LW Johnson & Assoc., Inc. v. RIVERS CONST. CO.

532 So. 2d 618, 1988 WL 102991
CourtSupreme Court of Alabama
DecidedSeptember 2, 1988
Docket85-1147
StatusPublished
Cited by14 cases

This text of 532 So. 2d 618 (LW Johnson & Assoc., Inc. v. RIVERS CONST. CO.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LW Johnson & Assoc., Inc. v. RIVERS CONST. CO., 532 So. 2d 618, 1988 WL 102991 (Ala. 1988).

Opinion

This appeal arises from a fraud and breach of contract suit filed by Rivers Construction Company, a corporation, and Allen Foster against L.W. Johnson and Associates, Inc. ("Johnson Associates"), and L.W. Johnson. Johnson Associates contracted with Rivers Construction for pipeline work in connection with gas wells developed by Johnson Associates. After Rivers Construction completed substantially *Page 619 all of the work, Johnson Associates refused to pay. The jury awarded $165,000 compensatory and $500,000 punitive damages.

Johnson Associates and Johnson raise the following issues:

"I. Whether the trial court erred to reversal by failing to grant defendants' motions for mistrial and/or post-trial motion for a new trial, raising as an issue the [alleged] misconduct and improper jury argument of plaintiffs' counsel.

"II. Whether the trial court erred to reversal by failing to grant defendants' post-trial motion for a new trial raising as an issue the [alleged] excessiveness of the punitive damages awarded by the jury.

"III. Whether the trial court abused its discretion by failing to grant to defendants a continuance of the trial.

"IV. Whether the trial court erred to reversal by failing to grant defendants' motion for a directed verdict and/or their post-trial motion for JNOV with respect to the claims of Allen Foster, individually; and by failing to grant defendants' post-trial motion for a new trial with respect to the claims of Rivers Construction Company, raising as an issue the [alleged] confusion caused by the submission of claims by both plaintiffs to the jury."

Defendant L.W. Johnson is the principal shareholder and chairman of the board of defendant L.W. Johnson and Associates, Inc. Plaintiff Allen Foster is the president and sole shareholder of plaintiff Rivers Construction Company, a Mississippi corporation. On or about March 15, 1985, Johnson telephoned Foster to discuss pipeline work for gas wells Johnson Associates was developing in the vicinity of Vina, Alabama. A few days later, Johnson and several employees of Johnson Associates met Foster in Tupelo, Mississippi, and drove to Vina to look at the wells and discuss the work. Johnson wrote a document headed "Check list — Pipeline," dated March 21, 1985, and describing the work to be done.

The parties apparently agreed to enter into a contract for the price of $115,000, although no written contract appears in the record. Johnson testified that that price included a $35,000 bonus because Rivers Construction could begin work immediately and could assist in financing by buying materials on its own credit. Foster testified, on the other hand, that the contract price did not include a bonus, but that Johnson promised a bonus of a 5% interest in a four-well drilling program, known as the Pilot Hill Program No. 5, if Rivers Construction completed the work by April 15.

On March 22, Johnson Associates, by Johnson as its president, executed a mortgage of its interest in the Pilot Hill Program No. 5 to Rivers Construction, "in consideration of the sum of $115,000 hereby acknowledged to have been paid," and as security for a promissory note in that amount from Johnson Associates to Rivers Construction on June 22, 1985. Johnson testified that Foster requested this mortgage so that Rivers Construction could use it as security for loans to buy materials. Foster, however, testified that he did not need the mortgage as security to obtain credit, but rather that he requested it as security for payment of Johnson Associates' obligation under the contract. He testified that Johnson represented to him that Johnson Associates held at least a 20% interest in the Pilot Hill Program No. 5.

That representation is a principal basis of the fraud action: Foster testified that he moved his crew to Vina and began work in reliance on Johnson's assurances that the mortgage represented at least a 20% interest in the Pilot Hill Program No. 5. In deposition and at trial, Johnson testified that the mortgage conveyed only a three or four percent interest in the subject property.

Foster testified that, when he expressed concern to Johnson that Rivers Construction was not qualified to do business in Alabama, Johnson reassured him, saying that if any problem arose, Johnson Associates could put Foster on its payroll. *Page 620 Johnson denied having made any such statement. Foster attempted to have Rivers Construction qualified to do business in Alabama; however, he paid the tax required by Ala. Code 1975, §40-14-1, but did not apply with the secretary of state for a certificate of authority, as required by § 10-2A-226 et seq.1 These facts are pertinent to the second aspect of the fraud claim, i.e., that Johnson fraudulently induced Foster to enter into the contract by promising to pay for his work with no intention of doing so. Foster testified that when he asked to be paid, Johnson would not talk to him and that Johnson Associates' employees said that he was not being paid because Rivers Construction was not qualified to do business in Alabama.

Under the contracts, Johnson Associates was to provide certain large items of equipment, such as a compressor station, a dehydrator unit, and production units for the wells. None of this equipment was on the site when Foster and his crew arrived. Foster testified that six production units arrived about three weeks later, that the dehydrator arrived some time in April, and that the compressor did not arrive until May. Johnson asked Foster to use a certain supplier for pipe and other materials, and Foster initially did so, but when he experienced delays in receiving materials he began ordering from his usual supplier. Thus, through no fault on its part, Rivers Construction was unable to meet the April 15 deadline.

Johnson Associates had Rivers Construction do additional work while its crew was on the job site, including laying about 7000 feet of pipe. Foster obtained pipe for another additional pipeline, but was ordered off the job site before laying it. Johnson Associates hired another contractor to lay this pipe, even though Foster told the Johnson Associates personnel not to use the pipe. The complaint included a count for conversion of this pipe, but that count was not submitted to the jury.

On May 25, an employee of Johnson Associates wrote and signed the following on a paper and gave it to Foster: "Informed Rivers Construction to stop work on drip legs at 12 noon this date as per instruction of Mr. L.W. Johnson." The pipeline included three "drip legs" that leaked when the line was pressurized. Rivers Construction replaced two of them with straight sections of pipe, and Johnson Associates later had the third one replaced. The evidence tended to show that the replacement of the drip legs was an adequate, if not preferable, substitution. The highest estimate of any loss caused by any failure of Rivers Construction to perform under the contract came from Johnson himself, who testified that these and all other alleged deficiencies in Rivers Construction's performance took $15,000 to $20,000 to correct. Although defendants made some attempt to show that they did not pay Rivers Construction because its work was not suitable, Foster testified that he was never told that his work was unsuitable.

Foster testified that after he was ordered off the work site, he tried to call Johnson at his business office in Mobile, but Johnson would not return his calls. He testified that when he talked to John Causey, vice president of Johnson Associates, Causey told him that he would not be paid "Because I wasn't an Alabama licensed contractor." Causey denied having made that statement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bennett v. Brewer
682 So. 2d 448 (Supreme Court of Alabama, 1996)
Finkbohner v. Principal Mutual Life Insurance Co.
682 So. 2d 409 (Supreme Court of Alabama, 1996)
Ex Parte Finkbohner
682 So. 2d 409 (Supreme Court of Alabama, 1996)
Rowland v. Bondy's Ford, Inc.
669 So. 2d 125 (Supreme Court of Alabama, 1995)
Ex Parte Rowland
669 So. 2d 125 (Supreme Court of Alabama, 1995)
Williston v. Ard
611 So. 2d 274 (Supreme Court of Alabama, 1992)
Empire Gas, Inc. of Belle Mina v. Cartwright
595 So. 2d 1348 (Supreme Court of Alabama, 1992)
Thomas v. Southeast Alabama Sickle Cell Ass'n
581 So. 2d 845 (Supreme Court of Alabama, 1991)
Harris v. M & S TOYOTA, INC.
575 So. 2d 74 (Supreme Court of Alabama, 1991)
HealthAmerica v. Menton
551 So. 2d 235 (Supreme Court of Alabama, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
532 So. 2d 618, 1988 WL 102991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lw-johnson-assoc-inc-v-rivers-const-co-ala-1988.