Lunning v. Land O'Lakes

303 N.W.2d 452, 1980 Minn. LEXIS 1653
CourtSupreme Court of Minnesota
DecidedDecember 26, 1980
Docket50568
StatusPublished
Cited by31 cases

This text of 303 N.W.2d 452 (Lunning v. Land O'Lakes) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lunning v. Land O'Lakes, 303 N.W.2d 452, 1980 Minn. LEXIS 1653 (Mich. 1980).

Opinion

*454 AMDAHL, Justice.

This is an appeal from an order of the district court, Third Judicial District, granting defendant judgment notwithstanding the verdict, or in the alternative, a new trial on the issue of liability on the ground that the evidence viewed most favorably to the plaintiff entitled defendant to judgment as a matter of law.

The issue is whether the evidence was sufficient to create a jury question as to the existence of either promissory or equitable estoppel and thus take an oral contract not performable within one year, out of the statute of frauds. Minn.Stat. § 513.06 (1978).

An examination of the evidence, in the light most favorable to the plaintiff, leads us to the conclusion that the evidence of promissory or equitable estoppel was not sufficient to create a jury question and the judgment of the district court is, therefore, affirmed.

Plaintiff, Wallace Lunning, began a business relationship with defendant, Land O’Lakes, in 1960. Plaintiff worked for the defendant as the owner-operator of a truck used in hauling turkeys. In 1967, plaintiff and defendant entered into a written contract granting plaintiff exclusive rights to transport live turkeys to defendant’s plant, located in Albert Lea, Minnesota. Pursuant to the terms of the contract, defendant compensated plaintiff at a rate based on the weight of the turkeys when delivered. If a truck was mistakenly dispatched to a farm where there were no turkeys to pick up, defendant compensated plaintiff at a rate based on mileage. In addition, defendant paid plaintiff an hourly wage for time spent repairing “batteries” — coops used in transporting live turkeys. This latter agreement, however, was not contained in the written contract.

The parties thereafter entered into a series of contracts, some for two years, some for three. The contracts were, except for rate changes, substantially identical. Plaintiff and defendant followed a regular procedure for putting their agreements into writing. First, the parties would negotiate an agreement; in particular, they would agree on the new rates. Next, the defendant would request a contract from its legal department in Minneapolis. The legal department would forward to defendant a prepared form that, but for the blanks left for the new rates, the plant location and the signatures of the parties, expressed all the terms that had been agreed upon by the parties. One contract term provided that either party could terminate the contract for cause, upon thirty days written notice to the opposing party. Though the record shows no direct evidence on this point, it appears that the parties did not renegotiate the terms of their agreements once the defendant had requested the prepared form.

One such contract was in force during the period from March 1974 to March 1976. During this time the events occurred which precipitated this law suit.

On September 15, 1975, the plaintiff sent the following letter to the defendant:

This letter is advising you of Termination of present contract between Land O’Lakes, Inc., and myself.
Paragraph No. 1 Term.
If nothing can be worked out our last day will be Friday October 17, 1975.
Sincerely,
Wallace E. Lunning

While plaintiff’s letter did not specify causes for termination, he testified on direct examination that health problems were affecting his ability to carry out the contract and that the same problem made it necessary that he employ a manager at additional expense and that the price of diesel fuel was skyrocketing. He additionally testified:

I was going to get away from the turkey haul because it is a lot of stress and strain on a person. You’re on duty 24 hours a day. I was going to put my trucking business into more grain business, more reaping business, and machinery.

Plaintiff’s letter caused extreme concern to defendant because the fall months are the busiest of the year for the turkey busi *455 ness. Mr. Barnes, the Production and Procurement Manager of the Albert Lea turkey division, testified at trial that he feared that if plaintiff went through with the termination, another transporter of turkeys could not be found to replace plaintiff; this would force a shut down of the plant and, with that, a layoff of approximately 350 employees. In the hope of forestalling a termination by plaintiff, defendant arranged meetings with him to discuss the September 15th letter.

The parties met twice, once on October 2, 1975, and once on October 16, 1975. There is dispute as to the parties present and the statements made at these meetings. However, there is little dispute over the substance of the negotiations. At the first meeting they went through the contract paragraph by paragraph and all agree that at one of the meetings the plaintiff explained that he had health problems and, as a result, wanted to shift some responsibilities to an assistant, Larry Hensche. Plaintiff also informed defendant that he had ordered some new trailers which were two feet longer than the old trailers and defendant stated they would add length to their turkey coops so they would fit the new trailers. 1 The parties also agree that, at one point, defendant asked the plaintiff what would happen if no contract was made. Plaintiff replied “I’ll never leave you high and dry.” While the plaintiff and Hensche testified that plaintiff made that statement in a businesslike and cordial manner, the defendant’s evidence was to the contrary. Both witnesses for defendant testified that when plaintiff made this statement, his tone was sarcastic and he had a smirk on his face. In defendant’s version, the conversation continued. Defendant then asked “What the hell are we supposed to do now? You got us over a barrel. What are we going to do if we don’t have a contract by the 17th of October?” Plaintiff’s response was “You got my letter.”

Plaintiff made demands at the first meeting for an 8 percent increase in the rates and/or a fuel escalator clause, and for an increase in coop repair rates. At the second meeting, defendant counter-proposed a 5½ percent increase in the rates and a $3.00 per hour increase in coop repair rates. The plaintiff accepted the counter-proposal. Defendant then stated that it would request a form contract for the parties’ signatures from the Minneapolis legal department. All parties agree that a new contract was formed on October 16, 1975, and that after that date the written contract was “dead.” Plaintiff testified “We were agreeable on everything on the 16th of October.” The parties thereafter operated under the oral contract, defendant paying plaintiff the higher rates.

A few days after the October 16th meeting, plaintiff met with his attorney to discuss changing the terms of the oral contract. The plaintiff did not notify defendant of this meeting.

Plaintiff and Hensche testified that they frequently questioned defendant about the whereabouts of the contract. They were repeatedly told “It’s coming.” On December 19,1975, the contract did come from the Minneapolis legal department; it was the standard form contract the parties had been using for years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moyer v. Lasher Construction, Inc.
Idaho Supreme Court, 2024
Cardiovascular Systems, Inc. v. Cardio Flow, Inc.
37 F.4th 1357 (Eighth Circuit, 2022)
SN4, LLC v. Anchor Bank, FSB
848 N.W.2d 559 (Court of Appeals of Minnesota, 2014)
Stumm v. BAC Home Loans Servicing, LP
914 F. Supp. 2d 1009 (D. Minnesota, 2012)
Labrant v. Mortgage Electronic Registration Systems, Inc.
870 F. Supp. 2d 671 (D. Minnesota, 2012)
Bohnhoff v. Wells Fargo Bank, N.A.
853 F. Supp. 2d 849 (D. Minnesota, 2012)
Best Buy Stores, L.P. v. Developers Diversified Realty Corp.
636 F. Supp. 2d 869 (D. Minnesota, 2009)
Glacial Plains Cooperative v. Lindgren
759 N.W.2d 661 (Court of Appeals of Minnesota, 2009)
WINTHROP RESOURCES CORP. v. Sabert Corp.
567 F. Supp. 2d 1084 (D. Minnesota, 2008)
Brekke v. THM Biomedical, Inc.
683 N.W.2d 771 (Supreme Court of Minnesota, 2004)
Heidi Ott A.G. v. Target Corp.
153 F. Supp. 2d 1055 (D. Minnesota, 2001)
Rhee v. Golden Home Builders, Inc.
617 N.W.2d 618 (Court of Appeals of Minnesota, 2000)
Sieve v. Rosar
613 N.W.2d 789 (Court of Appeals of Minnesota, 2000)
Marriage of Gully v. Gully
599 N.W.2d 814 (Supreme Court of Minnesota, 1999)
CONDEMNATION BY HOUS. & REDEV. v. Suh
553 N.W.2d 115 (Court of Appeals of Minnesota, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
303 N.W.2d 452, 1980 Minn. LEXIS 1653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lunning-v-land-olakes-minn-1980.