Lutz Co. v. United States

76 Ct. Cl. 405, 1932 U.S. Ct. Cl. LEXIS 266, 1932 WL 2098
CourtUnited States Court of Claims
DecidedDecember 5, 1932
DocketNo. C-691
StatusPublished
Cited by1 cases

This text of 76 Ct. Cl. 405 (Lutz Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lutz Co. v. United States, 76 Ct. Cl. 405, 1932 U.S. Ct. Cl. LEXIS 266, 1932 WL 2098 (cc 1932).

Opinion

Booth, Chief Justice,

delivered the opinion of the court: The plaintiff, a Pennsylvania corporation, sues to recover a judgment for $72,086.52 alleged to be due it under the provisions of a war contract canceled by the Government in December 1918. Plaintiff’s principal contract with the Government bears the date June 10, 1918. This contract obligated plaintiff to rough machine 1,000 recoil forgings for 75 m/m field guns and deliver the same according to a fixed schedule of delivery, all to be completed and delivered by January 1, 1919. The plaintiff was to receive for this work $105.00 for each forging machined and the Government was to furnish the rough forgings in sufficient numbers to enable the plaintiff to comply with its contract.

Prior to the execution of the contract the plaintiff had entered into two contracts with the French Government to machine 2,020 rough forgings, the French Government agreeing to furnish a sufficient number of forgings to enable plaintiff to do so, the same to be furnished plaintiff by the Pollack Steel Company. In order to supply the French Government with the forgings exacted under its contract [412]*412plaintiff had enlarged and equipped its plant to the point necessary to do so. Plaintiff’s equipment and machinery was, as the record discloses, amply sufficient and adequate to enable it to meet the terms and provisions of its contracts, with the French Government.

On June 10, 1918, and prior to the execution of the contract in suit signed on that date, it was known by both parties to the same that the plaintiff, in order to supply the Government with the number of forgings required, did not possess, adequate or sufficient equipment and machinery to do so. While the subject matter of the two sets of contracts was similar, the work required to be done on the forgings to be machined was not in all respects similar. This was due to-, the fact that the rough forgings to be furnished by the Government were to be supplied by the Carbon Steel Company and under the French contracts by the Pollack Steel Company, and a difference in contour and make-up obtained,, requiring the application of different types of machinery to some extent.

The plaintiff expended for additional equipment essential to the performance of its principal contract with the defendant the sum of $44,389.07 (finding V), and this sum represents the findings of the court as to this first item in suit. The sum stated has been arrived at by allowing only such items of claim as were authorized by the contract or officials with authority to incur the expense claimed, and it represents, in our opinion, the total amount which may be legally allowable under the provisions of the contract.

On July 27, 1918, plaintiff and defendant entered into a supplemental contract by the terms of which the plaintiff' was to purchase and install additional equipment for its plant in order to increase its output, said equipment and installation of the same to cost not to exceed $56,648.00, and the Government agreed to pay for it, all of the equipment so purchased to be and remain the property of the Government, to be removed by it within a year after the performance of the contract was completed. The plaintiff purchased and installed under this contract the additional equipment authorized, and expended therefor the sum of $56,520.41, [413]*413and the Government reimbursed plaintiff to the extent of $51,682.54, leaving a conceded balance due the plaintiff of $4,837.87 upon this item, which balance is included in the total sum mentioned in finding V.

It is proven that the labor cost expended by the plaintiff in the installation of said equipment averaged the plaintiff the rate of $2.50 per hour. It is also proven that a Government official or officials in charge of production agreed to pay plaintiff this increased cost of labor, which could not be obtained at a less rate, but the authority of the officials so to do is not established and we cannot allow the item. Soon after the execution of the supplemental contract a conflict arose between the United States Government and the French Government. The recoil forgings were urgently needed in the prosecution of the war, and inasmuch as the Government had taken over the control of the supply of rough forgings and diverted from plaintiff’s plant forgings from the Pollack Steel Company intended for plaintiff’s use in performing its contracts with France, an amicable arrangement was imperative between the Governments of France and the United States.

This arrangement was brought about by duly authorized changes and orders from the Ordnance Department and the plaintiff, wherein it was agreed that plaintiff, irrespective of the source of supply, should machine all rough forgings furnished it and apply the first ten machined upon the French contract and all additional ones up to ten per day upon its contract with the Government. It is not denied that the Government failed to furnish the plaintiff a sufficient number of rough forgings to machine more than ten per day, which were furnished to and were to be paid for by the French Government. No forgings were ever completed for the Government, and none could have been, for plaintiff’s contracts were duly suspended on December 10, 1918, and no work thereafter performed. So far as the record discloses, the plaintiff performed its contracts to the extent possible, and could have performed the same in accord with their terms.

[414]*414Article V of tbe contract contained the following provision:

“ In the event of the cancellation of this contract, as in this article provided, the United States will inspect the completed articles or material then on hand and such as may be completed within thirty (30) days after such notice, and will pay to the contractor the price herein fixed for the articles or material accepted by and delivered to the United States. The United States will also pay to the contractor the cost of the component materials and parts then on hand in an amount not exceeding the requirements for the completion of this contract, which shall be in accordance with the specifications referred to in schedule 1 hereto attached, and also all costs theretofore expended and for which payment has not previously been made and all obligations incurred solely for the performance of this contract of which the contractor cannot be otherwise relieved. To the above may be added such sums as the Chief of Ordnance may deem necessary to fairly and justly compensate the contractor for work, labor, and service rendered under this contract.”

It is not contended by the defendant, as we read its brief and argument, that plaintiff is not entitled to recover under this article of the contract. The defense interposed, unless we have misconceived it, goes to what items and the amount thereof which should or should not be allowed as coming within the article, and the total amount due, in our opinion, is expressed in finding V.

The defendant in its analysis of the record segregates the expenditures made for equipment essential to perform the contracts into two divisions, and as to one, i.e., the contract of June 10, 1918, it is said the contractor did not incur the expense claimed for the purpose of performing that contract, and as to the supplemental contract the expenditure made has been repaid except the amount of $4,831.81. The record before us does not sustain the defense. The total amount expended by the plaintiff to perform the contract of June 10, 1918, was $30,218.95, exclusive of overhead and direct labor costs, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goltra v. United States
91 Ct. Cl. 42 (Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
76 Ct. Cl. 405, 1932 U.S. Ct. Cl. LEXIS 266, 1932 WL 2098, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lutz-co-v-united-states-cc-1932.