates in the matrix; however, at the time the project schedule was created, Butler had already failed to comply with some of the delivery dates reflected in the matrix. In mid-April 1997, Butler agreed to continue its supply contract with ASC, and in late April 1997, Lyda signed a new subcontract with ASC, which related back to the original subcontract with SAC. Neither the matrix nor the project schedule was incorporated into the subcontract or supply contract.

During Butler’s negotiations with ASC over its entry into the project, Butler expressed concern over ASC’s ability to pay for the supplies delivered. Butler asked for a joint cheek agreement with Lyda so that payments to ASC for supplies delivered by Butler would be in checks payable jointly to ASC and Butler. Lyda claims Butler refused to deliver any more supplies until this joint check agreement was entered. Butler drafted a proposed joint check agreement, but it was rejected by Lyda because it did not bind Butler to the terms of the ASC/Lyda subcontract. On June 3, 1997, Butler requested a copy of the ASC/Lyda subcontract because, according to a representative from ASC, Butler wanted to know what terms it was being asked to abide by. A day later, Lyda sent Butler a letter stating that Lyda would issue checks jointly to ASC and Butler and that:

Butler Manufacturing is a material supplier and will abide by contract between ASC Metal Building Company and LYDA Constructors, Inc., to the extent of being a material supplier, but will not accept the conditions of the balance of the contract involving other suppliers, labor, etc.

Shortly after receiving the letter, Butler delivered a shipment of supplies. Butler’s delivery invoice contained the same terms and conditions it had used in its contract with ASC that limited Butler’s liability to repair and replacement.

When ASC failed to pay Butler for the delivered supplies, Butler filed suit against Lyda’s surety, seeking the $209,288.74 owed by ASC. Lyda intervened, alleging Butler caused Lyda delay damages by failing to deliver the supplies timely and failing to deliver supplies complying with the project’s design specifications. The trial court granted summary judgment to Butler on all of Lyda’s claims. On appeal, Lyda challenges the summary judgment on its claims of breach of contract, breach of express warranty, fraud, and negligent misrepresentation against Butler.

STANDARD OF REVIEW

We review a trial court’s grant of summary judgment afe novo. Sasser v. Dantex Oil & Gas, Inc., 906 S.W.2d 599, 602 (Tex.App.-San Antonio 1995, writ denied). We uphold a summary judgment only if the record establishes there is no genuine issue of material fact and that the movant is entitled to judgment as a matter of law. Tex.R. Civ. P. 166a(e); Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548-49 (Tex.1985). In determining whether there is a disputed issue of material fact precluding summary judgment, evidence *636 favorable to the nonmovant is taken as true and every reasonable inference is indulged in favor of the nonmovant. Nixon, 690 S.W.2d at 548-49. When, as here, the order granting summary judgment fails to specify the grounds, we affirm on any meritorious ground advanced in the motion. Carr v. Brasher, 776 S.W.2d 567, 569 (Tex.1989).

Discussion

Lyda contends the June 4, 1997 joint check letter it sent to Butler, in addition to the parties’ course of dealings, establishes a contract between Lyda and Butler. Lyda also contends the representations made by Butler regarding delivery dates, as reflected in the matrix, constitute express warranties, which are not governed by the limiting language of the Butler/ASC supply contract. In response, Butler reasserts its summary judgment grounds, arguing: (1) there is no evidence of an enforceable contract between itself and Lyda; (2) there can be no express warranty absent privity; and (3) the terms of the supply contract immunize Butler from liability for delay damages.

• Lyda’s Breach of Contract Claim

Initially, we must determine whether there is evidence of an enforceable contract between Lyda and Butler. In making this determination, we look to the parties’ communications and the acts and circumstances surrounding those communications. Harris v. Balderas, 27 S.W.3d 71, 77 (Tex.App.-San Antonio 2000, pet. denied). When ASC was substituted as the new subcontractor in place of SAC, Butler sent Lyda a proposed joint check agreement that was rejected because it contained no provision obligating Butler to abide by the Lyda/ASC subcontract. Lyda countered with the June 4, 1997 letter to Butler wherein it agreed to pay Butler and ASC by joint check, but it included a provision that Butler would abide by the Lyda/ASC subcontract to the extent of being a material supplier. There were no other communications between Butler and Lyda. Butler never responded to Lyda’s letter, but shortly thereafter delivered supplies to the project pursuant to its contract with ASC, and its delivery invoice purported to limit its liability to repairs and replacement.

Lyda argues that its June 4 joint check letter constituted an offer, which was accepted by Butler by virtue of its performance,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luig v. North Bay Enterprises, Inc.
55 F. Supp. 3d 942 (N.D. Texas, 2014)
Beauty Manufacturing Solutions Corp. v. Ashland, Inc.
848 F. Supp. 2d 663 (N.D. Texas, 2012)
Berge Helene Ltd. v. GE Oil & Gas, Inc.
830 F. Supp. 2d 235 (S.D. Texas, 2011)
Sterling Chemicals, Inc. v. Texaco Inc.
259 S.W.3d 793 (Court of Appeals of Texas, 2007)
Kelly v. Gaines
181 S.W.3d 394 (Court of Appeals of Texas, 2005)
Roger Kelly v. Russell Gaines
Court of Appeals of Texas, 2005
William A. McIntosh v. State
Court of Appeals of Texas, 2002
Michael T. Castaldo v. State
Court of Appeals of Texas, 2000

Cite This Page — Counsel Stack

Bluebook (online)
103 S.W.3d 632, 50 U.C.C. Rep. Serv. 2d (West) 100, 2003 Tex. App. LEXIS 2112, 2003 WL 1090581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyda-constructors-inc-v-butler-manufacturing-co-texapp-2003.